SUPREME COURT OF QUEENSLAND
CITATION:
Abigroup Contractors Pty Ltd v Multiplex Constructions Pty Ltd & Ors [2003] QSC 173
PARTIES:
ABIGROUP CONTRACTORS PTY LTD
ABN 40 000 201 516(plaintiff / first respondent)
v
MULTIPLEX CONSTRUCTIONS PTY LTD
ABN 96 008 687 063
(first defendant / first applicant)and
WATPAC AUSTRALIA PTY LTD
ABN 71 010 462 816
(second defendant / second applicant)and
THE CROWN in the right of the STATE OF QUEENSLAND through the DIRECTOR GENERAL, DEPARTMENT OF PUBLIC WORKS
ABN 46 752 917
(third defendant / second respondent)FILE NO/S:
No S 3723 of 2003
DIVISION:
Trial Division
PROCEEDING:
Application
ORIGINATING COURT:
Supreme Court
DELIVERED ON:
5 June 2003
DELIVERED AT:
Brisbane
HEARING DATE:
28 May 2003
JUDGE:
Philippides J
ORDER:
Pursuant to s 21 of the Subcontractors’ Charges Act 1974 the first respondent’s notices of claim of charge dated 1 April 2003 and 2 May 2003 be cancelled
CATCHWORDS:
BUILDING AND ENGINEERING CONTRACTS – Subcontractor’s charge – claim for uncertified amounts – application pursuant to s 21 of the Subcontractors’ Charges Act 1974 for cancellation or modification of first respondent’s claims – whether claim for money payable or to become payable under the subcontract – whether claim for money, the payment of which is governed by a provision of the subcontract still to be complied with
Subcontractors’ Charges Act 1974 s 5(2), s 5(6), s 9, s 10(1A), s 21, s 23
Groutco (Australia) Pty Ltd v Thiess Contractors Pty Ltd [1985] 1 Qd R 238
Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd (2002) 18 BCL 322
Riteway Constructions Pty Ltd v Baulderstone Hornibrook Pty Ltd [1998] 2 Qd R 218Re An Application by James Hardie Building Systems Pty Ltd (1999) 15 BCL 199
COUNSEL:
Mr H Fraser QC and Mr P Hastie for the applicants
Mr J Bond SC and Mr D Kelly for the first respondentNo Appearance by the second respondent
SOLICITORS:
Minter Ellison for the applicants
Carter Newell for the first respondentNo Appearance by the second respondent
PHILIPPIDES J:
Background Facts
In May 2001, the applicants, an unincorporated joint venture, entered into a managing contract with the Department of Public Works for the redevelopment of Lang Park. In April 2002, the applicants entered into a subcontract with the first respondent, Abigroup, under which that part of the project known as the Community Infrastructure West Works was subcontracted to the first respondent.
The first respondent claims two charges pursuant to Subcontractors’ Charges Act1974 (“the Act”) over monies payable to the applicants by the Department of Public Works. These concern a notice of charge delivered on 1 April 2003 for the sum of $1,559,158.70 and a further notice of charge delivered on 2 May 2003 for the sum of $1,735,548.10.
The applicants bring this application for cancellation or modification of the charges and for consequential orders pursuant to s 21 of the Act. The applicant’s primary submission is that the notices claim monies that have not been certified as…
Keep reading for free
Create a free CaseChat account to read Abigroup Contractors Pty Ltd v Multiplex Constructions Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] QSC 173
- Decision Date
CaseChat Overview and Summary
The court examined the nature of the claims made by Multiplex, considering whether they related to money payable or to become payable under the subcontract and if there were any conditions precedent that had not been fulfilled. The court found that the claims were for uncertified amounts and that the payment of these amounts was subject to certain conditions within the subcontract that had not been met at the time the claims were made. As such, the court determined that the claims did not constitute valid charges under the Act. The court concluded that the claims for money were not yet payable as they were contingent on the satisfaction of conditions within the subcontract, which had not been complied with.
In light of the findings, the court ordered that the notices of claim of charge dated 1 April 2003 and 2 May 2003 issued by Multiplex be cancelled pursuant to section 21 of the Subcontractors’ Charges Act 1974. This decision effectively disallowed Multiplex from enforcing the claims as charges against Abigroup until the conditions specified in the subcontract were met.
Orders
Orders of the court
Pursuant to s 21 of the Subcontractors’ Charges Act 1974 the first respondent’s notices of claim of charge dated 1 April 2003 and 2 May 2003 be cancelled
Background
Background to the litigation
The matter came before the court on an application by Multiplex under section 21 of the Subcontractors' Charges Act 1974. Multiplex sought an order cancelling or modifying Abigroup's notices of claim of charge. The court heard arguments from both parties on the application. The court considered the Subcontract Agreement, the notices of claim of charge, and the relevant statutory provisions.
Decision
Reasons for decision
1. Whether Abigroup's claim constitutes a claim for money payable or to become payable under the Subcontract Agreement.
2. Whether Abigroup's claim is for money the payment of which is governed by a provision of the Subcontract Agreement still to be complied with.
Held
1. The court held that Abigroup's claim does not constitute a claim for money payable or to become payable under the Subcontract Agreement.
2. The court held that Abigroup's claim is for money the payment of which is governed by a provision of the Subcontract Agreement still to be complied with.
Ratio Decidendi
Legal Principle Established
The court began by examining the nature of Abigroup's claim under the Subcontract Agreement. The court found that the claim in question was not for money payable or to become payable because it did not correspond to a direct entitlement to payment under the terms of the agreement. Instead, the claim was contingent upon the satisfaction of certain conditions that had not yet been fulfilled. This distinction was crucial as it aligned with the provisions of the Subcontractors’ Charges Act 1974, which specifically governs claims that are still subject to future compliance with contractual obligations.
The court then turned to the issue of whether Abigroup's claim was for money governed by a provision of the Subcontract Agreement that had not yet been complied with. The court noted that the claim was indeed contingent upon future actions or events, specifically the certification of the amounts claimed. This meant that the payment was not yet due because the contractual conditions for certification had not been met. The court relied on established legal principles that differentiate between claims for money already earned and those that require further contractual steps before payment is due.
In reaching its decision, the court applied the statutory provisions of section 21 of the Subcontractors’ Charges Act 1974. It held that since Abigroup's claim was contingent on future compliance with the Subcontract Agreement, it was not a claim for money payable or to become payable within the meaning of the Act. The ratio decidendi of this case is that claims for uncertified amounts under a subcontract, which are contingent on future compliance with the subcontract's terms, do not qualify as claims for money payable or to become payable under the Act. The court's decision aligns with the legislative intent to protect against premature claims that do not meet the necessary conditions for payment under the subcontract.