FEDERAL COURT OF AUSTRALIA
Australian Securities and Investments Commission v Rio Tinto Limited (No 2) [2022] FCA 184
File number(s): NSD 290 of 2018 Judgment of: YATES J Date of judgment: 7 March 2022 Catchwords: CORPORATIONS – admitted contravention of s 674(2) of the Corporations Act 2001 (Cth) – continuous disclosure obligations – contravention of a financial services civil penalty provision – appropriate penalty in all the circumstances Legislation: Corporations Act 2001 (Cth) ss 111AL, 674, 676, 677, 1317DA, 1317E, 1317G
Evidence Act 1995 (Cth) s 191
ASX Listing Rules r 3.1
Cases cited: Australian Building and Construction Commissioner v Construction, Forestry, Mining and Energy Union [2017] FCAFC 113; 254 FCR 68
Australian Competition and Consumer Commission v Universal Music Australia Pty Ltd (No 2) [2002] FCA 192; 201 ALR 618
Australian Securities and Investments Commission v Hochtief Aktiengesellschaft [2016] FCA 1489; 117 ACSR 589
Australian Securities and Investments Commission v Newcrest Mining Ltd [2014] FCA 698; 101 ACSR 46
Australian Securities and Investments Commission v Westpac Banking Corporation [2018] FCA 1701; 131 ACSR 585
Australian Securities and Investments Commission, in the matter of Chemeq Limited (ACN 009 135 264) v Chemeq Limited (ACN 009 135 264) [2006] FCA 936; 234 ALR 511
Commonwealth v Director, Fair Work Building Industry Inspectorate [2015] HCA 46; 258 CLR 482
Flight Centre Ltd v Australian Competition and Consumer Commission (No 2) [2018] FCAFC 53; 260 FCR 68
Division: General Division Registry: New South Wales National Practice Area: Commercial and Corporations Sub-area: Corporations and Corporate Insolvency Number of paragraphs: 60 Date of hearing: 28 February 2022 Counsel for the Plaintiff: Mr M Darke SC and Ms S Patterson Solicitor for the Plaintiff: Australian Government Solicitor Counsel for the First Defendant: Mr N Young QC, Mr D Thomas SC, and Ms E Bathurst Solicitor for the First Defendant: Ashurst Australia Counsel for the Second Defendant: Mr N Hutley SC and Mr J Hutton Solicitor for the Second Defendant: Jones Day Counsel for the Third Defendant: Mr J Sheahan QC and Mr D Blazer Solicitor for the Third Defendant: Allen & Overy ORDERS
NSD 290 of 2018 BETWEEN: AUSTRALIAN SECURITIES AND INVESTMENTS COMMISSION
Plaintiff
AND: RIO TINTO LIMITED ACN 004 458 404
First Defendant
THOMAS ALBANESE
Second Defendant
GUY ELLIOTT
Third Defendant
ORDER MADE BY:
YATES J
DATE OF ORDER:
7 MARCH 2022
THE COURT DECLARES THAT:
1.The first defendant contravened s 674(2) of the Corporations Act 2001 (Cth) (Corporations Act) on one occasion on and from 21 December 2012 continuing until 17 January 2013, in circumstances where:
(a)on 21 December 2012, the first defendant became aware of the Orebody Information;
(b)the Orebody Information was not generally available within the meaning of s 676 of the Corporations Act and for the purpose of s 674(2)(c)(i) of the Corporations Act;
(c)the Orebody Information was information that a reasonable person would have expected, if it had been generally available, to have had a material effect on the price…
Keep reading for free
Create a free CaseChat account to read Australian Securities and Investments Commission v Rio Tinto... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] FCA 184
- Decision Date
CaseChat Overview and Summary
The court examined the admitted contravention of section 674(2) of the Corporations Act and the appropriateness of the penalty proposed by ASIC, which was $750,000. The court considered the submissions of both ASIC and RTL, as well as the seriousness of the contravention. The court noted that RTL had not been found to have contravened its continuous disclosure obligations in the past, which was a mitigating factor. However, the court found the contravention to be serious and, therefore, an appropriate penalty should be imposed. The court was satisfied that the proposed penalty of $750,000 was appropriate in all the circumstances.
The court made the proposed declaration that RTL had contravened section 674(2) of the Corporations Act. It also imposed a monetary penalty of $750,000 on RTL, ordered RTL to pay ASIC's costs of the proceedings, and dismissed the proceedings against the two former executives with no order as to costs. The court found that the proposed orders were appropriate given the admitted contravention and the circumstances of the case.
Orders
Orders of the court
2. Pursuant to s 1317G(1A) of the Corporations Act in respect of the contravention the subject of the above declaration, the first defendant pay a pecuniary penalty to the Commonwealth of Australia in the sum of $750,000.
3. The first defendant pay the plaintiff’s costs of and incidental to these proceedings.
4. The proceedings against the first defendant otherwise be dismissed.
5. The proceedings against the second and third defendants be dismissed on the basis that there be no order as to costs as between the plaintiff and the second and third defendants.
In this order, Orebody Information means, in relation to mining and exploration assets the first defendant held (through subsidiaries) in the Moatize Basin in Mozambique, known as the RTCM Coal Projects and the Minjova Tenements, and which it operated through a business unit called Rio Tinto Coal Mozambique (RTCM), information that:
(a) there was a reduction in expected recoverable and mineable volumes of coking coal, or reduced degree of confidence in the potential economic extraction of the coal deposits, in respect of the RTCM Coal Projects and the Minjova Tenements; and
(b) the quality and quantity of the coal resources in respect of the RTCM Coal Projects and the Minjova Tenements were not what had previously been expected,
such that:
(c) RTL’s coal projects in the Moatize Basin were not highly prospective;
(d) the RTCM Coal Projects and the Minjova Tenements did not provide an opportunity to grow and develop a world class basin of high quality coking coal; and
(e) the RTCM Coal Projects and the Minjova Tenements were no longer economically viable as long-life, large-scale, Tier 1 coking coal resources.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi