Australian Energy Regulator v CAM Engineering and Construction Pty Ltd (Costs)

Link copied
Case Copied 7 min read

FEDERAL COURT OF AUSTRALIA

Australian Energy Regulator v CAM Engineering and Construction Pty Ltd (Costs) [2025] FCA 972  

File number: NSD 1187 of 2023
Judgment of: SARAH C DERRINGTON J
Date of judgment: 18 August 2025
Catchwords: COSTS – where respondent conceded to making of declarations in respect of admitted contravention of s 112(2) of the National Energy Retail Law (NSW) at initial trial – where admissions made eight months after proceeding commenced and after completion of the applicant’s evidence – where no dispute as to facts underlying the contravening conduct – where applicant seeks costs on standard basis in a fixed amount – where respondent did not oppose awarding of those costs
Legislation: Federal Court Rules 2011 (Cth) r 40.02(b)
Cases cited:

Australian Energy Regulator v CAM Engineering and Construction Pty Ltd [2025] FCA 737

Avetmiss Easy Pty Ltd v Australian Skills Qualifications Authority (No 2) [2014] FCA 444; 315 ALR 131

Beach Petroleum NL v Johnson (No 2) (1995) 57 FCR 119

Hancock v Rinehart (Lump Sum Costs) [2015] NSWSC 1640

Jadwan Pty Ltd v Rae & Partners (A Firm) (No 7) [2022] FCA 1174

Julien v Secretary, Department of Employment and Workplace Relations (No 2) [2009] FCA 1259

Keen v Telstra Corp Ltd (No 2) [2006] FCA 930

Paciocco v Australia and New Zealand Banking Group Limited (No 2) [2017] FCAFC 146; 253 FCR 403

Division: General Division
Registry: New South Wales
National Practice Area: Commercial and Corporations
Sub-area: Economic Regulator, Competition and Access
Number of paragraphs: 14
Date of last submission: 8 August 2025
Date of hearing: The matter was determined on the papers
Counsel for the Applicant: Mr M Peckham
Solicitor for the Applicant: Norton Rose Fulbright Australia
Counsel for the Respondent: The sole director of the Respondent was granted leave to make submissions on behalf of the Respondent

ORDERS

NSD 1187 of 2023
BETWEEN:

AUSTRALIAN ENERGY REGULATOR

Applicant

AND:

CAM ENGINEERING AND CONSTRUCTION PTY LTD (ACN 611 016 570)

Respondent

ORDER MADE BY:

SARAH C DERRINGTON J

DATE OF ORDER:

18 AUGUST 2025

THE COURT ORDERS THAT:

1.Within 28 days of the date of these Orders, the respondent pay the applicant’s costs of and incidental to the proceeding, fixed in the amount of $288,504.93.

Note:   Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


REASONS FOR JUDGMENT

SARAH C DERRINGTON J:

INTRODUCTION

  1. On 4 July 2025, I delivered judgment in respect of the appropriate pecuniary penalty against CAM Engineering and Construction Pty Ltd for its admitted contraventions of the National Energy Retail Law (NSW) in proceedings commenced by the Australian Energy Regulator (AER): Australian Energy Regulator v CAM Engineering and Construction Pty Ltd [2025] FCA 737 (J). I ordered the payment of a pecuniary penalty of $250,000 and granted declarations of contravention and remedial action in the terms agreed to by the parties.

  2. The remaining issue is costs. Pursuant to r 40.02(b) of the Federal Court Rules 2011 (Cth), the AER…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Australian Energy Regulator v CAM Engineering and Constructi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2025] FCA 972
Decision Date

CaseChat Overview and Summary

In the matter of the Australian Energy Regulator and CAM Engineering and Construction Pty Ltd, the Federal Court was tasked with determining costs in relation to a proceeding concerning contraventions of the National Energy Retail Law (NSW). The Australian Energy Regulator (AER) brought an action against CAM Engineering and Construction Pty Ltd (CAM) for breaches of the law, specifically under section 112(2). The primary dispute centred around the costs incurred by the AER during the proceedings, with CAM conceding to the making of declarations regarding the admitted contraventions.

The court was required to address whether the AER was entitled to costs on a standard basis, given that CAM had conceded to the making of the declarations and there was no dispute over the facts underlying the contraventions. The key legal issue was the appropriate quantum of costs to be awarded and whether the AER’s application for a fixed amount of costs was justified, considering the circumstances of the case, including the timing of the admissions and the completion of the AER’s evidence.

The court found that the AER was entitled to its costs on a standard basis. It determined that the fixed amount of $288,504.93 was appropriate, taking into account the totality of the proceedings and the fact that CAM did not oppose the application for costs. The court concluded that the admissions came relatively late in the process, after the completion of the AER’s evidence, and acknowledged that such factors should be considered in determining the quantum of costs. Consequently, the court ordered that CAM pay the AER’s costs within 28 days of the date of the orders, as fixed.

1. Within 28 days of the date of these Orders, the respondent pay the applicant’s costs of and incidental to the proceeding, fixed in the amount of $288,504.93.

Orders

Orders of the court

1. Within 28 days of the date of these Orders, the respondent pay the applicant’s costs of and incidental to the proceeding, fixed in the amount of $288,504.93.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established