JURISDICTION : DISTRICT COURT OF WESTERN AUSTRALIA
IN CIVIL
LOCATION: PERTH
CITATION: CHAPPLE & ANOR -v- CIS CONTRACTING PTY LTD & ANOR [2001] WADC 10
CORAM: DEANE DCJ
HEARD: 10, 14 MAY, 8-11 NOVEMBER 1999
DELIVERED : 29 JANUARY 2001
FILE NO/S: CIV 1451 of 1997
BETWEEN: RAYMOND WILLIAM CHAPPLE
JOAN NATASHA CHAPPLE
PlaintiffsAND
CIS CONTRACTING PTY LTD (ACN 070 228 563)
First DefendantABB POWER GENERATION LTD (ACN 000 038 237)
Second Defendant
Catchwords:
Building contract dispute - Fuller (F L Smith) contract with second defendant to construct electrostatic precipitator on building project - Second defendant contracts with first defendant to install thermal insulation and cladding to electrostatic precipitator - First defendant contracts with plaintiffs to supply, erect and dismantle scaffolding to permit insulation and cladding to be installed - Original scope of contract - When did contract begin and end - Whether plaintiffs entitled to charge weekly hire rates for material hired from commencement of hire until removal of final material from site - If so calculation of entitlement - Significant overrun in project schedule - Plaintiffs' claim against first defendant for recovery of money under contract or alternatively in quantum meruit - Plaintiffs' claim against second defendant in quantum meruit - First defendant counterclaims against plaintiffs for breach of implied terms of contract - Scott Schedule - Various items on Scott Schedule admitted by first defendant subject to counterclaim - Remaining items on Scott Schedule in dispute - Whether either or both defendants requested extra work of plaintiffs and if so the extent of such work - Whether plaintiffs entitled to a reasonable price for such work if it was carried out - The total value of the work done by the plaintiffs if such work was requested by either or both defendants
Legislation:
Nil
Result:
First defendant's counterclaim against plaintiffs dismissed in its entirety - Plaintiffs entitled to recover the further sum of $48,690.22 from the first defendant (having previously been paid the sum of $70,940 by the first defendant) - Plaintiffs entitled to recover the sum of $52,072 from the second defendant - Counsel to be heard in relation to question of interest
Representation:
Counsel:
Plaintiffs: Mr M J McPhee
First Defendant : Mr J R Ludlow
Second Defendant : Mr G I Brook
Solicitors:
Plaintiffs: Michell Sillar McPhee
First Defendant : McAuliffe Schwikkard
Second Defendant : Minter Ellison
Case(s) referred to in judgment(s):
Balfour Beatty Power Construction v Kidston Goldmines Ltd [1989] 2 Qd R 105
Brenner & Anor v First Artists Management Pty Ltd [1993] 2 VR 221
Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 346
Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221
Update Constructions Pty Ltd v Rozelle Childcare Centre Ltd (1990) 2 NSWLR 251
Case(s) also cited:
Anglopoulos & Anor v Sabatino & Anor, unreported; FCt SCt of SA; Library No BC9502270; September 1995
Parkinson (Sir Lindsay) v Transvaal Provincial Administration [1974] 4 SALR 506
Keep reading for free
Create a free CaseChat account to read Chapple v CIS Contracting Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2001] WADC 10
- Decision Date
CaseChat Overview and Summary
The court considered the arguments regarding the contract's commencement and termination, focusing on whether the contract began when the first defendant was engaged by the second defendant and ended when the scaffolding was dismantled. It also examined the plaintiffs' entitlement to weekly hire rates for materials hired, including the calculation of these rates. The court took into account the significant overrun in the project schedule and the plaintiffs' claims against both defendants for recovery of money under the contract or in quantum meruit. The first defendant's counterclaim for breach of implied terms of contract was analyzed in light of the Scott Schedule, which listed various items admitted by the first defendant subject to counterclaim, and those in dispute. The court needed to decide whether either or both defendants had requested extra work from the plaintiffs, and if so, the extent of such work and whether the plaintiffs were entitled to a reasonable price for it. The court also had to assess the total value of the work done by the plaintiffs if any extra work was requested by the defendants.
In its judgment, the court determined that the contract between the plaintiffs and the first defendant began when the first defendant was engaged by the second defendant and ended when the scaffolding was dismantled. It found that the plaintiffs were entitled to charge weekly hire rates for materials hired from the start of the hire until the removal of the final material from the site, but set out the method for calculating these rates. The court held that the plaintiffs were entitled to recover money from the first defendant under the contract, and from the second defendant in quantum meruit, based on the work done. The counterclaim by the first defendant for breach of implied terms of contract was dismissed, and the court found that the plaintiffs had not been requested to perform any additional work by either defendant. The final orders included a determination of the amount owed by the first defendant to the plaintiffs under the contract, and by the second defendant to the plaintiffs in quantum meruit, with the calculation of these amounts to be determined by the court.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi