BAE Systems Australia Ltd v Cubic Defence New Zealand Ltd

Link copied
Case Copied 40 min read

FEDERAL COURT OF AUSTRALIA

BAE Systems Australia Ltd v Cubic Defence New Zealand Ltd [2011] FCA 1434

Citation: BAE Systems Australia Ltd v Cubic Defence New Zealand Ltd [2011] FCA 1434
Parties: BAE SYSTEMS AUSTRALIA LIMITED v CUBIC DEFENCE NEW ZEALAND LTD
File number: SAD 302 of 2011
Judge: BESANKO J
Date of judgment: 14 December 2011
Catchwords:

CONTRACTS — application for declaration that respondent’s purported termination of contract was unlawful and invalid — where issue of termination of contract was to be decided as a separate question from the related Trade Practices Act 1974 (Cth) cause of action — where respondent had contracted with Commonwealth to provide defence supplies and support — where respondent entered into ‘back to back’ subcontract with applicant for provision of some supplies and support — where both contracts contained an ‘acquisition phase’ and an ‘operate and support/manage’ phase (‘O and S/M’) — where Commonwealth sought to terminate its contract for convenience after the acquisition phase and enter into new form of contract with respondent for the O and S/M phase with the terms and conditions remaining substantially the same — where Commonwealth and respondent entered into deed terminating contract and entered a new contract — where respondent purportedly terminated its subcontract with the applicant in reliance on a clause entitling it to terminate for convenience where it had received notice that Commonwealth had terminated for convenience — whether entry into deed and new contract constituted notice by Commonwealth of termination of main contract — whether deed and new contract were really reduction in scope or variation of the main contract which did not entitle respondent to terminate the subcontract — whether the subcontract contained implied terms that neither party would by its own motion prevent the other’s performance of the subcontract, that neither party would do anything to destroy efficacy of the parties’ bargain, and that each party would do all things necessary to enable the other to have the benefit of the contract — whether implied term required respondent to enter into deed varying rather than terminating its contract with Commonwealth — whether respondent obliged by implied term of cooperation to pass on new contractual provisions as variations to the existing subcontract

Held: The respondent had validly and lawfully terminated the subcontract.      

Legislation: Competition and Consumer Act 2010 (Cth) Schedule 2
Jurisdiction of Courts (Cross-Vesting) Act 1987 (NSW) s 5
Federal Court Rules r 30.01
Cases cited:

Australis Media Holdings Pty Ltd v Telstra CorporationLtd (1998) 43 NSWLR 104, cited
Commissioner of Taxation of the Commonwealth of Australia v Sara Lee Household and Body Care (Australia) Pty Limited (2000) 201 CLR 520, cited
Concut Pty Ltd v Worrell (2000) 176 ALR 693, cited
Dan v Barclays Australia Ltd (1983) 57 ALJR 442, cited

Downer Connect Pty Ltd v McConnell Dowell Constructors (Australia) Pty Ltd (No 2) [2008] VSC 443, cited

Hart v MacDonald (1910) 10 CLR 417, cited
Mackay v Dick (1881) 6 App Cas…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read BAE Systems Australia Ltd v Cubic Defence New Zealand Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] FCA 1434
Decision Date

CaseChat Overview and Summary

In the Federal Court of Australia, BAE Systems Australia Ltd (the applicant) brought an action against Cubic Defence New Zealand Ltd (the respondent) to challenge the respondent's purported termination of a subcontract for the provision of supplies and support services to the LAND 134 Program. The central issue was whether the respondent's termination of the subcontract was valid and lawful, particularly in light of the Commonwealth's termination of a main contract with the respondent. The court was required to determine whether the Commonwealth's entry into a deed and a new contract with the respondent constituted notice of termination for convenience, whether this triggered the respondent's right to terminate the subcontract, and if there were any implied terms in the subcontract that would prevent the respondent from terminating it unilaterally.

