HIGH COURT OF AUSTRALIA
GAGELER CJ,
GORDON, EDELMAN, STEWARD, GLEESON, JAGOT AND BEECH‑JONES JJCBI CONSTRUCTORS PTY LTD & ANOR APPELLANTS
AND
CHEVRON AUSTRALIA PTY LTD RESPONDENT
CBI Constructors Pty Ltd v Chevron Australia Pty Ltd
[2024] HCA 28
Date of Hearing: 16 April 2024
Date of Judgment: 14 August 2024P22/2023
ORDER
Appeal dismissed with costs.
On appeal from the Supreme Court of Western Australia
Representation
J C Sheahan KC with B Yin for the appellants (instructed by Clayton Utz)
S L Doyle KC with S J Davis and D C McKimmie for the respondent (instructed by Norton Rose Fulbright)
Notice: This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.
GAGELER CJ, GORDON, EDELMAN, STEWARD AND GLEESON JJ. An arbitral tribunal in Western Australia, in a domestic commercial arbitration governed by the UNCITRAL Model Law on International Commercial Arbitration ("the Model Law")[1] and the UNCITRAL Arbitration Rules ("the UNCITRAL Rules"),[2] issued an award that decided all issues of liability. The arbitral tribunal then issued a subsequent award in which the tribunal decided a new issue of liability. This appeal concerns whether the Supreme Court of Western Australia had the power under s 34(2)(a)(iii) of the Commercial Arbitration Act 2012 (WA) ("the Arbitration Act") to set aside that subsequent award on the grounds that the tribunal's authority ceased when it issued the earlier award, and the tribunal was then functus officio. And if the Supreme Court had that power, by what standard was the Supreme Court to exercise it?
[1]UNCITRAL Model Law on International Commercial Arbitration (1985) as amended by the United Nations Commission on International Trade Law on 7 July 2006, given force of law in Australia by the International Arbitration Act 1974 (Cth) and, relevantly, applying to domestic commercial arbitrations as modified by the Commercial Arbitration Act 2012 (WA).
[2]Arbitration Rules of the United Nations Commission on International Trade Law, initially adopted in 1976 (General Assembly resolution 31/98) and revised in 2010 (General Assembly resolution 65/22).
For the reasons that follow, the Supreme Court had power under s 34(2)(a)(iii) of the Arbitration Act to set aside the subsequent award if the Supreme Court determined de novo that the tribunal was functus officio.
Background
The arbitration arose from a dispute concerning a Contract in relation to an offshore oil and gas project conducted by the respondent ("Chevron"), known as the Gorgon Project. The governing law of the Contract was that of Western Australia.[3] Under the Contract, the appellants (collectively, "CKJV") provided staff to work at certain construction sites and Chevron reimbursed CKJV for the cost of the staff ("Staff Costs"). CKJV contended that Chevron had underpaid it for Staff Costs. Chevron alleged (by counterclaim) that it had been overcharged by, and had overpaid, CKJV.
[3]Subject to some express exclusions which are not relevant to the resolution of the appeal.
The Contract provided that "any dispute or controversy arising out of" the Contract, including "any…
Keep reading for free
Create a free CaseChat account to read CBI Constructors Pty Ltd v Chevron Australia Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] HCA 28
- Decision Date
CaseChat Overview and Summary
The arbitral tribunal issued a first interim award determining issues of liability, finding that CKJV was entitled to recover actual staff costs incurred, not contractual rates, and that Chevron's counterclaim regarding overpayment was also subject to certain adjustments. CKJV subsequently repleaded its case on quantum, which Chevron objected to on grounds of *res judicata*, issue estoppel, *Anshun* estoppel, and that the tribunal was *functus officio*. The tribunal rejected Chevron's objections and issued a second interim award. Chevron then applied to the Supreme Court of Western Australia to set aside this second award under section 34(2)(a)(iii) of the *Commercial Arbitration Act 2012* (WA), arguing the tribunal lacked authority. The primary judge set aside the award, finding the tribunal was *functus officio*, and the Court of Appeal dismissed Chevron's subsequent appeal.
The High Court of Australia considered whether the Court of Appeal erred in holding that the Supreme Court had the power to set aside the second interim award under section 34(2)(a)(iii) of the *Commercial Arbitration Act 2012* (WA) and whether the standard of review applied by the Supreme Court was a *de novo* review. The Court determined that section 34(2)(a)(iii) permits a court to set aside an award if it deals with a dispute not contemplated by or falling within the submission to arbitration, or contains decisions beyond the scope of that submission. The Court affirmed that the question of whether an arbitral tribunal has exceeded its jurisdiction, including by becoming *functus officio* in relation to issues already determined, is a matter that a court can review *de novo* under section 34(2)(a)(iii). The Court found that the first interim award had finally determined the issues of liability, and the subsequent repleaded case on quantum by CKJV related to those same issues, thus falling beyond the scope of the tribunal's authority after the first award.
