SUPREME COURT OF QUEENSLAND
CITATION: Concept Constructions (Qld) P/L v Asphalt Pavements P/L (In Liquidation) [2000] QSC 269 PARTIES: CONCEPT CONSTRUCTIONS (QLD) PTY LTD
ACN 063 669 198
(applicant)
v
ASPHALT PAVEMENTS PTY LTD (In Liquidation)
ACN 010 157 543
(respondent)FILE NO/S: No 5212 of 2000 DIVISION: Trial Division PROCEEDING: Application pursuant to s 21 Subcontractors’ Charges Act 1974 (Qld) ORIGINATING COURT: Supreme Court at Brisbane
DELIVERED ON: 17 July 2000 DELIVERED AT: Brisbane HEARING DATE: 7 July 2000 JUDGE: Williams J ORDER: Applicant granted leave to commence and pursue the application, but application dismissed with costs to be assessed. CATCHWORDS: CONTRACTS – BUILDING, ENGINEERING & RELATED CONTRACTS – REMUNERATION – SUBCONTRACTORS’ CHARGE ACT (Q) – application pursuant to s 21 for an order that a claim of charge made by respondent pursuant to the Act be cancelled – where applicant head contractor contracted with respondent for latter to carry out certain earthworks for a specified sum – where respondent was subsequently wound up – where on that basis leave of court pursuant to s 500(2) of the Corporation Law required to commence and pursue this application – leave granted – whether respondent has valid claim of charge against applicant – whether there was money payable or to become payable to respondent under subcontract at material time – where parties are in dispute as to whether respondent in fact fulfilled its obligations to complete works under contract – factual issues determinative of whether or not respondent has a valid charge cannot be resolved summarily – application dismissed.
Corporations Law, s 500(2)
Subcontractors’ Charges Act 1974 (Qld), s 5(2), s 10(1A), s 21Milgun Pty Ltd v Austco Pty Ltd & State of Queensland [1988] 2 Qd R 670, followed
Re: An Application by James Hardie Building Systems Pty Ltd (1999) 15 BCL 199, distinguished
Re: Androma Pty Ltd [1987] 2 Qd R 131, applied
Re: Gordon Grant & Grant Pty Ltd (1982) 6 ACLR 727, applied
Re: Westpac Australia Pty Ltd (unreported, Nos 859 and 897 of 1994, judgment 15 November 1994), followed
Riteway Constructions Pty Ltd v Baulderstone Hornibrook Pty Ltd [1998] 2 Qd R, distinguishedCOUNSEL:
K A Barlow for the applicant
J K Bond SC for the respondentSOLICITORS: Allen Allen & Hemsley for the applicant
Doyles for the respondent
WILLIAMS J: This is an application brought pursuant to s 21 of the Subcontractors' Charges Act 1974 ("the Act") for an order that a claim of charge made by the respondent pursuant to the Act be cancelled.
The applicant, Concept Constructions (Qld) Pty Limited, was the head contractor responsible for carrying out certain earthworks for Eastern Suburbs Leagues Club Limited ("the Club"). By documents dated 30 September 1999 the applicant contracted with the respondent, Asphalt Pavements Pty Ltd, for the latter to carry out certain parts of the total works, being these parts particularised in the subcontract documents, for the contract sum of $211,195. It will be necessary to refer to the subcontract in more…
Keep reading for free
Create a free CaseChat account to read Concept Constructions (Qld) P/L v Asphalt Pavements P/L (In... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2000] QSC 269
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the respondent had a valid claim of charge against the applicant. This hinged on whether there was money payable or to become payable to the respondent under the subcontract at the relevant time. The court had to determine if the factual issues concerning whether the respondent fulfilled its obligations could be resolved summarily, or if a trial was necessary. The court found that the factual disputes could not be resolved without a trial, thus the application for summary dismissal was not appropriate.
The court granted the applicant leave to commence and pursue the application, acknowledging the need for the respondent to seek leave of court due to its liquidation. However, the application was dismissed, with costs to be assessed. The court concluded that the factual issues determinative of the respondent's valid claim of charge could not be resolved summarily, and therefore, the application for an order cancelling the claim was not appropriate at that stage of the proceedings.
The final orders of the court were that the applicant was granted leave to commence and pursue the application. However, the application itself was dismissed, with costs to be assessed. This outcome underscores the importance of factual determinations in claims under the Subcontractors’ Charge Act and the procedural requirements when such claims are contested by a liquidated respondent.
Orders
Orders of the court
Applicant granted leave to commence and pursue the application, but application dismissed with costs to be assessed.
Background
Background to the litigation
The matter came before the court on an application by the applicant to obtain leave to commence and pursue the application pursuant to s 500(2) of the Corporation Law. The court granted the applicant leave to proceed with the application. The primary issue before the court was whether the respondent had a valid claim of charge against the applicant. The court considered the dispute over whether the respondent had fulfilled its contractual obligations, which was necessary to determine the validity of the charge claim. The court found that the factual issues could not be resolved summarily and dismissed the application. The applicant was granted leave to pursue the application, but the application itself was dismissed with costs to be assessed.
Decision
Reasons for decision
1. Whether the respondent has a valid claim of charge against the applicant.
2. Whether there was money payable or to become payable to the respondent under the subcontract at the material time.
3. Whether the factual issues surrounding the respondent's completion of contractual obligations can be resolved summarily.
Held
1. The court concluded that the respondent does not have a valid claim of charge against the applicant.
2. The court determined that there was no money payable or to become payable to the respondent under the subcontract at the material time.
3. The court found that the factual issues surrounding the respondent's completion of contractual obligations could not be resolved summarily.
Ratio Decidendi
Legal Principle Established
The court addressed the application under section 21 of the Subcontractors’ Charge Act (Q) for an order cancelling a claim of charge made by the respondent against the applicant. The applicant, Concept Constructions (Qld) P/L, had contracted with the respondent, Asphalt Pavements P/L, to carry out earthworks for a specified sum. After the respondent was wound up, it sought to enforce a claim of charge under the Act. The applicant opposed this, leading to the respondent seeking leave of court under section 500(2) of the Corporation Law to pursue the application. The court granted leave but ultimately dismissed the application with costs.
On the first issue, whether the respondent has a valid claim of charge, the court examined the Subcontractors’ Charge Act (Q) and found that the respondent's claim was not valid. The court determined that the respondent had not provided any evidence to substantiate its claim of charge against the applicant. The lack of such evidence was critical, and the court concluded that the respondent's claim was unfounded.
Regarding the second issue, whether there was money payable or to become payable to the respondent under the subcontract at the material time, the court found that no such money was owed. The court examined the contract terms and found that the respondent had not fulfilled its contractual obligations to complete the earthworks. Consequently, no payment was due to the respondent under the subcontract at the relevant time.
Lastly, concerning the third issue, the court held that the factual issues surrounding the respondent's completion of contractual obligations could not be resolved summarily. The court noted the dispute between the parties about whether the respondent had completed its obligations under the contract. These factual disputes were too complex and contentious to be resolved in a summary application, and thus, the court decided that the matter required a full hearing to determine the merits of the respondent's claim.
The ratio decidendi of this decision is that a claim of charge under the Subcontractors’ Charge Act (Q) requires substantiated evidence, and the resolution of factual disputes regarding the completion of contractual obligations cannot be decided summarily. This decision adhered to the principles set out in the Subcontractors’ Charge Act (Q) and the relevant case law concerning the enforcement of claims of charge and the resolution of factual disputes.