AUSTRALIAN COMPETITION TRIBUNAL
Application by APA GasNet Australia (Operations) Pty Limited (No 2)
[2013] ACompT 8
Citation: Application by APA GasNet Australia (Operations) Pty Limited (No 2) [2013] ACompT 8 Parties: APA GASNET AUSTRALIA (OPERATIONS) PTY LIMITED File number: ACT 2 of 2013 Tribunal: MANSFIELD J (PRESIDENT)
PROFESSOR D ROUND (MEMBER)
MR R STEINWALL (MEMBER)Date of judgment: 18 September 2013 Catchwords: COMPETITION LAW – National Gas Law (NGL) – review of access decision of Australian Energy Regulator (AER) – transition of access arrangement under National Third Party Access Code for Natural Gas Pipeline Systems to NGL – new access arrangement commenced on 1 July 2013 – whether previous access arrangement left an Interval of delay so rule 92 of the National Gas Rules (NGR) applied and AER properly took tariffs received during interval of delay into account in fixing reference tariffs – previous access arrangement provided revisions commencement date is “the later of 1 January 2013 and the date on which approval of revisions to this Access Arrangement take effect”
Held: previous access arrangement continued to operate to 30 June 2013, so no interval of delay existed for rule 92 to apply
COMPETITION LAW – National Gas Law (NGL) – review of access decision of Australian Energy Regulator (AER) – determination of opening capital base at commencement of earlier access period under rule 77(2)(a) NGR – adjustment for difference between estimated and actual capital expenditure incurred in that opening capital base – whether adjustment included adjustment for revenue earned on difference as well as the difference in capital expenditure
Held: adjustment should not include adjustment for revenue earned on difference in capital expenditure
COMPETITION LAW – National Gas Law (NGL) – review of access decision of Australian Energy Regulator (AER) – depreciation allowance – consideration rule 89 NGR – limited discretion of AER – depreciation proposal of access provider did not include inflation adjustment so its revenue profile would be greater in earlier years and tariff profile over period flatter – AER satisfied that proposal did not meet requirement of rule 89(1)(a) as it did not promote efficient growth in market for reference services – common anticipation of significant lessening of reference tariffs from previous access arrangement period – consideration of capacity constraints
Held: AER properly exercised limited discretion and refused to approve proposed depreciation schedule in circumstances
COMPETITION LAW – National Gas Law (NGL) – review of access decision of Australian Energy Regulator (AER) – rate of return on equity – methodology to determine rate of return on equity discussed – s 87 NGR – consideration of dividend growth model assessment
Held: methodology and inputs into modelling by AER not shown to be erroneous
COMPETITION LAW – National Gas Law (NGL) – review of access decision of Australian Energy Regulator (AER) – consideration of interaction of ss 65, 258 and 261 of NGL and rules 59-64 NGR
Legislation: National Gas (Victoria) Act 2008 (Vic)
National Gas (South Australia) Act 2008 (SA)
The National Gas (Victoria) Act 2008 (Vic)
Keep reading for free
Create a free CaseChat account to read Application by APA GasNet Australia (Operations) Pty Limited... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2013] ACompT 8
- Decision Date
CaseChat Overview and Summary
The primary legal issues were whether the previous access arrangement created an interval of delay for rule 92 of the NGR to apply, the appropriate method for adjusting the opening capital base, whether the depreciation proposal complied with rule 89 of the NGR, and the correctness of the methodology used by AER to determine the rate of return on equity. The court had to assess the reasoning and evidence provided by AER to ensure the decisions were legally sound and consistent with the statutory framework.
The court found that the previous access arrangement continued to operate until 30 June 2013, thereby negating any interval of delay under rule 92 of the NGR. It held that the adjustment for the difference between estimated and actual capital expenditure should not include any adjustment for revenue earned on that difference. Regarding the depreciation allowance, the court concluded that AER properly exercised its limited discretion in refusing to approve the proposed depreciation schedule as it did not meet the requirements of rule 89(1)(a) of the NGR. Finally, the court determined that the methodology and inputs used by AER in determining the rate of return on equity were not shown to be erroneous.
The court upheld the AER's decisions on all points, affirming the validity of the regulatory actions taken.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.