The court concluded that the respondent had validly and lawfully terminated the subcontract. It found that the Commonwealth's actions did not constitute a termination for convenience that would trigger the respondent's right to terminate the subcontract. The court also rejected the applicant's claims regarding implied terms in the subcontract, such as terms of cooperation and mutual support, which would have prohibited the respondent from terminating the subcontract. The court held that the respondent's termination of the subcontract was lawful and valid, and the Commonwealth's actions did not entitle the respondent to terminate the subcontract.

As a result, the court answered the separate question in the affirmative, confirming that the respondent's termination of the subcontract was valid and lawful. Consequently, the respondent was entitled to a declaration that the subcontract had been validly terminated, an order for specific performance of certain obligations, and orders restraining the applicant from performing work under the subcontract or entering Commonwealth land. The court scheduled a hearing to address any consequential and other orders.

Orders

Orders of the court

1. The separate question:

Does the letter dated 31 October 2011 enclosing the Termination Directions and Schedule from the Respondent to the Applicant amount to a valid termination of the Contract for the Provision of Supplies and Support Services to the LAND 134 Program (Contract Number: SC-BAE_AU_CTC-LIS) entered into on 9 June 2003 between the Applicant and the Respondent (Subcontract) pursuant to clause 12.3.1 of the Subcontract?

be answered, yes.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

The parties have agreed that certain orders will follow depending upon the answer to the separate question. It is agreed that if the answer to the question is yes, then the respondent is entitled to a declaration that the Subcontract has been validly terminated; an order that the applicant specifically perform the obligations set out in the Termination Directions and Schedule; an order that the Applicant, by itself, its employees or agents be restrained from undertaking work under the Subcontract, save for performance of the obligations set out in the Termination Directions and Schedule; and an order that from 23 December 2011 the Applicant by itself, its employees or agents be restrained from entering the Commonwealth land the subject of the Subcontract for the purpose of the Subcontract. It is agreed that if the answer to the question is no, then the Applicant is entitled to a declaration that the Respondent’s purported termination for convenience of the Subcontract in purported reliance on clause 12.3.1 of the Contract is unlawful and invalid and a declaration that the respondent’s purported termination of the Contract for convenience in purported reliance on clause 12.3.1 of the Contract constitutes a breach of the Contract by the respondent.THE FACTS Both the applicant and the respondent are corporations which carry on business in Australia as defence contractors. On 9 June 2003 the applicant and the respondent entered into a ‘Contract for the Provision of Supplies and Support Services to the LAND 134 Program’ (Contract Number SC-BAE_AU_CTC-LIS). This contract is referred to in the separate question as the Subcontract and I will refer to it in that way. The recitals to the Subcontract are in the following terms:A.The Commonwealth of Australia represented by the Department of Defence ABN 68706814312 (the ‘Commonwealth’) has a requirement for the supply, operation, management support and maintenance of the core, live-simulation, range instrumentation and information systems for the Combat Training Centre – Live Simulation, Range Instrumentation and Information System (CTC-LIS).B.The Prime Contractor, has been selected by the Commonwealth and has entered into a contract to provide the CTC-LIS.C.The Subcontractor has offered to provide the Supplies and Services to the Prime Contractor on the terms set out in the Contract.D.The Prime Contractor has agreed to accept the offer by the Subcontractor on the terms set out in the Contract. The Subcontract commenced on the effective date of 31 January 2003. The Subcontract provided for two phases, an acquisition phase and an operate and support/manage (‘O and S/M’) phase. The acquisition phase of the Subcontract is complete. The O and S/M phase of the Subcontract commenced on the system acceptance date in December 2006 and continues for an initial period of seven years thereafter unless terminated earlier in accordance with the Subcontract. Since the commencement of the Subcontract it has been amended on various occasions pursuant to agreed Contract Change Proposals (‘CCP’).

Evidence

Evidence Before The Court

Decision

Reasons for decision

The applicant’s arguments having regard to the express terms of the Subcontract and the implied terms it alleges must be rejected.CONCLUSION The separate question should be answered in the affirmative. I will hear the parties on consequential and other orders.

Ratio Decidendi

Legal Principle Established