Chapple v CIS Contracting Pty Ltd

Link copied
Case Copied 49 min read

JURISDICTION     :   DISTRICT COURT OF WESTERN AUSTRALIA

IN CIVIL

LOCATION:   PERTH

CITATION:   CHAPPLE & ANOR -v- CIS CONTRACTING PTY LTD & ANOR [2001] WADC 10

CORAM:   DEANE DCJ

HEARD:   10, 14 MAY, 8-11 NOVEMBER 1999

DELIVERED          :   29 JANUARY 2001

FILE NO/S:   CIV 1451 of 1997

BETWEEN:   RAYMOND WILLIAM CHAPPLE

JOAN NATASHA CHAPPLE
Plaintiffs

AND

CIS CONTRACTING PTY LTD (ACN 070 228 563)
First Defendant

ABB POWER GENERATION LTD (ACN 000 038 237)
Second Defendant

Catchwords:

Building contract dispute - Fuller (F L Smith) contract with second defendant to construct electrostatic precipitator on building project - Second defendant contracts with first defendant to install thermal insulation and cladding to electrostatic precipitator - First defendant contracts with plaintiffs to supply, erect and dismantle scaffolding to permit insulation and cladding to be installed - Original scope of contract - When did contract begin and end - Whether plaintiffs entitled to charge weekly hire rates for material hired from commencement of hire until removal of final material from site - If so calculation of entitlement - Significant overrun in project schedule - Plaintiffs' claim against first defendant for recovery of money under contract or alternatively in quantum meruit - Plaintiffs' claim against second defendant in quantum meruit - First defendant counterclaims against plaintiffs for breach of implied terms of contract - Scott Schedule - Various items on Scott Schedule admitted by first defendant subject to counterclaim - Remaining items on Scott Schedule in dispute - Whether either or both defendants requested extra work of plaintiffs and if so the extent of such work - Whether plaintiffs entitled to a reasonable price for such work if it was carried out - The total value of the work done by the plaintiffs if such work was requested by either or both defendants

Legislation:

Nil

Result:

First defendant's counterclaim against plaintiffs dismissed in its entirety - Plaintiffs entitled to recover the further sum of $48,690.22 from the first defendant (having previously been paid the sum of $70,940 by the first defendant) - Plaintiffs entitled to recover the sum of $52,072 from the second defendant - Counsel to be heard in relation to question of interest

Representation:

Counsel:

Plaintiffs:     Mr M J McPhee

First Defendant             :     Mr J R Ludlow

Second Defendant         :     Mr G I Brook

Solicitors:

Plaintiffs:     Michell Sillar McPhee

First Defendant             :     McAuliffe Schwikkard

Second Defendant         :     Minter Ellison

Case(s) referred to in judgment(s):

Balfour Beatty Power Construction v Kidston Goldmines Ltd [1989] 2 Qd R 105

Brenner & Anor v First Artists Management Pty Ltd [1993] 2 VR 221

Codelfa Construction Pty Ltd v State Rail Authority of New South Wales (1982) 149 CLR 346

Pavey & Matthews Pty Ltd v Paul (1987) 162 CLR 221

Update Constructions Pty Ltd v Rozelle Childcare Centre Ltd (1990) 2 NSWLR 251

Case(s) also cited:

Anglopoulos & Anor v Sabatino & Anor, unreported; FCt SCt of SA; Library No BC9502270; September 1995

Parkinson (Sir Lindsay) v Transvaal Provincial Administration [1974] 4 SALR 506

Sharpe v San…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Chapple v CIS Contracting Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2001] WADC 10
Decision Date

CaseChat Overview and Summary

The matter before the court involved a dispute between Chapple, the plaintiffs, and CIS Contracting Pty Ltd, the first defendant, along with a second defendant. The dispute arose from a building contract concerning the installation of thermal insulation and cladding on an electrostatic precipitator as part of a larger building project. The first defendant had contracted with the plaintiffs to supply, erect, and dismantle scaffolding, while the second defendant was responsible for the insulation and cladding work. The primary legal issues the court had to address were the commencement and termination of the contract, whether the plaintiffs were entitled to charge weekly hire rates for materials hired from the start of the hire until the removal of the final material from the site, and the calculation of this entitlement. Additionally, the court needed to determine if the plaintiffs were owed money under the contract or alternatively in quantum meruit, and if so, the extent of this liability. The first defendant counterclaimed for breach of implied terms of contract, and the second defendant was also involved in the dispute, particularly regarding the Scott Schedule and the extent of any additional work requested by the defendants.

The court considered the arguments regarding the contract's commencement and termination, focusing on whether the contract began when the first defendant was engaged by the second defendant and ended when the scaffolding was dismantled. It also examined the plaintiffs' entitlement to weekly hire rates for materials hired, including the calculation of these rates. The court took into account the significant overrun in the project schedule and the plaintiffs' claims against both defendants for recovery of money under the contract or in quantum meruit. The first defendant's counterclaim for breach of implied terms of contract was analyzed in light of the Scott Schedule, which listed various items admitted by the first defendant subject to counterclaim, and those in dispute. The court needed to decide whether either or both defendants had requested extra work from the plaintiffs, and if so, the extent of such work and whether the plaintiffs were entitled to a reasonable price for it. The court also had to assess the total value of the work done by the plaintiffs if any extra work was requested by the defendants.

In its judgment, the court determined that the contract between the plaintiffs and the first defendant began when the first defendant was engaged by the second defendant and ended when the scaffolding was dismantled. It found that the plaintiffs were entitled to charge weekly hire rates for materials hired from the start of the hire until the removal of the final material from the site, but set out the method for calculating these rates. The court held that the plaintiffs were entitled to recover money from the first defendant under the contract, and from the second defendant in quantum meruit, based on the work done. The counterclaim by the first defendant for breach of implied terms of contract was dismissed, and the court found that the plaintiffs had not been requested to perform any additional work by either defendant. The final orders included a determination of the amount owed by the first defendant to the plaintiffs under the contract, and by the second defendant to the plaintiffs in quantum meruit, with the calculation of these amounts to be determined by the court.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established