| CITATION: | Mahmudov v Goncalves [2012] QCAT 629 |
| PARTIES: | Natalia Mahmudov (Applicant) |
| v | |
| Jose Goncalves t/as Z Build (Respondent) |
| APPLICATION NUMBER: | BDL287-11 / BDL333-11 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 12 October 2012 |
| HEARD AT: | Brisbane |
| DECISION OF: | Sandra G Deane, Member |
| DELIVERED ON: | 17 December 2012 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. Jose Goncalves t/as Z Build is to pay to Natalia Mahmudov the sum of $676.68 by 4:00pm on 21 January 2013. 2. Jose Goncalves t/as Z Build is to deliver up to Natalia Mahmudov by 4:00pm on 21 January 2013 certificates and durable termite label held by him in relation to the works undertaken at 45 Clough St, Mt Gravatt East including the originals of: (a) The form 16 certificate in relation to installation of a termite management system; (b) an installation certificate issued by (c) Certificate of waterproofing for upper deck; (d) Certificate for trusses. |
| CATCHWORDS: | DOMESTIC BUILDING DISPUTE – home owner purported to terminate – whether valid termination – amounts owing for incomplete or defective work – whether liquidated damages payable – whether practical completion achieved – whether other damages payable – delivery up of certificates – whether amounts are recoverable by builder where variations were not in writing – whether there were exceptional circumstances or the builder would suffer unreasonable hardship – whether recovery would be unfair to the owner Domestic Building Contracts Act 2003, ss 39, 79-84 Ownit Homes Pty Ltd v Bachelor [1983] 2 Qd R 124 Habachi and Anor v Harjrudin Turcinovic [2011] QCAT 309 Ross v Rangel [2004] QCCTB 98 Better Homes Queensland Pty Limited v O’Reilly & Anor [2012] QCATA 37 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Natalia Mahmudov (in person) |
| RESPONDENT: | Jose Goncalves (in person) |
REASONS FOR DECISION
Background
Mrs Mahmudov, home owner, commenced 2 applications arising out of work performed by Mr Goncalves, a builder, under a domestic building contract dated 24 August 2010[1] (the Contract). Mr Goncalves counterclaims for moneys owing for work performed as variations. The applications were heard together.
[1] Exhibit 1.
The Contract was in respect of additions to an existing house at 45 Clough Street, Mt Gravatt East.
Mrs Mahmudov purported to terminate the Contract on 26 July 2011. Mr Goncalves contends that Mrs Mahmudov was not entitled to terminate.
Mrs Mahmudov claimed the following:
a)Work paid for in the practical completion stage payment but not performed $2,900
b)Rectification of termite protection $2,700
c)Damages for late completion $7,920
d)Legal Costs $1,880
e)Installation of hot water $ 400
f)Waterproofing works $1,300
g)Water tank contractor costs $1,149
h)Delivery up of certificates under the Contract
i)Relief from payment of Mr Goncalves’ invoice for variations in the amount of $4,361.50
j)Filing fees $265.00 x 2 $ 530
Mr Goncalves seeks payment of his invoice relating to claimed variations in the sum of $4,361.50, interest in accordance with the Contract…
Continue reading Mahmudov v Goncalves
Sign in free to access the full text
- AGLC
- Mahmudov v Goncalves [2012] QCAT 629
- Case
- [2012] QCAT 629
- Decision Date
CaseChat Overview and Summary
The court found that Mrs. Mahmudov was entitled to terminate the contract as Mr. Goncalves had failed to perform his obligations and had not attempted to remedy any breaches within the specified period. It was also determined that Mrs. Mahmudov was not in breach for not paying for variations that were not documented in writing, as required by the Domestic Building Contracts Act 2003. The court ruled that Mr. Goncalves was not entitled to withhold certificates until he received payment for amounts owing under the contract. Mrs. Mahmudov was not entitled to damages for late completion, as she did not challenge the notice of practical completion within the required timeframe. Legal costs incurred due to Mr. Goncalves' breach were awarded to Mrs. Mahmudov, but costs for the proceedings were to be borne by the parties themselves. The court allowed partial recovery for variations not documented in writing, as required by the Domestic Building Contracts Act 2003, and disallowed interest due to insufficient evidence.
The final orders were that Mr. Goncalves was to pay Mrs. Mahmudov $676.68 by 4:00pm on 21 January 2013, and deliver up certificates and documents related to the works undertaken at 45 Clough St, Mt Gravatt East.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.