QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Davis & Ors v Queensland Building and Construction Commission [2020] QCAT 189
PARTIES: In GAR139-18:
GREGORY RENTOUL DAVIS
(first applicant)
ROBYN KAY CURHAM
(second applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (respondent)
In GAR144-18:
BODY CORPORATE FOR 24-26 QUERRIN ST COMMUNITY TITLES SCHEME
(applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION
(respondent)
APPLICATION NO/S:
GAR139-18; GAR144-18
MATTER TYPE:
General administrative review matters
DELIVERED ON:
26 May 2020
HEARING DATE:
On the papers
HEARD AT:
Brisbane
DECISION OF:
Member Howe
ORDERS: 1. The answer to the question raised in issue 1 is no.
2. The answer to the question raised in issue 2 is no.
CATCHWORDS: PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – whether the statutory time limit for the Commission to issue a direction to rectify defective building work had expired – whether the statutory time limit for the Commission to issue a direction to rectify defective building work was extended - whether a new statutory time limit for the Commission to issue a direction to rectify defective building work arose in circumstances where remedial work utilised different rectification methods - where the applicants made complaints about building work outside the statutory time limit – where the builder had returned and performed rectification work before that and within the statutory time limit voluntarily – where the work done by the builder when he returned was claimed to be defective
Queensland Building and Construction Commission Act 1991 (Qld), s 72A(4)
Sadd, S v QBSA [2007] QCCTB 45
Stephens v QBCC [2018] QCAT 281
REPRESENTATION:
Applicants:
P J Hick, Active Law
Respondent:
N Thirumoorthi, in house legal
APPEARANCES:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
An eight townhouse complex was constructed by a builder at Yeronga in about June 2009. The applicants (“the owners”) in matter GAR139-18 purchased one of the units (Lot 5). The applicant in matter GAR 144–18 is the body corporate for the complex (“the body corporate”).
A certificate of classification for the building was issued on 10 July 2009.
Water entry into the ground floor rooms at the rear of the complex through the rear retaining wall, which also formed the exterior wall to a living area in Lot 5, was first noticed in December 2014 or January 2015.
According to the applicants, over the period January 2015 to January 2016 the builder returned and carried out work on the retaining wall and in some units including Lot 5 with the object of preventing water penetration through the retaining wall. The work involved removing floor coverings and internal wall framing and lining from the ground floor rooms, the application of a waterproof membrane to the inside face of the retaining wall and replacing internal wall framing and lining and…
Keep reading for free
Create a free CaseChat account to read Davis & Ors v Queensland Building and Construction Commissio... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] QCAT 189
- Decision Date
CaseChat Overview and Summary
The central legal issues before the court were whether the statutory time limit for the Commission to issue a direction to rectify defective building work had expired, whether the time limit was extended, and whether a new time limit arose when the builder used different rectification methods. Additionally, the court needed to determine if the applicants' complaints were valid despite being made outside the statutory time limit, and if the builder's voluntary rectification work within the statutory time limit was defective.
The court ruled that the statutory time limit for the Commission to issue a direction to rectify defective building work had not expired and that it was not extended. The court also held that a new statutory time limit did not arise when the builder used different rectification methods. The applicants' complaints were deemed invalid as they were made outside the statutory time limit. Furthermore, the court found that the builder's voluntary rectification work within the statutory time limit was not defective.
The court's final orders were that the statutory time limit for the Commission to issue a direction to rectify defective building work had not expired, and that the time limit was not extended. Additionally, a new time limit did not arise when the builder used different rectification methods. The applicants' complaints were invalid as they were made outside the statutory time limit, and the builder's voluntary rectification work within the statutory time limit was not defective.
Orders
Orders of the court
1. The answer to the question raised in issue 1 is no.
2. The answer to the question raised in issue 2 is no.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.