SUPREME COURT OF QUEENSLAND
CITATION:Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd (No 2) [2024] QSC 64
PARTIES: CIVIL MINING AND CONSTRUCTION PTY LTD
(plaintiff)
v
WIGGINS ISLAND COAL EXPORT TERMINAL PTY LTD
(defendant)
FILE NO: BS 6050 of 2013
DIVISION: Trial Division
PROCEEDING: Costs
ORIGINATING COURT:
Supreme Court at Brisbane
DELIVERED ON: 26 April 2024
DELIVERED AT: Brisbane
HEARING DATE: On the papers: written submissions 2 April 2024. JUDGE: Muir J
ORDER: It is ordered that:
1. WICET pay CMC’s costs of WICET’s application; and
2. CMC pay 90 per cent of WICET’s costs of CMC’s application.
CATCHWORDS: PROCEDURE – COSTS - whether costs should follow the event - assessing the event warranting an award of costs - whether proportion of costs should be awarded to the defendant
Uniform Civil Procedure Rules 1999 (Qld) r 681
Aklia Holdings Pty Ltd v The Carter Group Pty Ltd (in liq) (No 2) [2017] QSC 266
Alborn & Ors v Stephens & Ors [2010] QCA 58 Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd [2003] FCA 325
Bostik Australia Pty Ltd v Liddiard (No 2) [2009] NSWCA 304
Built Qld Pty Ltd v Pro-Invest Australian Hospitality Opportunity (ST) Pty Ltd [No 2] [2023] QCA 140 Commonwealth of Australia v Gretton [2008] NSWCA 117 Courtney v Chalfen [2021] QCA 25
Davis v Perry O'Brien Engineering Pty Ltd (No 2) [2023] QSC 281
Interchange Corporation Ltd (in liq) v Grosvenor Hill (Qld) Pty Ltd (No 3) [2003] 1 Qd R 26
James & Ors v Surf Road Nominees Pty Ltd & Ors (No 2)
Kosho Pty Ltd & Anor v Trilogy Funds Management Ltd, Trilogy Funds Management Ltd & Ors v Fujino (No
MacKinnon v Petersen, unreported judgment Supreme Court of New South Wales, Cole J, 10 April 1989
Mickelberg & Ors v The State of Western Australia & Ors
[2007] WASC 140 (S)
Oshlack v Richmond River Council [1998] HCA 11 Speets Investment Pty Ltd v Bencol Pty Ltd (No 2) [2021] QCA 39
Waterman v Gerling Australia Insurance Co Pty Ltd (No 2)
NSWSC 1111
Wollongong Coal Ltd v Gujarat NRE India Pty Ltd (No 2)
COUNSEL:Thomson Geer sols prepared costs submissions S Eggins for the defendant
SOLICITORS: Thomson Geer for the plaintiff
Corrs Chambers Westgarth for the defendant
Overview
On 8 March 2024, I published detailed Reasons following an earlier four day hearing of separate applications by CMC and WICET for a review of a costs assessor’s assessment of CMC’s costs in the substantive proceeding.1 Final Orders consequential upon my findings were made on 22 March 2024. The Final Orders increased the costs assessor’s certificate by $160,833.43, but otherwise, both applications for review were dismissed.2
My Reasons outlined my then preliminary view that (subject to there being other factors warranting another order being made) the appropriate order as to costs was that WICET pay 20 per cent of CMC’s costs of CMC’s…
Keep reading for free
Create a free CaseChat account to read Civil Mining & Construction Pty Ltd v Wiggins Island Coal Ex... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] QSC 64
- Decision Date
CaseChat Overview and Summary
The court considered the legal principles surrounding the allocation of costs in litigation. It examined whether the costs incurred by the parties should indeed follow the event, which generally means that the losing party should bear the costs of the successful party. The court also had to assess the event that warranted an award of costs, which involved determining the proportion of costs that should be awarded to the defendant. The court balanced the principles of fairness and the outcome of the proceedings in making its decision.
Upon reviewing the case, the court determined that costs should indeed follow the event, aligning with the general principle of awarding costs to the prevailing party. However, in this instance, the court found that a proportionate award was necessary. It was deemed appropriate to award 90 per cent of the defendant's costs to the plaintiff. This decision reflected the specific circumstances of the case and the outcomes of the applications made by the parties. The court’s ruling provided clarity on the allocation of costs, ensuring that both parties were fairly treated based on the events of the litigation.
The final orders of the court were that Wiggins Island Coal Export Terminal Pty Ltd was to pay Civil Mining & Construction Pty Ltd’s costs associated with its application, while Civil Mining & Construction Pty Ltd was to pay 90 per cent of Wiggins Island Coal Export Terminal Pty Ltd’s costs related to its application. This decision provided a clear and equitable resolution to the dispute over costs in the proceedings.
Orders
Orders of the court
It is ordered that:
1. WICET pay CMC’s costs of WICET’s application; and
2. CMC pay 90 per cent of WICET’s costs of CMC’s application.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi