FEDERAL COURT OF AUSTRALIA
BHP STEEL (AIS) PTY LTD v CONSTRUCTION, FORESTRY, MINING & ENERGY UNION [2000] FCA 1853
CONTEMPT - in respect of injunctive relief obtained by employer requiring the cessation of work stoppages by Union members - liability of Union for failure to effect prompt compliance by directing members to return to work - where Orders made ex parte in absence of Union representatives - circumstances surrounding communication of orders to Union officials and adequacy of response - relevance of different action taken by officials in the two states to which the Orders applied - responsibility of officials at different levels of Union hierarchy to effect compliance - observations on creditworthiness of Union’s sole witness and inferences available in the context of failure to call other officials with relevant involvement.
Workplace Relations Act 1996 s 127
Australian Industry Group v Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union & Ors [2000] FCA 629 Discussed
Concrete Constructions Pty Ltd v Plumbers & Gasfitters Employees’ Union & Anor (1987) 15 FCR 64 Applied
Australian Consolidated Press Ltd v Morgan (1965) 112 CLR 483 cited
Jones v Dunkel (1959) 101 CLR 298 Applied
Minister for Aboriginal & Torres Strait Islander Affairs v State of Western Australia (1996) 67 FCR 40 Cited
Australasian Meat Industry Employees’ Union v Mudginberri Station Pty Ltd (1986) 161 CLR 98 Cited
Witham v Holloway (1995) 183 CLR 525 Cited
Attorney-General for New South Wales v Mayas Pty Ltd (1988) 14 NSWLR 342 Cited
Sun Newspapers Pty Ltd v Brisbane TV Ltd (1989) 92 ALR 535 Cited
Windsurfing International Inc v Sailboards Australia Pty Ltd (1986) 19 FCR 110 Cited
MacLeod v Australian Securities Commission, unreported, Full Court of the Federal Court of Australia, 13 August 1993 CitedBHP STEEL (AIS) PTY LTD v CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
Q 9 OF 2000KIEFEL J
BRISBANE
15 DECEMBER 2000
IN THE FEDERAL COURT OF AUSTRALIA
QUEENSLAND DISTRICT REGISTRY
Q 9 OF 2000
BETWEEN:
BHP STEEL (AIS) PTY LTD
ACN 000 019 625
APPLICANTAND:
CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
RESPONDENTJUDGE:
KIEFEL J
DATE OF ORDER:
15 DECEMBER 2000
WHERE MADE:
BRISBANE
THE COURT DECLARES THAT:
1.The Construction, Forestry, Mining and Energy Union is guilty of contempt of this Court by its conduct in breaching the Order made against it on 7 February 2000 by continuing strike action and authorising its members to stop performing work and procuring and authorising its members to take further strike action.
THE COURT ORDERS THAT:
2.The further hearing of the motion on the question of penalty is adjourned to a date to be fixed.
3.The respondent pay the applicant’s costs of the motion including any reserved costs.
Note:Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
IN THE FEDERAL COURT OF AUSTRALIA
QUEENSLAND DISTRICT REGISTRY
Q 9 OF 2000
BETWEEN:
BHP STEEL (AIS) PTY LTD
ACN 000 019 625
APPLICANTAND:
CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
RESPONDENT
JUDGE:
KIEFEL…
Keep reading for free
Create a free CaseChat account to read BHP Steel (AIS) Pty Ltd v Construction, Forestry, Mining and... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2000] FCA 1853
- Decision Date
CaseChat Overview and Summary
The legal issues before the court involved the interpretation and enforcement of the Federal Court injunction, the obligations of the Union under the injunction, and the consequences of the Union's alleged failure to comply with the injunction. The court had to determine whether the Union's actions constituted a breach of the injunction and, if so, what the appropriate remedies and penalties should be.
The court's reasoning focused on the Union's obligations under the injunction and the evidence presented regarding the Union's compliance. The court examined the Union's actions and communications in response to the injunction, including the timing and content of communications between Union officials. The court found that the Union had not taken sufficient steps to ensure compliance with the injunction, leading to a significant work stoppage. The court concluded that the Union's actions constituted a breach of the injunction and ordered the Union to pay the applicant's costs of the motion, including any reserved costs.
The court adjourned the further hearing of the motion on the question of penalty to a date to be fixed, indicating that additional considerations would be needed to determine the appropriate penalty for the Union's breach of the injunction.
Orders
Orders of the court
2. The further hearing of the motion on the question of penalty is adjourned to a date to be fixed.
3. The respondent pay the applicant’s costs of the motion including any reserved costs.
Note:
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Established by: KIEFEL J