SUPREME COURT OF QUEENSLAND
CITATION:
Barry & Anor v Queensland Building and Construction Commission [2015] QSC 50
PARTIES:
TERRENCE RALPH BARRY
(first applicant)
TERRY BARRY BUILDERS PTY LTD
ACN 115 050 998(second applicant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISION
(respondent)FILE NO:
SC No 915 of 2015
DIVISION:
Trial Division
PROCEEDING:
Application
DELIVERED ON:
13 March 2015
DELIVERED AT:
Brisbane
HEARING DATE:
4 March 2015
JUDGE:
Flanagan J
ORDER:
1. Application dismissed.
2. I will hear the parties as to costs.
CATCHWORDS:
PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – where the second applicant was contracted to construct an outdoor deck and extension to an existing deck – where the majority of building work was completed on 18 December 2007, further building work was completed on 21 May 2008 and the final inspection certificate of the building work was issued on 26 August 2008 – where a direction was issued by the respondent to the second applicant to rectify defective or incomplete building work on 22 August 2014 – where the direction was required to be given within 6 years and 3 months after the “building work to which the direction relates” was completed pursuant to s 72(8) of the Queensland Building Construction Commission Act 1991 (Qld) – whether a direction issued outside 6 years and 3 months is invalid – whether the relevant date for s 72(8) should be identified by reference to the completion date of the defective work identified in the direction or the completion date of the whole of the building work, including the issuing of a final inspection certificate
Queensland Building Construction Commission Act 1991 (Qld), s 72(1), s 72(2), s 72(8)
Guitar Buildings v Queensland Building Services Authority & Meznaric [2013] QCATA 260, distinguished
Lange v Queensland Building Services Authority [2012] 2 Qd R 457; [2011] QCA 58, citedO’Grady v Northern Queensland Co Limited (1990) 169 CLR 356, 374; [1990] HCA 16, cited
Project Blue Sky v Australian Broadcasting Authority (1998) 194 CLR 355; [1998] HCA 28, cited
Torea Pty Ltd v Queensland Building Services Authority [2013] QCAT 004, not followed
COUNSEL:
M T Labone for the applicants
T J Mitchell (sol) for the respondent
SOLICITORS:
BCCS Law for the applicants
CBP Lawyers for the respondent
By originating application, the first and second applicants seek a declaration that a Direction to Rectify and/or Complete Number 40384 (“the Direction”) is void.
The Direction was given by the respondent, Queensland Building and Construction Commission (“QBCC”), on 22 August 2014. The Direction was given to the second applicant, Terry Barry Builders Pty Ltd, of which the first applicant is a director.
The Direction relevantly provides:
“You are directed to rectify the following defective or incomplete building work within the Time Period for Completion.
1. The inspection found that a significant percentage of the timber joists to the newly constructed deck area are…
Keep reading for free
Create a free CaseChat account to read Barry v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QSC 50
- Decision Date
CaseChat Overview and Summary
The court had to interpret the term "building work" as defined in the QBCC Act, which includes contract administration such as arranging for certificates. The applicants contended that the term "building work" should be limited to the defective work identified in the direction, citing a decision from Torea Pty Ltd v Queensland Building Services Authority. However, the court rejected this interpretation, holding that the term "building work" carries its defined meaning in the Act, which encompasses not only the physical construction of the deck but also the administrative tasks such as arranging for certificates. Consequently, the court found that the building work was not completed until the final inspection certificate was issued on 26 August 2008, meaning the direction was given within the required timeframe.
The court concluded that the direction was valid, as the building work to which the direction related was completed on the issuing of the final inspection certificate on 26 August 2008. The applicants' application for declaratory relief was dismissed, and the originating application was otherwise dismissed. The court will hear the parties regarding costs.
Orders
Orders of the court
1. Application dismissed.
2. I will hear the parties as to costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The term “contract administration” in subsection (fa) of the definition of “building work” is also a defined term:[13]“contract administration, in relation to building work designed by a person, includes the following—(a) preparing tender documentation and calling and selecting tenders;(b) preparing, or helping the person’s clients with the preparation of, contracts;(c) preparing additional documentation for the person’s clients or building contractors;(d) arranging and conducting on-site meetings and inspections;(e) arranging progress payments;(f) arranging for certificates, including certificates from a local government, to be issued;(g) providing advice and help to the person’s clients including during the maintenance period allowed under a contract.”[13] Queensland Building and Construction Commission Act 1991 (Qld) sch 2. In the present case the respondent did not make any application, pursuant to s 72(8), to the tribunal for any extension of time. The question is when was the “building work” to which the Direction relates completed? The applicant, relying on a QCAT decision in Torea Pty Ltd v Queensland Building Services Authority,[14] submitted that the “building work to which the direction relates” should be identified by reference to the defective work identified in the Direction. I have set out the Direction above. The applicant’s submission would limit the “building work to which the direction relates” to “the timber joists to the newly constructed deck area”. The applicant relied on the following passage from Torea Pty Ltd v Queensland Building Services Authority:“[21]In my view it is not correct to determine the completion date on which all of the building work was completed. That is, it is not correct to have regard to dates of certification for a building or dates of practical completion for a building or dates of certification for fire requirements. To do so would be to ignore the words which qualify the building work as they are used in s 72(8) of the Act.”[14] [2013] QCAT 004. To the extent that the applicant relies on the decision in Torea Pty Ltd v Queensland Building Services Authority, I am of the view that the case was wrongly decided. As I have already observed, the term “building work” is a defined term in the QBCC Act. Section 32A of the Acts Interpretation Act 1954 (Qld) provides that definitions in or applicable to an Act apply except so far as the context or subject matter otherwise indicates or requires. The words “the building work to which the direction relates” does not indicate that “building work” is to have other than its defined meaning. The defined meaning of “building work” includes not just the physical construction of the deck but also arranging for a certificate to be issued. The legislature, had it intended to limit “the building work to which the direction relates” to the defective building work identified in the direction, could have used other terms such as “the building work referred to in the direction” or “the building work the direction requires to be rectified” rather than the broader term “the building work to which the direction relates”.