| CITATION: | CG and HG Windsor Pty Ltd v Waterman [2013] QCAT 618 |
| PARTIES: | CG and HG Windsor Pty Ltd (Applicant) |
| v | |
| Guy Waterman (Respondent) |
| APPLICATION NUMBER: | BDL299-12 |
| MATTER TYPE: | Building Matters |
| HEARING DATE: | 5, 6 and 7 August 2013 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Howe |
| DELIVERED ON: | 7 November 2013 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1 The application of the builder is dismissed. 2 The counter-application of the owner is dismissed. 3 No order as to costs. |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | The Applicant was represented by Mr Dearlove, Solicitor, of Shine Lawyers |
| RESPONDENT: | The Respondent was represented by Mr Thomson of Counsel instructed by Hemming and Hart |
REASONS FOR DECISION
On 18 July 2011, CG and HG Windsor Pty Ltd, builders (Mr Windsor) agreed to renovate Mr Waterman’s house on North Stradbroke Island. They signed a contract. The agreed cost for the work was $395,296.95.
In July 2011 they agreed to add a deck to the works for an additional $14,684.
The contract provided for commencement on 23 January 2012. In fact construction didn't start until 14 February 2012 through no fault of Mr Windsor. Completion was due for 25 June 2012.
Throughout the project numerous additional variations were requested by either Mr Waterman or his son. None of the variations were reduced to writing signed by Mr Waterman as required by s 82 of the Domestic Building Contracts Act 2000 (the DBC Act).
Mr Windsor claimed the variations as extras with his first, second and fourth progress claims. These were all paid by Mr Waterman.
The contract stipulated for payment of a deposit, four progress payments and a final payment on practical completion, all…
Keep reading for free
Create a free CaseChat account to read CG and HG Windsor Pty Ltd v Waterman and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] QCAT 618
- Decision Date
CaseChat Overview and Summary
The court held that the builder was not entitled to payment for the variations, as they did not comply with the statutory requirements. The court also held that the owner was entitled to terminate the contract and claim damages for the builder’s failure to comply with the contract, suspension of works, and defects and incomplete work. The court found that the nature of building contracts was such that the entire contract must be performed as agreed, and that the builder’s failure to do so justified termination and damages. The court also held that the owner was entitled to set off any progress payment claims outside the terms of the contract against the builder’s claim for payment.
The application of the builder is dismissed. The counter-application of the owner is dismissed. No order as to costs.
Orders
Orders of the court
1 The application of the builder is dismissed.
2 The counter-application of the owner is dismissed.
3 No order as to costs.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.