Al Builders Pty Ltd v Fatseas

Case [2015] QCAT 166


CITATION: AL Builders Pty Ltd v Fatseas [2015] QCAT 166
PARTIES: A L Builders Pty Ltd
(Applicant)
v
Nicholas Fatseas and Tricia Fatseas
(Respondents)
APPLICATION NUMBER: BDL302-12
MATTER TYPE: Building matters
HEARING DATE: 1- 5 December 2014
HEARD AT: Brisbane
DECISION OF: Member King-Scott
DELIVERED ON: 8 May 2015
DELIVERED AT: Brisbane
ORDERS MADE:

1.    The Applicant’s claim is dismissed;

2.    The Respondents’ counterclaim is allowed in the sum of $191,559.86 with interest of $14,064.34;

3.    The Applicant to pay the Respondents $205,624.20 by 4.00 pm on 31 July 2015.

4.    I direct that written submissions, if any, in respect of costs be filed by the Respondents by 1 June 2015 and any reply, by the Applicant, by 14 June 2015.

CATCHWORDS: Building dispute – Fixed price contract or costs plus contract – Contract not in writing – Acceptance by conduct – Written contract a sham – Effect of Domestic Building Contracts Act 2000 on oral costs plus contract and s. 55(4) discretion – implication of terms – quantum meruit claim – Failure to mitigate

APPEARANCES and REPRESENTATION (if any):

APPLICANT: Mr L D Bowden of Counsel instructed by Nicholas Radich solicitor.
RESPONDENT: Mr M Williams of Counsel instructed by Robert Casalegno solicitor.

REASONS FOR DECISION

Introduction

[1]The Respondents, Mr and Mrs Fatseas, entered into a contract with Deep North Developments Pty Ltd (Deep North) to build a house at 20 Admiralty Drive, Paradise Waters in 2007.  That company went into receivership and was unable to complete the contract.  The Applicant, A L Builders Pty Ltd (“A L Builders”), submitted a quote to the Building Services Authority (BSA) to rectify and complete the work, There were two quotes, the Applicant’s was the lowest at $1,098,939.60. Previously, the Applicant had been involved in the original construction as a form work subcontractor.

[2]The house was designed by architect Paul Clout. It’s construction consisted of wooden floors, wooden louvre windows, curved walls and involved the extensive use of natural stone and marble. All these features created challenges for the builder.  At the time the Applicant took over the construction all of the structural work had been completed.  The house consisted of two storeys and a basement.  The roof was substantially on and the windows and outside doors had been installed.  Some of the internal gyprock lining had been completed.  It seems not to be disputed that the house had reached a lock-up stage.[1] 

[1]Transcript Day 3 1-20 line 3.

[3]Mr and Mrs Fatseas made a successful claim on the Queensland Building Services Authority (QBSA) statutory insurance scheme. An amount of $200,000 as an insurance payment was approved to be paid to the contractor engaged to complete the work.

[4]The Building Services Authority (BSA) invited quotes for rectification work to be undertaken at the Respondents’ property. The Applicant provided a quote in response to an invitation to tender by the BSA. The Applicant responded to the BSA Scope of Work for Incomplete Building Work as follows:

1. To carry out all necessary work to…

Continue reading Al Builders Pty Ltd v Fatseas

Sign in free to access the full text

Details
AGLC
Al Builders Pty Ltd v Fatseas [2015] QCAT 166
Case
[2015] QCAT 166
Decision Date

CaseChat Overview and Summary

Al Builders Pty Ltd brought an action against Fatseas, seeking payment for work completed under an alleged fixed price contract. The case was heard in the Supreme Court of Queensland. The primary dispute was whether the contract between the parties was a fixed price agreement or a costs plus arrangement, and if the former, whether the contract was enforceable despite not being in writing. The crux of the matter was whether the Domestic Building Contracts Act 2000 applied to the oral agreement, and if so, what implications this had for the enforceability of the contract and the availability of the court's discretion under section 55(4).

The court needed to determine whether the contract was a fixed price agreement or a costs plus contract, and if the former, whether it was enforceable despite not being in writing. It was also necessary to consider whether the Domestic Building Contracts Act 2000 applied to the oral agreement and the implications of this on the enforceability of the contract and the court's discretion under section 55(4). Additionally, the court had to address the issue of whether the parties had agreed on a costs plus contract, and if so, whether that agreement was enforceable. The court was also required to consider whether the applicant had failed to mitigate its losses and whether this impacted the quantum of the respondent's entitlement.

The court found that the parties had entered into a costs plus contract and that the written contract was a sham. The court held that the Domestic Building Contracts Act 2006 applied to the oral agreement, but this did not affect the enforceability of the costs plus contract. The court also found that the applicant had failed to mitigate its losses and, as a result, the quantum of the respondent's entitlement was reduced. The court exercised its discretion under section 55(4) of the Act and dismissed the applicant's claim. The court allowed the respondent's counterclaim and ordered the applicant to pay the respondent $205,624.20 by 4.00 pm on 31 July 2015. The court also directed that written submissions, if any, in respect of costs be filed by the respondent by 1 June 2015 and any reply, by the applicant, by 14 June 2015.

Orders

Orders of the court

1. The Applicant’s claim is dismissed;

2. The Respondents’ counterclaim is allowed in the sum of $191,559.86 with interest of $14,064.34;

3. The Applicant to pay the Respondents $205,624.20 by 4.00 pm on 31 July 2015.

4. I direct that written submissions, if any, in respect of costs be filed by the Respondents by 1 June 2015 and any reply, by the Applicant, by 14 June 2015.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.