| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
No. 6453 of 2004
| BMD MAJOR PROJECTS PTY LTD | Plaintiff |
| v | |
| VICTORIAN URBAN DEVELOPMENT AUTHORITY | Defendant |
---
JUDGE: | PAGONE J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 31 July 2007 | |
DATE OF JUDGMENT: | 19 October 2007 | |
CASE MAY BE CITED AS: | BMD Major Projects Pty Ltd v Victorian Urban Development Authority | |
MEDIUM NEUTRAL CITATION: | [2007] VSC 409 | Revised 15 November 2007 |
---
BUILDING AND CONSTRUCTION CONTRACTS – Latent condition – Requirements of notice – Meaning of forthwith – Whether identification of precise location of latent condition necessary for notice – Whether physical conditions differed materially from what the contractor should reasonably have anticipated – Objective standard – Whether reasonable enquiries made – Valuation for additional work at “reasonable rates” – Notice for delay sufficient for contractual variation – Contractual variation for the convenience of the contractor – Payment certificate issued – Breach of duty of care
TRADE PRACTICES — Misleading and deceptive conduct – s 52 Trade Practices Act
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr G Golvan QC with Mr P Kelly | Rigby Cooke with Carter Newell |
| For the Defendant | Mr H Foxcroft SC with Ms G Gray | Corrs Chambers Westgarth |
TABLE OF CONTENTS
A. Preliminary observations........................................................................................................... 2
B. BMD’s contract claim for latent condition.............................................................................. 3
1. Quarry Floor Stockpiles/Southern Stockpile claim............................................................ 5
(a) Notification.......................................................................................................................... 5
(b) Extent of 2 August 2002 notification................................................................................. 7
(c) Estoppel.............................................................................................................................. 12
(d) The latent condition.......................................................................................................... 13
(e) Breach of contractual warranties....................................................................................... 22
2. Avenue Stockpile, Eastern Stockpile and Northern Stockpile........................................ 23
3. Quantum: over excavation.................................................................................................... 25
(a) Additional placement of Type B and Type C material in “quarry floor” stockpile........... 26
(b) Additional placement of Type A material in Eastern Stockpile........................................ 31
(c) Additional placement of Type A in the Avenue Stockpile................................................. 32
(d) Additional placement of Type A in the Northern Stockpile.............................................. 33
(e) Additional wet base treatment........................................................................................... 33
(f) Additional works as a result of a change in topography in the area of the Northern Stockpile. 37
(g) Additional works as a result of haulage requirements in the area of the Avenue Stockpile 38
(h) Additional costs for material processing........................................................................... 40
(i) Value of delay claims caused by the latent conditions....................................................... 42
4. Second latent condition: oversized rock............................................................................. 49
C. Contractual variation................................................................................................................. 59
1. Stockpiling of Type A material............................................................................................ 60
2. Extra layers and tolerances in placing Type B material................................................... 65
3. Additional tolerances at Type A/B interface..................................................................... 68
4. Geofabric claim....................................................................................................................... 71
D. Certificates and payments........................................................................................................ 74
E. Trade Practices Claim................................................................................................................ 80
F. Unjust enrichment...................................................................................................................... 91
G. Liquidated Damages................................................................................................................. 92
H. VicUrban’s counterclaim.......................................................................................................... 93
I. Second Bank Guarantee............................................................................................................. 98
J. Orders and Costs......................................................................................................................... 98
HIS HONOUR:
BMD Major Projects Pty Ltd (“BMD” or “the contractor”) primarily claims against the Victorian Urban Development Authority as the successor to the Urban and Regional Land Corporation (“VicUrban” or “the principal”) under a “latent conditions” clause of a contract between them dated 22 March 2002 based upon AS 2124 1992.…
Keep reading for free
Create a free CaseChat account to read BMD Major Projects Pty Ltd v Victorian Urban Development Aut... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] VSC 409
- Decision Date
CaseChat Overview and Summary
The court examined various legal issues, including the requirements for notice of latent conditions, the meaning of "forthwith," the extent of the latent conditions, and whether BMD should have reasonably anticipated the conditions. The court also considered whether BMD breached contractual warranties and if VicUrban was estopped from relying on strict compliance with the contract. The court ultimately determined that BMD provided effective notice of the latent conditions and that the conditions were indeed latent, as they differed materially from the physical conditions that should reasonably have been anticipated by BMD at the time of the tender. BMD was also found to be entitled to compensation for the additional work and costs incurred due to the latent conditions.
In addition to the latent condition claims, the court evaluated BMD's claim for contractual variations, including the stockpiling of Type A material, extra layers and tolerances in placing Type B material, and additional tolerances at the Type A/B interface. The court concluded that BMD was entitled to payment for these variations. The court also found that BMD was not liable for liquidated damages, as it was entitled to extensions of time for completing the works.
Finally, the court dismissed VicUrban's counterclaim for failure to maintain the required capping layer, ruling that the primary cause for the need to redesign the surface levels was the shortfall of materials available for placement.
In conclusion, the court ordered VicUrban to pay BMD the sum of $2,549,850.89 for the claims under the contract, repay $670,000 for liquidated damages, and return the remaining bank guarantee. The court dismissed BMD's other claims and VicUrban's counterclaim.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.