CITATION: CC No 1 v Reed [2010] NSWSC 294 HEARING DATE(S): 16/04/10
JUDGMENT DATE :
6 May 2010JURISDICTION: Equity Divison JUDGMENT OF: Macready AsJ at 1 DECISION: I dismiss the proceedings with costs and dissolve the existing interlocutory injunction. CATCHWORDS: Contracts. Building, engineering and related contracts. Progress claims under the Building and Construction Industry Security of Payment Act 1999 - Claim that later claim was an abuse as it reagitated matters the subject of earlier claims. - No adjudication of earlier claims. - Held in the circumstances no abuse. - Proceedings dismissed. PARTIES: CC No 1 Pty Ltd & Anor v Reed Constructions Australia Pty Ltd & Anor FILE NUMBER(S): SC 2010/81752 COUNSEL: Mr G Inatey SC with Mr D Miller for plaintiff
Mr B Coles QC with Mr B DeBuse for defendantSOLICITORS: Minter Ellison Lawyers for plaintiff
HWL Ebsworth Lawyers for defendant
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
IN THE SUPREME COURT OF
NEW SOUTH WALE
EQUITY DIVISION
TECHNOLOGY AND CONSTRUCTION LIST
ASSOCIATE JUSTICE MACREADY
Thursday 6 May 2010
2010 / 81752 CC No 1 Pty Ltd & Anor v Reed Constructions Pty Ltd
1 HIS HONOUR: This is the final hearing of the plaintiffs’ suit to restrain the adjudication process initiated by the first defendant’s adjudication application dated 29 March 2010 concerning the first defendant’s payment claim dated 1 March 2010. The second defendant is the appointed adjudicator. At present there are injunctions in place to restrain the second defendant from delivering his determination until 5pm on 30 April 2010. A judge of the Court has referred the matter to me for hearing.
Background
2 The claims concern construction works being undertaken by the first defendant, as contractor, for the plaintiffs, as principal, at the Chatswood Chase retail redevelopment in Sydney pursuant to a contract dated 24 January 2008. The contract was in the form of AS4300.
3 The contract progressed with progress claims numbers 1 to 20 being dealt with under the contractual arrangements between the parties. These claims were made between 24 January 2008 and 28 August 2009. None of these progress claims were submitted as payment claims under the Building and Construction Industry Security of Payment Act 1999 (“the Act”).
4 On 28 September 2009 payment claim 21 for the period the ‘week ending 28th September 2009’ which was submitted under the Act was given to the plaintiff. A payment schedule was submitted out-of-time on 20 October 2009. The payment schedule suggested that the amount payable should be $1,957.954. The actual amount claimed in the September payment claim was $3,664,670.55. On 20 October 2009 the plaintiff paid the amount of $1,957,954 after the defendant raised an invoice for that amount.
5 On 13 November 2009 a further payment claim was submitted. This is described in the evidence as the October payment claim and was for an amount $5,126,297.59. On 27 November 2009 a payment schedule was served within time in respect of the October payment claim.…
Continue reading CC No 1 v Reed
Sign in free to access the full text
- AGLC
- CC No 1 v Reed [2010] NSWSC 294
- Case
- [2010] NSWSC 294
- Decision Date
CaseChat Overview and Summary
The court was required to decide if the later claim was an abuse of process, given that the earlier claims had not been adjudicated. The key legal issues centred around the interpretation of the act and the principles of fairness and efficiency in the construction industry's payment processes. Specifically, the court had to consider whether the re-litigation of already considered issues in the later claim constituted an abuse of process.
The court found that, in the absence of adjudication on the earlier claims, there was no abuse of process in the later claim. The court reasoned that the act does not preclude a party from making a further claim if the earlier claims have not been adjudicated. Additionally, the court highlighted the importance of ensuring that the construction industry's payment processes are fair and efficient. The court concluded that the later claim was not an abuse of process under the circumstances. Consequently, the proceedings were dismissed.
This decision underscores the importance of proper adjudication of earlier claims to prevent potential abuse of process in subsequent claims. It also reaffirms the need for clear and efficient processes within the building and construction industry to avoid unnecessary litigation.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.