CG and HG Windsor Pty Ltd v Waterman

Link copied
Case Copied 37 min read
CITATION: CG and HG Windsor Pty Ltd v Waterman [2013] QCAT 618
PARTIES: CG and HG Windsor Pty Ltd
(Applicant)
v
Guy Waterman
(Respondent)
APPLICATION NUMBER: BDL299-12
MATTER TYPE: Building Matters
HEARING DATE: 5, 6 and 7 August 2013
HEARD AT:  Brisbane
DECISION OF: Member Howe
DELIVERED ON: 7 November 2013
DELIVERED AT: Brisbane
ORDERS MADE:

1     The application of the builder is dismissed.

2     The counter-application of the owner is dismissed.

3     No order as to costs.

CATCHWORDS:

Variations – recovery of the cost of variations by a builder – variations failing to comply with statutory requirements – quantum meruit – progress payment claims outside the terms of the contract – suspension of works - termination of contract –measure of damages – nature of building contracts – entire contract – set-off -defects and incomplete work

Queensland Civil and Administrative Tribunal Act 2009 s 24(1)(c)
Domestic Building Contracts Act 2000 ss 44, 79(4), 84(2) and (4)
Queensland Building Services Authority Act 1991 s 42(3)

Better Homes Queensland Pty Ltd v O'Reilly & Anor  [2012] QCATA 37
Allaro Homes Cairns Pty Ltd v O’Reilly and Anor [2012] QCA 286

Ownit Homes Pty Ltd v Batchelor [1981] 2 Qd R 124
Robinson v Harman [1848] EngR 135
Bellgrove v Eldridge (1954) 90 CLR 613
Parry & Anor v Ewart [2000] QDC 54
Avilake Pty Ltd v Tucker & Anor [2012] QCAT 41
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Rocci & Anor v Diploma Construction Pty Ltd [2004] WASC 18
Tan Hung Nguyen v Luxury Design Homes Pty Ltd [2004] NSWCA 178
Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184
Mertens v Home Freehold [1921] 2 KB 526.
Amann Aviation Pty Ltd v Commonwealth (1990) 174 CLR 64
Ventura v Svirac [1961] WAR 63

APPEARANCES and REPRESENTATION (if any):

APPLICANT:  The Applicant was represented by Mr Dearlove, Solicitor, of Shine Lawyers
RESPONDENT:  The Respondent was represented by Mr Thomson of Counsel instructed by Hemming and Hart

REASONS FOR DECISION

  1. On 18 July 2011, CG and HG Windsor Pty Ltd, builders (Mr Windsor) agreed to renovate Mr Waterman’s house on North Stradbroke Island.  They signed a contract.  The agreed cost for the work was $395,296.95.

  2. In July 2011 they agreed to add a deck to the works for an additional $14,684. 

  3. The contract provided for commencement on 23 January 2012. In fact construction didn't start until 14 February 2012 through no fault of Mr Windsor.  Completion was due for 25 June 2012.

  4. Throughout the project numerous additional variations were requested by either Mr Waterman or his son. None of the variations were reduced to writing signed by Mr Waterman as required by s 82 of the Domestic Building Contracts Act 2000 (the DBC Act).

  5. Mr Windsor claimed the variations as extras with his first, second and fourth progress claims.  These were all paid by Mr Waterman.

  6. The contract stipulated for payment of a deposit, four progress payments and a final payment on practical completion, all…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read CG and HG Windsor Pty Ltd v Waterman and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2013] QCAT 618
Decision Date

CaseChat Overview and Summary

CG and HG Windsor Pty Ltd (the builder) brought an application seeking payment for variations made to a building contract with Waterman (the owner). The builder claimed that the variations were necessary to comply with statutory requirements, and that it was owed a quantum meruit for the work done. The owner counter-applied, seeking termination of the contract and damages for the builder’s failure to comply with the contract, suspension of works, and defects and incomplete work. The court had to determine whether the builder was entitled to payment for the variations, and whether the owner was entitled to terminate the contract and claim damages.

The court held that the builder was not entitled to payment for the variations, as they did not comply with the statutory requirements. The court also held that the owner was entitled to terminate the contract and claim damages for the builder’s failure to comply with the contract, suspension of works, and defects and incomplete work. The court found that the nature of building contracts was such that the entire contract must be performed as agreed, and that the builder’s failure to do so justified termination and damages. The court also held that the owner was entitled to set off any progress payment claims outside the terms of the contract against the builder’s claim for payment.

The application of the builder is dismissed. The counter-application of the owner is dismissed. No order as to costs.

Orders

Orders of the court

1 The application of the builder is dismissed.

2 The counter-application of the owner is dismissed.

3 No order as to costs.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.