Biosciences Research Centre Pty Ltd v Plenary Research Pty Ltd

Link copied
Case Copied 68 min read
IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL AND EQUITY DIVISION

COMMERCIAL COURT

ARBITRATION LIST

No. 2464 of 2012

BIOSCIENCES RESEARCH CENTRE PTY LTD Plaintiff
v
PLENARY RESEARCH PTY LTD Defendant

---

JUDGE:

CROFT J

WHERE HELD:

Melbourne

DATE OF HEARING:

21 May 2012

DATE OF JUDGMENT:

19 June 2012

CASE MAY BE CITED AS:

Biosciences Research Centre Pty Ltd v Plenary Research Pty Ltd

MEDIUM NEUTRAL CITATION:

[2012] VSC 249

---

CONTRACT – construction contract – extension of time claim – whether disputed claims to be referred to an independent expert or to arbitration for determination – interpretation and construction of the dispute resolution regime – intention of parties – nature of dispute and construction issues – appropriateness of determination by independent expert - Badgin Nominees Pty Ltd v Oneida Ltd [1998] VSC 188 - The Heart Research Institute Ltd v Psiron Ltd [2002] NSWSC 646.

ARBITRATION – clause permitting resolution of extension of time dispute by arbitration – whether binding arbitration agreement - Manningham City Council v Dura (Australia) Constructions Pty Ltd (1999) 3 VR 13 (CA) – Commercial Arbitration Act (Vic) 1984, sub-s 53(1).

WORDS AND PHRASES – interpretation of the word ‘may’ in dispute resolution clauses - Oakton Services Pty Ltd v Tenix Solutions IMES Pty Ltd [2010] VSC 176.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr J. Rowland QC with
Ms K. Stynes
Clayton-Utz
For the Defendant Mr C.M. Scerri QC Allens

TABLE OF CONTENTS

Introduction......................................................................................................................................... 2

The Project Agreement...................................................................................................................... 6

Provisions of the Project Agreement................................................................................................. 6
Dispute resolution regime............................................................................................................... 12
Construction of subclause 26.16.................................................................................................... 18
Relevant case law........................................................................................................................... 26

Nature of the dispute....................................................................................................................... 34

Effect in relation to construction issues.......................................................................................... 34
Appropriateness of expert determination........................................................................................ 38

Summary and conclusions............................................................................................................. 42

HIS HONOUR:

Introduction

  1. The context in which this proceeding comes before the Court is an agreement dated 30 April 2009 between Biosciences Research Centre Pty Ltd (“the plaintiff”) and Plenary Research Pty Ltd (“the defendant”) whereby the defendant agreed to design, construct and operate a biosciences research facility at the Bundoora Campus of Latrobe University (“the Project Agreement”).  The Project Agreement was varied by an amending deed dated 16 June 2011 (“the Amending Deed”).

  1. By a contract dated 13 May 2009, the defendant subcontracted the design and construction of the Biosciences Research facility to Grocon Constructors (Vic) Pty Ltd (“the Builder”).

  1. The Project Agreement requires that:

(a)‘Technical Completion’[1] be achieved by 19 October 2011, unless adjusted under clause 26 of that Agreement;  and

(b)‘Commercial Acceptance’[2] be achieved by 30 November 2011, unless adjusted under clause 26.

[1]‘Technical Completion’ is defined in Clause 1.1 of the Project Agreement in the following terms:

‘Technical Completion means that stage of the works where all of the Technical Completion Criteria and Completion Requirements with respect to Technical Completion have been satisfied to the reasonable satisfaction of the Independent Reviewer.’

[2]‘Commercial Acceptance’ is defined in Clause 1.1 of the Project Agreement in the following terms:

‘

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Biosciences Research Centre Pty Ltd v Plenary Research Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] VSC 249
Decision Date

CaseChat Overview and Summary

Biosciences Research Centre Pty Ltd brought a claim against Plenary Research Pty Ltd in the Supreme Court of Victoria, challenging a construction contract dispute concerning an extension of time. The central issue was whether a claim for an extension of time should be referred to an independent expert or to arbitration for resolution. The contract included a dispute resolution clause that allowed either party to seek resolution of a dispute by arbitration, or to request an independent expert determine the dispute if the parties could not agree on an expert.

The court was required to interpret the contract's dispute resolution clause to determine the appropriate mechanism for resolving the extension of time claim. It needed to ascertain whether the clause permitting arbitration was binding and whether the clause allowing for an independent expert was mandatory or discretionary. The court also had to consider the intention of the parties regarding the nature of the dispute and the construction issues.

The court found that the clause permitting resolution by arbitration was binding, and therefore, the dispute should be resolved by arbitration. The court noted that the use of the word 'may' in the clause referring to an independent expert indicated a discretionary process rather than a mandatory one. The court concluded that the parties intended the dispute to be resolved through arbitration, and not by an independent expert, due to the nature of the construction issues involved. The court's interpretation was influenced by previous cases such as Manningham City Council v Dura (Australia) Constructions Pty Ltd and Oakton Services Pty Ltd v Tenix Solutions IMES Pty Ltd.

The court ordered that the dispute regarding the extension of time claim be referred to arbitration, in accordance with the binding arbitration clause in the contract. The court emphasised the importance of interpreting the contract in line with the intention of the parties, considering the nature of the dispute and the construction issues at hand. The court's decision was based on a careful analysis of the contract terms and relevant case law, providing clarity for the parties in resolving their dispute.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.