SUPREME COURT OF QUEENSLAND
CITATION:
AGL Sales (Qld) Pty Limited v Dawson Sales Pty Ltd & Ors [2009] QSC 8
PARTIES:
AGL SALES (QLD) PTY LIMITED
(ACN 121 177 740)
Plaintiff
V
DAWSON SALES PTY LTD
(ACN 087 886 913)
First Defendant
ANGLO COAL (DAWSON) LIMITED
(ACN 100 155 342)
Second Defendant
MITSUI MOURA INVESTMENT PTY LTD
(ACN 088 091 356)
Third Defendant
FILE NO/S:
10731 of 2007
DIVISION:
Trial Division
PROCEEDING:
Hearing
ORIGINATING COURT:
Supreme Court Brisbane
DELIVERED ON:
9 February 2009
DELIVERED AT:
Brisbane
HEARING DATE:
28, 29, 20, 31 July; 1, 4, 5, 6, 7, 8, 18, 19, 20, 21, 22 August; 1, 2, 3, 4, 5, September 2008
JUDGE:
McMurdo J
ORDER:
1. It is declared that:
(a) The matters set out in the letter from the first defendant to the plaintiff dated 9 July 2007 do not constitute a Force Majeure Event as defined under the Gas Sale Agreement between the parties and do not entitle the first defendant to curtail the supply of gas (in whole or in part) under clause 14 of that Agreement;
(b) The MDQ within the schedule to that Agreement of 18,000 gigajoules per day has not been amended by that letter of 9 July 2007, by the Notice purportedly issued by the first defendant to the plaintiff on 10 December 2007 or otherwise.
2. The plaintiff’s claim will be stood over for further submissions, if any, as to other relief according to the reasons for judgment.
3. The counterclaim is dismissed.
CATCHWORDS:
CONTRACT LAW-GENERAL CONTRACTUAL PRINCIPLES- CONSTRUCTION AND INTERPRETATION OF CONTRACTS-where the plaintiff purchases coal seam gas from defendant- where the defendant relies on force majeure clause to vary contract - where defendant did not apply good engineering and operation practice- whether geology constitutes force majeure event
Gamlen Chemical Co (Australasia) Pty Ltd v Shipping Corporation of India Ltd [1978] 2 NSWLR 12
Energy Assets (Restructuring and Disposal) Act 2006 (Qld)
COUNSEL:
Mr P O’Shea SC with Ms S Brown for the Plaintiff
Mr GA Thompson SC with Mr S Cooper for the defendants
SOLICITORS:
Brian Bartley & Associates as town agents for Gilbert & Tobin for the plaintiff
Mallesons Stephen Jaques for the defendants
The plaintiff (“AGL”) purchases coal seam gas from the first defendant (“Dawson”). The gas is extracted from the Moura Coal Mine and is supplied to AGL under a written contract made in February 2003, which I will call the Agreement. Dawson contracted to supply the gas on behalf of the owners of the mine who are the second and third defendants.
The parties are in dispute as to the amount of gas which must be supplied under the Agreement. It provides for the supply of certain quantities, but it also provides that in some circumstances, described as a “Force Majeure Event”, Dawson may supply less gas.
Dawson says that it has encountered unforeseen difficulties in extracting gas at Moura, due to the particular geology of part of its field, and that the relevant events…
Keep reading for free
Create a free CaseChat account to read AGL Sales (Qld) Pty Limited v. Dawson Sales Pty Ltd & Ors and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QSC 8
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the geological conditions cited by the defendants constituted a force majeure event under the Gas Sale Agreement, and if the defendants' actions were in line with their contractual obligations, particularly concerning the application of good engineering and operation practices. Additionally, the court had to decide if the defendants' actions constituted a breach of contract.
The court found that the defendants' reliance on the force majeure clause was not justified as the geological conditions did not meet the definition of a force majeure event under the agreement. The court emphasised the need for the defendants to apply good engineering and operation practices and concluded that the defendants' actions were not in line with these requirements. The court also determined that the defendants had not provided sufficient evidence to support their claim that the geological conditions constituted a force majeure event. Consequently, the court declared that the defendants were not entitled to curtail the gas supply under the terms of the agreement.
The court made a declaration that the matters set out in the letter from the first defendant to the plaintiff dated 9 July 2007 did not constitute a force majeure event and did not entitle the first defendant to curtail the supply of gas. The court also declared that the minimum daily quantity within the schedule to that agreement had not been amended. The plaintiff's claim was to be stood over for further submissions, if any, as to other relief, and the counterclaim was dismissed.
Orders
Orders of the court
1. It is declared that:
(a) The matters set out in the letter from the first defendant to the plaintiff dated 9 July 2007 do not constitute a Force Majeure Event as defined under the Gas Sale Agreement between the parties and do not entitle the first defendant to curtail the supply of gas (in whole or in part) under clause 14 of that Agreement;
(b) The MDQ within the schedule to that Agreement of 18,000 gigajoules per day has not been amended by that letter of 9 July 2007, by the Notice purportedly issued by the first defendant to the plaintiff on 10 December 2007 or otherwise.
2. The plaintiff’s claim will be stood over for further submissions, if any, as to other relief according to the reasons for judgment.
3. The counterclaim is dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi