| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
COMMERCIAL COURT
ARBITRATION LIST
No. 2464 of 2012
| BIOSCIENCES RESEARCH CENTRE PTY LTD | Plaintiff |
| v | |
| PLENARY RESEARCH PTY LTD | Defendant |
---
JUDGE: | CROFT J | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 21 May 2012 | |
DATE OF JUDGMENT: | 19 June 2012 | |
CASE MAY BE CITED AS: | Biosciences Research Centre Pty Ltd v Plenary Research Pty Ltd | |
MEDIUM NEUTRAL CITATION: | [2012] VSC 249 | |
---
CONTRACT – construction contract – extension of time claim – whether disputed claims to be referred to an independent expert or to arbitration for determination – interpretation and construction of the dispute resolution regime – intention of parties – nature of dispute and construction issues – appropriateness of determination by independent expert - Badgin Nominees Pty Ltd v Oneida Ltd [1998] VSC 188 - The Heart Research Institute Ltd v Psiron Ltd [2002] NSWSC 646.
ARBITRATION – clause permitting resolution of extension of time dispute by arbitration – whether binding arbitration agreement - Manningham City Council v Dura (Australia) Constructions Pty Ltd (1999) 3 VR 13 (CA) – Commercial Arbitration Act (Vic) 1984, sub-s 53(1).
WORDS AND PHRASES – interpretation of the word ‘may’ in dispute resolution clauses - Oakton Services Pty Ltd v Tenix Solutions IMES Pty Ltd [2010] VSC 176.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr J. Rowland QC with Ms K. Stynes | Clayton-Utz |
| For the Defendant | Mr C.M. Scerri QC | Allens |
TABLE OF CONTENTS
Introduction......................................................................................................................................... 2
The Project Agreement...................................................................................................................... 6
Provisions of the Project Agreement................................................................................................. 6
Dispute resolution regime............................................................................................................... 12
Construction of subclause 26.16.................................................................................................... 18
Relevant case law........................................................................................................................... 26
Nature of the dispute....................................................................................................................... 34
Effect in relation to construction issues.......................................................................................... 34
Appropriateness of expert determination........................................................................................ 38
Summary and conclusions............................................................................................................. 42
HIS HONOUR:
Introduction
The context in which this proceeding comes before the Court is an agreement dated 30 April 2009 between Biosciences Research Centre Pty Ltd (“the plaintiff”) and Plenary Research Pty Ltd (“the defendant”) whereby the defendant agreed to design, construct and operate a biosciences research facility at the Bundoora Campus of Latrobe University (“the Project Agreement”). The Project Agreement was varied by an amending deed dated 16 June 2011 (“the Amending Deed”).
By a contract dated 13 May 2009, the defendant subcontracted the design and construction of the Biosciences Research facility to Grocon Constructors (Vic) Pty Ltd (“the Builder”).
The Project Agreement requires that:
(a)‘Technical Completion’[1] be achieved by 19 October 2011, unless adjusted under clause 26 of that Agreement; and
(b)‘Commercial Acceptance’[2] be achieved by 30 November 2011, unless adjusted under clause 26.
[1]‘Technical Completion’ is defined in Clause 1.1 of the Project Agreement in the following terms:
‘Technical Completion means that stage of the works where all of the Technical Completion Criteria and Completion Requirements with respect to Technical Completion have been satisfied to the reasonable satisfaction of the Independent Reviewer.’
[2]‘Commercial Acceptance’ is defined in Clause 1.1 of the Project Agreement in the following terms:
‘
Keep reading for free
Create a free CaseChat account to read Biosciences Research Centre Pty Ltd v Plenary Research Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] VSC 249
- Decision Date
CaseChat Overview and Summary
The court was required to interpret the contract's dispute resolution clause to determine the appropriate mechanism for resolving the extension of time claim. It needed to ascertain whether the clause permitting arbitration was binding and whether the clause allowing for an independent expert was mandatory or discretionary. The court also had to consider the intention of the parties regarding the nature of the dispute and the construction issues.
The court found that the clause permitting resolution by arbitration was binding, and therefore, the dispute should be resolved by arbitration. The court noted that the use of the word 'may' in the clause referring to an independent expert indicated a discretionary process rather than a mandatory one. The court concluded that the parties intended the dispute to be resolved through arbitration, and not by an independent expert, due to the nature of the construction issues involved. The court's interpretation was influenced by previous cases such as Manningham City Council v Dura (Australia) Constructions Pty Ltd and Oakton Services Pty Ltd v Tenix Solutions IMES Pty Ltd.
The court ordered that the dispute regarding the extension of time claim be referred to arbitration, in accordance with the binding arbitration clause in the contract. The court emphasised the importance of interpreting the contract in line with the intention of the parties, considering the nature of the dispute and the construction issues at hand. The court's decision was based on a careful analysis of the contract terms and relevant case law, providing clarity for the parties in resolving their dispute.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.