SUPREME COURT OF QUEENSLAND
CITATION:
Baker v Minister for Employment Skills and Mining & Anor [2012] QSC 160
PARTIES:
MICHAEL VINCENT BAKER
(applicant)
v
MINISTER FOR EMPLOYMENT, SKILLS AND MINING
(first respondent)
and
QCLNG PIPELINE PTY LTD ACN 140 760 612
(second respondent)FILE NO/S:
2493 of 2012
DIVISION:
Trial
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court of Queensland
DELIVERED ON:
22 June 2012
DELIVERED AT:
Brisbane
HEARING DATE:
8 May 2012
JUDGE:
Dalton J
ORDER:
I declare void the decision of the first respondent to grant a part 5 permission pursuant to s 467 of the Act made on 17 February 2012 over Lot 5 WK 207 owned by the applicant.
CATCHWORDS:
ENERGY AND RESOURCES – GAS – PIPES AND MAINS – GENERALLY – where the second respondent has a point-to-point licence to build a pipeline which will pass over the applicant’s rural property – where the second respondent applied for a part 5 permission to enter the land owned by the applicant to construct or operate a pipeline – where the material before the Minister at the end of the consultation period did not accurately identify the land to which the part 5 permission related
ADMINISTRATIVE LAW – JUDICIAL REVIEW – GROUNDS OF REVIEW – PROCEDURAL FAIRNESS – GENERALLY – where the consultation notice did not specify the land over which part 5 permission was sought – where this information was only received two business days before the end of the 20 business days’ consultation period – whether the applicant was appraised of the land that was the subject of the application – whether the applicant was given sufficient opportunity to make submissions about the specific piece of land which was the subject of the part 5 permission application – whether there would have been a different result had the applicant been appraised of the subject land from the time of the delivery of the consultation notice
Judicial Review Act 1991 (Qld)
Petroleum and Gas (Production and Safety) Act 2004 (Qld)Annetts v McCann (1990) 170 CLR 596
Hansen Yuncken Pty Ltd v Ian James Erickson [2011] QSC 327
Kioa v West (1985) 159 CLR 550
Queensland Police Credit Union Ltd v Criminal Justice Commission [2000] 1 Qd R 626
Re Minister for Immigration and Multicultural Affairs; ex parte “A” [2001] HCA 77
Upham v The Grand Hotel (1999) 74 SASR 557COUNSEL:
Mr A J H Morris QC for the applicant
Mr S Hornemann-Wren SC, with Mr A Scott for the first respondent
Mr T P Sullivan SC, with Mr S S Hooper for the second respondentSOLICITORS:
Creevey Russell for the applicant
Crown Law for the first respondent
Corrs Chambers Westgarth for the second respondent
This is an application for a statutory order of review – s 20 Judicial Review Act 1991 (Qld). Various grounds are advanced in the application. Nonetheless, counsel for the applicant conceded he could not succeed unless he showed that the first of them – which alleges a breach of the rules of…
Keep reading for free
Create a free CaseChat account to read Baker v Minister for Employment Skills and Mining and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] QSC 160
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether Baker was adequately informed about the land that was the subject of the application and whether Baker was given a sufficient opportunity to respond to the specific details of the proposed pipeline route. The legal issues centered on whether the Minister's decision was made in a manner that complied with the principles of procedural fairness, particularly given that the specific land was not clearly identified until very close to the end of the consultation period. The court also had to consider whether Baker would have provided different submissions had they been informed of the exact land from the outset.
In ruling on these issues, the court found that the Minister's decision process did not comply with the requirements of procedural fairness. The court determined that the late disclosure of the specific land meant that Baker was not given a fair opportunity to respond to the precise details of the proposed pipeline route. This failure meant that the Minister's decision was flawed and, therefore, invalid. Consequently, the court declared the Minister's decision to grant part 5 permission over Baker's land void.
Orders
Orders of the court
I declare void the decision of the first respondent to grant a part 5 permission pursuant to s 467 of the Act made on 17 February 2012 over Lot 5 WK 207 owned by the applicant.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi