Blanalko Pty Ltd v Lysaght Building Solutions Pty Ltd

Link copied
Case Copied 54 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL COURT

ARBITRATION LIST

S CI 2012 05740
S CI 2016 04504

LYSAGHT BUILDING SOLUTIONS PTY LTD t/as HIGHLINE COMMERCIAL CONSTRUCTIONS (ACN 103 232 444) Plaintiff
v
BLANALKO PTY LTD (ACN 005 822 926) Defendant
BLANALKO PTY LTD (ACN 005 822 926) Applicant
v
LYSAGHT BUILDING SOLUTIONS PTY LTD t/as HIGHLINE COMMERCIAL CONSTRUCTIONS (ACN 103 232 444) Respondent

---

JUDGE:

CROFT J

WHERE HELD:

Melbourne

DATE OF HEARING:

23 February 2017

DATE OF JUDGMENT:

10 March 2017

CASE MAY BE CITED AS:

Blanalko Pty Ltd v Lysaght Building Solutions Pty Ltd

MEDIUM NEUTRAL CITATION:

[2017] VSC 97

---

ARBITRATION – Application for a stay of court proceedings in favour of arbitral proceedings – Application to set aside arbitral award – Whether arbitral award final where all issues referred to arbitration not determined – Extent to which correction and interpretation provisions of the legislation are applicable where arbitrator decides, expressly, not to determine an issue – Extent to which arbitrator’s mandate subsists – Johnson v Latham (1850) 19 LJQB 329 – Gatoil International Inc v National Iranian Oil Company (unreported, 22 February 1990, EWCA) – Administration of Norfolk Island v SMEC Australia Pty Ltd (2004) NFSC 1 – CRW Joint Operation v PT Perusahaan Gas Negara (Persero) TBK [2011] 4 SLR 305 – TCL Air Conditioner (Zhongshan) Company Ltd v Castel Electronics Pty Ltd (2014) 232 FCR 361 – BLC v BLB [2014] 4 SLR 79 – Dyna-Jet Pte Ltd v Wilson Taylor Asia Pacific Pte Ltd [2016] SGHC 238 – Commercial Arbitration Act 2011, s 5, 14, 32, 33 and 34 – Arbitration Act 1996 (Eng), s 68.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff
(S CI 2012 05740)
Mr T Clarke King & Wood Mallesons
For the Defendant
(S CI 2012 05740)
Mr R Manly QC with
Mr S Stuckey
Wisewould Mahony
For the Applicant
(S CI 2016 04504)
Mr R Manly QC with
Mr S Stuckey
Wisewould Mahony
For the Respondent
(S CI 2016 04504)
Mr T Clarke King & Wood Mallesons

HIS HONOUR:

Introduction

  1. This dispute has been before this Court since 2012.  It deals with two proceedings, both of which now relate to unresolved legal costs arising out of the first proceeding. Specifically, the parties dispute whether Lysaght Building Solutions Pty Ltd (“Lysaght”) must pay the costs of Blanalko Pty Ltd (“Blanalko”) of and incidental to the first proceeding, including the reference to the Court of Appeal (“the Supreme Court Costs”).

  1. The first proceeding was commenced in 2012 by Blanalko which alleged that Lysaght had breached a design and construction contract that existed between the two parties.  After an extensive procedural history that need not be recounted, it was partially settled in April 2016, with the remaining issues being referred to arbitration by the settlement deed of 21 April 2016 (“the Settlement Deed”).[1]

    [1]Settlement Deed as exhibited to Affidavit of Peter Thomas Pether (30 November 2016).

  1. The arbitrator delivered an interim award on 15 June 2016…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Blanalko Pty Ltd v Lysaght Building Solutions Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] VSC 97
Decision Date

CaseChat Overview and Summary

Blanalko Pty Ltd applied for a stay of the court proceedings in favour of arbitral proceedings against Lysaght Building Solutions Pty Ltd. In addition, Blanalko applied to set aside the arbitral award made by the arbitrator. The dispute centred around whether the arbitral award was final when all the issues referred to arbitration had not been determined. The court was required to determine whether the arbitral award was final and whether the correction and interpretation provisions of the legislation were applicable where the arbitrator expressly decided not to determine an issue.

The court considered the extent to which the arbitrator’s mandate subsisted and whether the award was final. The court held that the arbitral award was not final, as not all issues had been determined. The court noted that the arbitrator had expressly decided not to determine an issue, and therefore, the correction and interpretation provisions of the legislation were not applicable. The court held that the arbitrator’s mandate had not subsisted, and therefore, the award was not final.

The court held that the arbitral award was not final and set it aside. The court granted the application for a stay of the court proceedings in favour of arbitral proceedings. The court held that the application to set aside the arbitral award was well-founded, and the award was set aside.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.