The High Court dismissed the appeal, upholding the decision of the Court of Appeal. The Court concluded that the Supreme Court had the power to review the tribunal's decision *de novo* and correctly found that the tribunal had acted *functus officio* in issuing the second interim award, thereby exceeding the scope of the submission to arbitration. Consequently, the second interim award was properly set aside.
Orders
Orders of the court
Appeal dismissed with costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: GAGELER CJ, GORDON, EDELMAN, STEWARD AND GLEESON JJ, JAGOT AND BEECH-JONES JJ
At the level of the courts, s 34 of the Arbitration Act, drawn from Art 34 of the Model Law, provides that recourse to a court against an arbitral award may only be made by an application for setting aside an award in limited circumstances.[23] The first set of circumstances is where the party making the application "furnishes proof" of one of the following:(1)a party to the arbitration agreement was under some incapacity, or the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication in it, under the law of Western Australia (s 34(2)(a)(i)); (2)the party making the application was not given proper notice of the appointment of an arbitral tribunal or of the arbitral proceedings or was otherwise unable to present the party's case (s 34(2)(a)(ii)); (3)the award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or contains decisions on matters beyond the scope of the submission to arbitration, provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the award which contains decisions on matters not submitted to arbitration may be set aside (s 34(2)(a)(iii)); or (4)the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of the Arbitration Act from which the parties cannot derogate, or, failing such agreement, was not in accordance with that Act (s 34(2)(a)(iv)).The second set of circumstances is where the court finds that: (1) the subject matter of the dispute is not capable of settlement by arbitration under the law of Western Australia (s 34(2)(b)(i)); or (2) the award is in conflict with the public policy of Western Australia (s 34(2)(b)(ii)).Ground 1 – Chevron's application to set aside the Second Interim Award under s 34(2)(a)(iii) of the Arbitration Act[23]Or by an appeal on a question of law: Arbitration Act, s 34A. See also Model Law, Art 5 (cf Arbitration Act, s 5). As has just been explained, the First Interim Award was final and binding. But what did it resolve? Determining the scope of the issues that an arbitral tribunal resolved finally and conclusively is answered by primarily focusing on what the tribunal said and concluded in the award.[24] The Court of Appeal undertook that analysis[25] and found that, by the First Interim Award, the arbitral tribunal determined all issues of liability and that the Contract Criteria Case determined in the Second Interim Award was a case on liability. As already noted, those findings were not challenged in this Court.[26] [24]See, eg, ONGC [2023] SGHC 197 at [35].[25]See [12]-[13] above.[26]See [13] above. In Fidelitas Shipping Co Ltd v V/O Exportchleb,[27] Diplock LJ distinguished the effect of a "final award" on an arbitrator from its effect as an issue estoppel on the parties. Diplock LJ said that "the arbitrator himself becomes functus officio as respects all the issues between the parties" and that the effect of an "interim award" was that "the arbitrator is functus officio as respects the issues to which his interim award relates".[28] Diplock LJ thus considered that where the award is an interim award, such an award "creates an issue estoppel or issue estoppels between the parties and the arbitrator is functus officio as respects the issues to which his interim award relates".[29] While Fidelitas was decided under the Arbitration Act 1950 (UK) in the procedural context of an interim award having been made in the form of a case stated, a procedure which has no equivalent under the Model Law, the reasoning of Diplock LJ in the respect above has been accepted in Australian and English courts.[30] It has been adopted by leading commentaries as authority for the general proposition that if an award is an interim award, "the arbitrator still has authority to deal with the matters left over, although he is functus officio as regards matters dealt with in the award".[31] And the Court of Appeals of New York has held that "partial determinations may be treated as final awards where the parties expressly agree both that certain issues submitted to the arbitrators should be decided in separate partial awards and that such awards will be considered to be final" with the result that the arbitral tribunal lacks "authority to reconsider the resulting partial final award".[32] This international treatment confirms the approach of Diplock LJ described above and informs the intended meaning of Art 34(2) of the UNCITRAL Rules. [27][1966] 1 QB 630 at 644.[28][1966] 1 QB 630 at 644.[29][1966] 1 QB 630 at 644.[30]ABB Service Pty Ltd v Pyrmont Light Rail Company Ltd (2010) 77 NSWLR 321 at 337 [70], 341-342 [93]-[97]; Discovery Beach [2011] QSC 306 at [68]; Emirates Trading Agency LLC v Sociedade de Fomento Industrial Private Ltd [2016] 1 All ER (Comm) 517 at 526 [26], 527-528 [33], [35]-[36]. See also Alvaro v Temple [2009] WASC 205 at [67]. [31]Mustill and Boyd, The Law and Practice of Commercial Arbitration in England, 2nd ed (1989) at 405. See also Sutton, Gill and Gearing, Russell on Arbitration, 24th ed (2015) at 297 [6-016], 352 [6-166]. [32]American International Specialty Lines Insurance Company v Allied Capital Corporation (2020) 149 NE 3d 33 at 38.