Court of Appeal
New South Wales
Case Title: The Craftsmen Restoration & Renovations Pty Ltd v Boland Medium Neutral Citation: [2011] NSWCA 147 Hearing Date(s): 17 May 2011 Decision Date: 08 June 2011 Jurisdiction: Before: Allsop P at 1;
Basten JA at 5;
Sackville AJA at 74Decision: (1) To the extent necessary, grant the builder leave to appeal from the judgments and orders of Howie J in the Common Law Division.
(2) In respect of both appeals brought to the Common Law Division, set aside the orders of Howie J made on 2 March 2009 and in place thereof:
(a) answer the question of law raised by the builder's appeal in respect of the termination of the contract as follows:
"According to the proper construction of the contract, in the circumstances found by the Tribunal, namely that the owners were, in August 2003, in breach of their obligation to pay progress payment No. 8, the notice given by them under clause 12.3 of the contract, purporting to terminate the contract, was not a valid notice";
(b) set aside order (2), and to the extent that it determines the amount referred in order (3), order (3), made by the Tribunal on 28 August 2006;
(c) remit to the Tribunal the answer at (a) above and order a further hearing by the Tribunal to determine the outstanding issues in the dispute between the parties consistently with the answer given to the question of law, and
(d) order each party to bear its own costs of the proceedings in the Common Law Division.
(3) Refuse the owners' application for an extension of time within which to seek leave to file a notice of cross-appeal.
(4) Direct that the builder's costs in respect of the application referred to in (3) above be its costs in the appeal.
(5) Order the owners to pay the builder's costs of the proceedings in this Court.
(6) Grant the owners a certificate under the Suitors' Fund Act 1951 (NSW) in respect of the costs of the appeal in this Court.
(7) Grant leave to the parties to seek a variation of orders (2)(d) and (5) by:
(a) within 14 days of the date of this judgment providing to the Registrar (with a copy to the Associate to each Judge and to the other party), a document setting out the order sought, any supporting material and reasons for such order;
(b) the other party shall, within 14 days of receiving such material, respond in like manner.
(8) The Registrar is directed:
(a) not to enter orders (2)(d) and (5) for 14 days;
(b) if no document is received within 14 days in accordance with order (7)(a), to enter those orders, or
(c) otherwise, to enter such order as the Court shall direct.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system.…
Keep reading for free
Create a free CaseChat account to read Craftsmen Restoration & Renovations Pty Ltd v Boland and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] NSWCA 147
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the Court of Appeal was whether an invalid notice of termination given by the owners under the contract constituted a repudiation of the contract, and if so, whether the builder could accept such a repudiation. A further issue concerned the extent to which an appellate court could make findings of fact in an appeal limited to a question of law.
The Court of Appeal reasoned that the owners' notice purporting to terminate the contract was not a valid notice according to the proper construction of the contract, given that the owners were themselves in breach of their obligation to pay a progress payment at the time the notice was issued. The Court held that an invalid notice of termination, in the circumstances found by the Tribunal, did not constitute a repudiation of the contract by the owners. Consequently, the builder could not accept such a repudiation.
The Court of Appeal granted the builder leave to appeal, set aside the orders of Howie J, and remitted the matter to the Tribunal for further hearing. The Court answered the question of law by stating that the owners' notice was not a valid termination notice. The owners' application for an extension of time to file a cross-appeal was refused. The Court ordered the owners to pay the builder's costs of the proceedings in the Court of Appeal.
Orders
Orders of the court
(1) To the extent necessary, grant the builder leave to appeal from the judgments and orders of Howie J in the Common Law Division.
(2) In respect of both appeals brought to the Common Law Division, set aside the orders of Howie J made on 2 March 2009 and in place thereof:
(a) answer the question of law raised by the builder's appeal in respect of the termination of the contract as follows:
"According to the proper construction of the contract, in the circumstances found by the Tribunal, namely that the owners were, in August 2003, in breach of their obligation to pay progress payment No. 8, the notice given by them under clause 12.3 of the contract, purporting to terminate the contract, was not a valid notice";
(b) set aside order (2), and to the extent that it determines the amount referred in order (3), order (3), made by the Tribunal on 28 August 2006;
(c) remit to the Tribunal the answer at (a) above and order a further hearing by the Tribunal to determine the outstanding issues in the dispute between the parties consistently with the answer given to the question of law, and
(d) order each party to bear its own costs of the proceedings in the Common Law Division.
(3) Refuse the owners' application for an extension of time within which to seek leave to file a notice of cross-appeal.
(4) Direct that the builder's costs in respect of the application referred to in (3) above be its costs in the appeal.
(5) Order the owners to pay the builder's costs of the proceedings in this Court.
(6) Grant the owners a certificate under the Suitors' Fund Act 1951 (NSW) in respect of the costs of the appeal in this Court.
(7) Grant leave to the parties to seek a variation of orders (2)(d) and (5) by:
(a) within 14 days of the date of this judgment providing to the Registrar (with a copy to the Associate to each Judge and to the other party), a document setting out the order sought, any supporting material and reasons for such order;
(b) the other party shall, within 14 days of receiving such material, respond in like manner.
(8) The Registrar is directed:
(a) not to enter orders (2)(d) and (5) for 14 days;
(b) if no document is received within 14 days in accordance with order (7)(a), to enter those orders, or
(c) otherwise, to enter such order as the Court shall direct.
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.