District Court
New South Wales
Medium Neutral Citation: Casey v Retford [2025] NSWDC 1 Hearing dates: 26 – 27 June 2024, 9 August 2024 Date of orders: 04 February 2025 Decision date: 04 February 2025 Jurisdiction: Civil Before: Cole DCJ Decision: (1) Judgment for the plaintiffs in the sum of $117,566.20.
(2) Judgment for the defendant on the cross-claim in the sum of $814.
Catchwords: BUILDING AND CONSTRUCTION — Contract — Damages — Defects – Incomplete work - Restitution
Legislation Cited: District Court Act 1973
Home Building Act 1989
Home Building Regulation 2014
Cases Cited: ANZ Banking Group Limited v Westpac Banking Corporation (1988) 164 CLR 662
Armstrong Strategic Management and Marketing Pty Ltd v Expense Reduction Analysts Group Pty Ltd (No 9) [2016] NSWSC 1005
Donau Pty Ltd v ASC AWD Shipbuilder Pty Ltd [2019] NSWCA 185
Mann v Paterson Constructions Pty Ltd [2019] HCA 32
Matthew Lumbers and Anor v W Cook Builders Pty Ltd [2008] HCA 27
McDonald v Dennys Lascelles Ltd (1933) 48 CLR 457
Paraiso v CBS Build Pty Ltd [2020] NSWSC 190
Realestate.com.au Pty Ltd v Hardingham and Others; RP Data Pty Ltd v Hardingham and Others [2022] HCA 39
Sargent v ASL Developments Ltd (1974) 131 CLR 634
Westpoint Management Ltd v Chocolate Factory Apartments Ltd [2007] NSWCA 253
Category: Principal judgment Parties: Craig Casey (First Plaintiff)
Katy Casey (Second Plaintiff)
Hayden Retford trading as Skope Construction (Defendant)Representation: Counsel:
M Klooster (Plaintiffs)
D Neggo (Defendant)
Solicitors:
KLH & Associates (Plaintiffs)
PBL Law Group (Defendant)
File Number(s): 2023/00221664 Publication restriction: Nil
JUDGMENT
-
On 16 July 2021, the plaintiffs, Mr Craig Casey and Ms Katy Casey, entered into a written contract with the defendant, Mr Hayden Retford, a builder, which provided for Mr Retford to undertake alterations and additions to the dwelling (“the house”) on land owned by Mr and Ms Casey (“the property”) for the price of $624,475.
-
In their amended statement of claim, in summary, the plaintiffs allege that, by 19 December 2022, the defendant was in breach of contract, and in breach of the Home Building Act 1989 (“the Act”), in that he had failed to complete the works provided for in the contract within 26 weeks from the date of the commencement of the works. It was further alleged that some of the work done was defective and had not been rectified. It is common ground that the works the subject of the contract are “residential building works” under the Act.
-
The plaintiffs also allege, in their amended statement of claim, that they paid $818,862.51 for the works and that this sum represented an overpayment. They allege that the defendant has received a benefit at their expense, that it would be unjust or unconscionable for the defendant to retain that benefit and that the defendant is liable to repay to them the amount of the overpayment.
-
The plaintiffs say that they terminated the contract by email to the defendant on 19…
Keep reading for free
Create a free CaseChat account to read Casey v Retford and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2025] NSWDC 1
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the defendant breached the contract by failing to complete the work and whether the plaintiffs were entitled to damages for the incomplete work and defects. The court also had to decide whether the plaintiffs were entitled to restitution for any overpayment made to the defendant and whether the defendant was entitled to payment for the work that he had completed.
The court found that the defendant did breach the contract by failing to complete the work and that the plaintiffs were entitled to damages for the incomplete work and defects. The court also found that the plaintiffs were not entitled to restitution for any overpayment made to the defendant as the plaintiffs had not provided sufficient evidence to support their claim. The court further found that the defendant was entitled to payment for the work that he had completed, but the amount was less than what the plaintiffs had previously paid to the defendant. The court ordered judgment for the plaintiffs in the sum of $117,566.20 and judgment for the defendant on the cross-claim in the sum of $814.
Orders
Orders of the court
(1) Judgment for the plaintiffs in the sum of $117,566.20.
(2) Judgment for the defendant on the cross-claim in the sum of $814.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi