Colagrande v D a Radic Pty Ltd trading as David Radic Prestige Homes

Link copied
Case Copied 61 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Colagrande & Anor v D A Radic Pty Ltd trading as David Radic Prestige Homes [2019] QCATA 176

PARTIES: CES COLAGRANDE AND REBECCA COLAGRANDE

(applicant\appellant)

v

D A RADIC PTY LTD TRADING AS DAVID RADIC PRESTIGE HOMES

(respondent)

APPLICATION NO/S:

APL081-18

ORIGINATING APPLICATION NO/S:

BDL118-16

MATTER TYPE:

Appeals

DELIVERED ON:

11 December 2019

HEARING DATE:

16 November 2018

HEARD AT:

Brisbane

DECISION OF:

Senior Member Brown
Member Olding

ORDERS:

1.   The appeal is allowed.

2.   The decision of the Tribunal made 12 March 2018 is set aside.

3.   Ces Colagrande and Rebecca Colagrande must pay D A Radic Pty Ltd trading as David Radic Prestige Homes SEVEN THOUSAND, TWO HUNDRED AND FIFTY DOLLARS ($7,250) within fourteen (14) days of the date of this decision.

4.   The parties must file and exchange written submissions in respect of the question of costs of the appeal within twenty-eight (28) days of the date of this decision.

CATCHWORDS:

APPEALS AND NEW TRIAL – APPEAL – GENERAL PRINCIPLES – WHEN APPEAL LIES – ERROR OF LAW – WHAT IS – GENERALLY – whether material before tribunal admitted of the conclusion that respondent had established ‘exceptional circumstances’ and ‘unreasonable hardship’

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – RECOVERY – where the parties entered into a building contract for construction of a luxury home – where disputes arose as to variations and as to the amount payable for the works – where builder non-compliant with requirements for contractual variations under the Domestic Building Contracts Act 2000 (Qld) – whether builder should be permitted to recover amounts for non-compliant variations – whether exceptional circumstances– whether unreasonable hardship

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – VARIATIONS – where builder non-compliant with requirements for contractual variations under the Domestic Building Contracts Act 2000 (Qld) – whether liquidated damages payable for delays in practical completion – whether builder made an application to adjust completion date under s 18(6) of the Domestic Building Contracts Act 2000 (Qld)

Domestic Building Contracts Act 1995 (Vic), s 38

Domestic Building Contracts Act 2000 (Qld) s 3, s 7, s 16, s 18, s 79, s 80, s 81, s 82, s 83, s 84, s 92, s 93, sch 2
Queensland Civil and Administrative Tribunal Act 2009 (Qld) s 142, s 147

Allaro Homes Cairns Pty Ltd v O’Reilly & Anor  [2012] QCA 286
Australian Broadcasting Tribunal v Bond (1990) 170 CLR 321
Better Homes Queensland Pty Ltd v O’Reilly [2012] QCATA 37
Cachia v Grech [2009] NSWCA 232
Collector of Customs v Agfa-Gevaert Ltd (1996) 186 CLR 389
Collector of Customs v Pressure Tankers Pty Ltd and Pozzolanic Enterprises Pty Ltd [1993] FCA 322
D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112
Ericson v Queensland Building Services Authority [2013] QCA 391
Glenwood Properties Pty Ltd v Delmoss Pty Ltd [1986] 2 Qd R 388

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Colagrande v D a Radic Pty Ltd trading as David Radic Presti... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] QCATA 176
Decision Date

CaseChat Overview and Summary

Colagrande v D a Radic Pty Ltd trading as David Radic Prestige Homes involved a dispute arising from a building contract for the construction of a luxury home. The primary issue before the court was whether the builder, David Radic, could recover amounts for non-compliant variations under the Domestic Building Contracts Act 2000 (Qld). Additionally, the court needed to determine whether the builder should be permitted to recover liquidated damages for delays in practical completion and whether there were exceptional circumstances or unreasonable hardship that should be taken into account.

