QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Dacro Constructions Qld Pty Ltd ATF Dacro Family Trust v Queensland Building Construction Commission [2022] QCAT 396
PARTIES: dacro constructions qld pty ltd as trustee for dacro family trust (applicant)
V
queensland building and construction commission (respondent)
APPLICATION NO/S:
GAR141-20 and GAR386-20
MATTER TYPE:
General administrative review matters
DELIVERED ON:
1 December 2022
HEARING DATE:
16 November 2022
HEARD AT:
Brisbane
DECISION OF:
Member Cranwell
ORDERS:
1. The direction to rectify is confirmed.
2. The scope of works is amended to remove the reference to ‘movement joints’, but is otherwise confirmed.
CATCHWORDS:
PROFESSIONS AND TRADES – BUILDERS – STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK – where decision made to issue a direction to rectify to the builder – where scope of works issued in respect of the direction to rectify – where the builder filed applications to review both decisions – whether fair to give a direction to rectify – whether direction to rectify issued within time – whether scope of works reasonable and necessary
Queensland Building and Construction Commission Act 1991 (Qld), s 71J, s 72, s 86C
Barry & Anor v Queensland Building and Construction Commission [2015] QSC 50
Briginshaw v Briginshaw (1938) 60 CLR 336
Jarvis v Queensland Building and Construction Commission [2014] QCAT 693
APPEARANCES & REPRESENTATION:
Applicant:
Self-represented
Respondent:
G Andrews
REASONS FOR DECISION
Dacro Constructions Qld Pty Ltd as trustee for Dacro Family Trust (‘Dacro’) entered into a contract to undertake renovation work on property owned by Tracey Lee Cunningham (‘the owner’) on or about 12 October 2011.
Building work commenced, but the parties subsequently fell into dispute. The owner commenced proceeding BDL284-14 in the Tribunal. On 17 April 2015, consent orders were made in the following terms:
1. Tracey Lee Cunningham pay to Dacro Constructions Qld Pty Ltd the sum of $35,000.00 as follows:
i. $10,000 by 1 May 2015
ii. $10,000 by 1 June 2015
iii. $15,000 on completion
2. Dacro Constructions Qld Pty Ltd will complete the outstanding works in accordance with the contract being: the western wall; garage door; disconnect existing garage; stair to rear of carport; and remove colonial bars, by 31 July 2015.
A ‘Form 21 – Final inspection certificate’ was issued on 15 April 2016, following an inspection of final stage items on 20 November 2015.
It is not in dispute that the owner has not paid the final instalment of $15,000.
Between 16 December 2019 and 19 December 2019, the Queensland Building and Construction Commission (‘QBCC’) exchanged emails with the owner. The QBCC has treated this as a complaint by the owner.
The QBCC issued a direction to rectify on 23 January 2020, with an amended direction to rectify being issued on 27 April 2020 following an internal review. The terms of the direction to rectify are as follows:
1. The cracking, delamination and dislodging of render applied to the western elevation external wall evidences a failure of the rendering system, which is unsatisfactory and/or…
Keep reading for free
Create a free CaseChat account to read Dacro Constructions Qld Pty Ltd ATF Dacro Family Trust v Que... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QCAT 396
- Decision Date
CaseChat Overview and Summary
The central legal issues were whether it was fair and reasonable to issue the direction to rectify, and whether the scope of works was reasonable and necessary. The court found that the direction to rectify was fair and reasonable, noting the significant safety risks posed by the defective work and the disproportionate cost of rectification compared to the outstanding payment. The time limit for issuing the direction was also found to be complied with. Regarding the scope of works, the court agreed with the QBCC's concession that the installation of movement joints was unnecessary. However, it upheld the requirement to replace the FC sheeting to address the water penetration issue, based on expert evidence supporting this action as necessary.
The court confirmed the direction to rectify, with the amendment that the scope of works should exclude the reference to movement joints. This decision ensures that the defective building work will be rectified in a manner that addresses the safety and integrity concerns identified by the QBCC, while also taking into account the financial implications for the builder.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi