JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: APG HOMES PTY LTD -v- PRIMARY CREATIONS PTY LTD [2009] WASC 227
CORAM: MURPHY J
HEARD: 23 JULY 2009
DELIVERED : 21 AUGUST 2009
FILE NO/S: ARB 6 of 2009
BETWEEN: APG HOMES PTY LTD
Applicant
AND
PRIMARY CREATIONS PTY LTD
Respondent
Catchwords:
Application to set aside interim award - Arbitral misconduct - Application out of time - Requirement for explanation for delay - Finality in arbitral matters
Legislation:
Commercial Arbitration Act 1985 (WA), s 42
Result:
Application dismissed
Category: B
Representation:
Counsel:
Applicant: Mr B P Wheatley
Respondent: Mr K Burgoyne
Solicitors:
Applicant: Mossensons
Respondent: Burgoynes
Case(s) referred to in judgment(s):
Alvaro v Temple [2009] WASC 205
Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27
Carr v Finance Corporation of Australia Ltd (No 1) [1981] HCA 20; (1981) 147 CLR 246
Doran Constructions Pty Ltd v Health Administration Corporation of New South Wales (1994) 12 BCL 59
Gallo v Dawson [1990] HCA 30; (1990) 64 ALJR 458
Gas & Fuel Corporation of Victoria v Wood Hall Ltd & Leonard Pipeline Contractors Ltd [1978] VR 385
Gebauer Nominees Pty Ltd v Cole [No 2] [2008] WASCA 41
Girando v Girando (1997) 18 WAR 450
Lester v Heitman (Unreported, WASC, Library No 980515, 9 September 1998)
Livesey v New South Wales Bar Association [1983] HCA 17; (1983) 151 CLR 288
Minenco Pty Ltd v Abigroup Contractors (WA) Pty Ltd (1992) 7 WAR 576
Modern Engineering (Bristol) Ltd v C Miskin & Son Ltd (1980) 15 BLR 82
Nathan v MJF Constructions [1986] VR 75
Oil Basins Ltd v BHP Billiton Ltd [2007] VSCA 255; (2007) 18 VR 346
Pakenham Upper Fruit Co Ltd v Crosby [1924] HCA 55; (1924) 35 CLR 386
Peter Schwarz (Overseas) Pty Ltd v Morton [2003] VSC 144
Shirley Sloan Pty Ltd v Merril Holdings Pty Ltd t/as Airen Constructions [2000] WASC 99
Silent Vector Pty Ltd v Hassell [2005] WASC 79
Sydney Water Corporation Ltd v Aqua Clear Technology Pty Ltd [1996] NSWSC 640
Technical Team Projects Pty Ltd v Noble Dunn Pty Ltd (1990) 20 NSWLR 221
MURPHY J:
Introduction
The applicant is a builder. The respondent is the owner of certain land in Dawesville upon which the applicant agreed to build a domestic dwelling. A dispute arose between the parties as to the construction of the dwelling, which was referred to arbitration. The arbitrator delivered three interim awards, the first and third of which are under challenge in these proceedings. I will refer to the applicant as the builder and the respondent as the owner in these reasons.
This is an application by notice of originating motion filed 28 April 2009, but dated 17 April 2009, by the builder for, in effect:
(a)leave to extend the time in which to make an application under s 42 of the Commercial Arbitration Act 1985 (WA) (the Act);
(b)an…
Keep reading for free
Create a free CaseChat account to read APG Homes Pty Ltd v Primary Creations Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2009] WASC 227
- Decision Date
CaseChat Overview and Summary
The Court found that the arbitrator had indeed made findings outside the agreed scope of the arbitration, which constituted arbitral misconduct. However, the Court also held that the application to set aside the award was out of time. The Court found that the applicant had not provided a satisfactory explanation for the delay in bringing the application. The Court emphasised the importance of finality in arbitral matters and noted that applications to set aside awards should be brought promptly. The Court held that the application was barred by the doctrine of finality.
The Court dismissed the application to set aside the interim award. The Court noted that the interim award would be subject to review in the context of the final award. The Court did not make any orders regarding the substantive merits of the dispute between the parties.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
On 27 April 2008 the arbitrator delivered the first interim award dealing with the two issues to which he had earlier referred. It commenced in these terms:… I find and determine -The Respondent has been delayed in the procurement of a Building Licence from the City of Mandurah, for reasons outside of its control and is entitled to amend the price of the works, consistent with Clause 4(b) of the HIA Contract dated the 23rd January 2006, for the period between the expiry of the fixed price, (29 March 2006) until receipt of the issue of the Building licence on or around the 13th June 2006. No finding is made as to the quantum of the price rise. That the Respondent was not entitled to suspend work under the contract as a result of a refusal by the Claimant to accept the quantum of the price rise. The parties are at liberty to make submissions as to costs. The arbitrator also said, in the first interim award:Extent of 1st Stage of ArbitrationThe parties agreed that the extent of this Award should be limited to the determination of 2 issues•Was the Respondent entitled to claim for additional costs as a result of delays in obtaining a building licence, consistent with the contract, that is were the delays outside of the control of the Builder and for the reasons allowed for in the contract that would give rise to a right to make a claim for increase in cost•With reference to the finding at 1 above, was the Respondent entitled to suspend works for failure by the Claimant to sign the price rise variation.It was agreed that other matters, including the matter of quantum arising from any finding could be left for further determination and subject to the determination of these 2 preliminary questions. The reference in the second dot point above to 'sign the price rise variation' was a reference to the finding (line 94) that:On the 20th June 2006, the [builder] advised the [owner] that it would not commence construction until the [owner] signed the variation for the price rise submitted by the [builder] on the 20th April 2006. On 6 May 2008 the builder's solicitor wrote to the arbitrator and said, relevantly:We refer to the finding 'That the Respondent was not entitled to suspend work under the contract as a result of a refusal by the Claimant to accept the quantum of the price rise' (lines 13 and 14 of the interim award). The Respondent did not address this issue and was not afforded an opportunity to be heard in relation to the same. The two issues that the parties agreed to be determined by the Arbitrator at the initial hearing were the Claimant's entitlement to the first price rise on 20 April 2006 and the second price rise on 11 September 2006 (compare lines 137 to 149 of the interim award).It was further agreed that the quantum of the price rises arising from these two issues and the issue of specific performance, etc. would be left for later determination. Both sides restricted submissions to matters of delay and did not make submissions regarding specific performance or whether the Claimant was entitled to delay the works. It should be noted that paragraph 32 of the Claimant's Points of Claim, dated 16 April 2007, refers to an order for specific performance or alternatively that the Respondent is not entitled to delay the works as a result of this dispute.