The court found that the learned member had erred in law by approving the non-compliant variations without a contractual entitlement or an application by the builder in accordance with section 18(6)(b) of the DBC Act. The learned member had also erred in extending the completion date based on section 18(6)(b) of the Act. The court concluded that, without the adjustment for non-compliant variations, the completion date should have been 7 October 2015, and practical completion was achieved on 18 December 2015. The delay resulted in liquidated damages of $18,000.00, calculated based on calendar days rather than business days as per the contract terms.

The court allowed the appeal and set aside the Tribunal's decision. The applicants, Ces Colagrande and Rebecca Colagrande, were ordered to pay David Radic Pty Ltd trading as David Radic Prestige Homes $7,250 within fourteen days of the decision. The parties were also required to exchange written submissions regarding the costs of the appeal within twenty-eight days of the decision.

Orders

Orders of the court

1. The appeal is allowed.

2. The decision of the Tribunal made 12 March 2018 is set aside.

3. Ces Colagrande and Rebecca Colagrande must pay D A Radic Pty Ltd trading as David Radic Prestige Homes SEVEN THOUSAND, TWO HUNDRED AND FIFTY DOLLARS ($7,250) within fourteen (14) days of the date of this decision.

4. The parties must file and exchange written submissions in respect of the question of costs of the appeal within twenty-eight (28) days of the date of this decision.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

In the absence of an application by Radic pursuant to s 18(6)(b) of the Act, it was not open to the learned member to adjust the completion date. To the extent that the learned member relied upon s 18(6)(b) of the Act in finding that the date for practical completion was extended, there was an error in law. Conclusion We have found errors of law by the learned member. The orders sought by the applicants are to set aside the decision below and to substitute a decision in the following terms:(a)A declaration that the applicants are entitled to set off the amount of $13,000 against the final payment claimed by Radic being the liquidated damages pursuant to clause 19 of the contract; and(b)An order that the applicants pay to the respondents $12,250. At the hearing of the appeal, Counsel for the applicants submitted that the correct figure in respect of the liquidated damages calculation was $18,000.00 and that the final order sought was that Radic pay the applicants $7,250.00. The calculations were not disputed by Radic’s solicitor. If the determination of the questions of law decides the appeal entirely in the applicants’ favour, we may set aside the decision below and substitute our own decision. There is no cross appeal by Radic. We have concluded that it was not open to the learned member to approve the non-compliant variations. The learned member allowed $32,985.83 in respect of the non-compliant variations.[127] [127]D A Radic Pty Ltd t/as David Radic Prestige Homes v Colagrande & Ors [2018] QCAT 112, [145]. We have found that in the absence of a contractual entitlement to do so or an application by Radic in accordance with s 18(6)(b) of the DBC Act there was no basis to adjust the completion date. The learned member found that the date for practical completion pursuant to the contract was 22 July 2015.[128] The learned member adjusted the date to take into consideration the agreed variations. The additional time allowed by the learned member for the agreed variations was from 22 July 2015 until 7 October 2015. [128]Ibid, [215]. The finding by the learned member, that 55 additional days be permitted in respect of the agreed variations, and thus adjusting the date for practical completion to 7 October 2015 is not challenged. It is uncontentious that, in the absence of a finding that the date for practical completion was extended in respect of the non-compliant variations, the date for practical completion was 7 October 2015. It is also uncontentious that practical completion was achieved on 18 December 2015. The contract provided for the payment of liquidated damages at the rate of $250.00 per calendar day in the event the builder failed to achieve practical completion by the due date. The delay in achieving practical completion was 72 calendar days. Undertaking the required arithmetical exercise the calculation of liquidated damages is $18,000.00. The learned member calculated the relevant period from 7 October 2015 to 18 December 2015 as being 52 business days. However the contract provides for the payment of liquidated damages calculated by reference to calendar days not business days.

Ratio Decidendi

Legal Principle Established