Aalborg CSP A/S v Ottoway Engineering Pty Ltd

Case [2017] SASCFC 158


SUPREME COURT OF SOUTH AUSTRALIA

(Full Court)

AALBORG CSP A/S v OTTOWAY ENGINEERING PTY LTD

[2017] SASCFC 158

Judgment of The Full Court

(The Honourable Chief Justice Kourakis, The Honourable Justice Blue and The Honourable Justice Bampton)

1 December 2017

APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES

CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - STATUTORY REGULATION OF ENTITLEMENT TO AND RECOVERY OF PROGRESS PAYMENTS - PAYMENT CLAIMS

CORPORATIONS - LEGAL CAPACITY AND RELATIONS WITH OUTSIDERS - SERVICE OF DOCUMENT ON COMPANY

Appeal against summary judgment in favour of the plaintiff.

The parties entered into a construction contract within the meaning of the Building and Construction Industry Security of Payment Act 2009 (SA). The appellant is a Danish company. Clause 3 of the contract required all relevant documentation to be provided by the respondent to the appellant in one hard copy and one electronic copy.

The respondent sent to the appellant 22 invoices by email and in addition delivered some or all of them to the appellant in Denmark.  The invoices generally comprised payment claims under the Act.

In May 2016 the respondent sent to the appellant certain formal notices and proceedings in two Supreme Court actions by email and also apparently by delivery to Aalborg’s registered office, being the office of its accountants BDO in Adelaide.

In August 2016 the respondent issued a further invoice/payment claim to the appellant which it delivered only to the appellant’s registered office in Adelaide.

After the appellant did not respond within the requisite 15 days, the respondent instituted the action and sought summary judgment. The appellant relied on three grounds to oppose summary judgment. The Master granted summary judgment. The Master held that section 109X of the Corporations Act 2001 (Cth) empowered service of documents on the registered office and clause 3 of the contract did not affect the position. The Master held that reliance by the appellant on estoppel and misleading conduct was precluded by section 15(4)(b) of the Act and in any event any continuing representation by the respondent was negated by its conduct in May 2016 in serving documents upon the appellant’s registered office.

Held by the Court (allowing the appeal):

1. The Master erred in holding that the decision of the New South Wales Court of Appeal in Falgate Constructions Pty Ltd v Equity Australia Corporation Pty Ltd determined the issue of service under section 109X against the appellant. However, it is unnecessary and undesirable to decide on this appeal constructional issues relating to sections 109X and 601CX of the Corporations Act and clause 3 of the contract and their interaction (at [52]-[54]).

2.  The Master erred in holding that the appellant’s answers based on estoppel and misleading conducted were precluded by section 15(4)(b) of the Act (at [67]).

3.  The Master erred in finding that there was no arguable case for estoppel or misleading conduct to arise on the facts of the dispute (at [78] and [82]).

4.  Appeal allowed, summary judgment set aside…

Continue reading Aalborg CSP A/S v Ottoway Engineering Pty Ltd

Sign in free to access the full text

Details
AGLC
Aalborg CSP A/S v Ottoway Engineering Pty Ltd [2017] SASCFC 158
Case
[2017] SASCFC 158
Decision Date

CaseChat Overview and Summary

The appeal concerned a dispute between Aalborg CSP A/S, a Danish company, and Ottoway Engineering Pty Ltd, an Australian company, regarding a contract for the supply and fabrication of tubular steel towers for a solar-thermal-desal-energy system project. The contract, which was later varied to include labour supply, was the subject of an application for summary judgment. The appeal was heard by the Full Court of the Supreme Court of South Australia.

The primary legal issues before the Full Court were whether the Master erred in granting summary judgment to Ottoway, and whether Aalborg had established a reasonably arguable defence of misleading or deceptive conduct against Ottoway. The Court also considered the proper approach to summary judgment applications, particularly when a party raises a defence that requires further factual investigation.

The Full Court reasoned that the Master had erred in finding that Aalborg had not established a reasonably arguable answer of misleading conduct. The Court held that the evidence adduced on the summary judgment application was sufficient to raise a reasonably arguable case for Aalborg, and that the determination of whether all elements of this defence would be established required a full trial. The Court applied the principle that summary judgment should not be granted if there is a reasonably arguable defence, even if its ultimate success is uncertain.

Consequently, the Full Court allowed the appeal, set aside the Master's orders, and remitted the matter to proceed to trial.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

On the hearing of the appeal, the Court allowed the appeal, set aside the Master’s orders and remitted the matter to proceed to trial. These are our reasons for making those orders.Background The facts set out below are based on the evidence adduced on and in the context of the application for summary judgment. Obviously the facts found at the trial of the action based on comprehensive evidence may differ. Aalborg is a company incorporated in Denmark having its head office in Aalborg, Denmark. Svante Bundgaard was at all material times its Chief Executive Officer. Ottoway is a company having its head office in Wingfield, South Australia. Bryan Tidswell was at all material times its Chief Executive Officer. Stephen Young and Mark Vartuli were at all material times two of its directors. John Holland Pty Ltd was engaged by Sundrop Farms Pty Ltd to design and supply a solar-thermal-desal-energy system at Port Augusta. Aalborg was in turn engaged by John Holland Pty Ltd to design and supply the solar field and solar power station for the project. In March 2015 Aalborg and Ottoway entered into a contract for the supply and fabrication of tubular steel towers for the project (the contract). The contract was later varied amongst other things to incorporate the provision by Ottoway of labour at specified rates.[2][2] It may be that the parties entered into a separate contract in respect of labour supply rather than varying the original contract and this may be an issue at trial. However, for the purpose of this appeal both parties proceeded on the assumption that all work by Ottoway was performed pursuant to the contract. The contract comprised a formal instrument executed by the parties containing variable terms together with several schedules, one of which was Aalborg’s General Terms and Conditions for Purchase (the Terms). The Instrument showed Aalborg’s address as Hjulmagervej 55, DK-9000 Aalborg, Denmark (Aalborg’s head office) and Ottoway’s address as 61-67 Plymouth Road, Wingfield, South Australia. Clause 3 of the Terms (clause 3) addressed Documentation. Clause 3 provided:3. Documentation3.1 Together with the goods, Supplier shall deliver original invoice and full OC-documentation within 8 days after delivery of goods. All invoices must be marked with purchase order numbers, name of Aalborg CSP contact person and project number.3.2The Supplier is responsible for all faults and defects in drawings, calculations, packing lists and other information supplied by him whether or not approved by Aalborg CSP.3.3If shipment is required, the Supplier shall transmit to Aalborg CSP by email copies of shipping invoice, packing list, and certificate of origin on the day of shipment.3.4For all goods to be lifted or displaced using lifting tools or machineries, the Supplier shall provide installation manual with description of procedures.3.5All documentation must be in English, unless otherwise agreed.3.6Documents and drawings need to be in accordance to Aalborg CSP and/or the client color code, numbering system, drawing specification etc. (to be clarified in the technical specification).3.7All relevant documentation shall be provided by Supplier in one hard copy and one electronic copy; the electronic copy shall be supplied as one pdf File, containing all relevant documentation in the order specified by Aalborg CSP. 3.8The Supplier acknowledges that any documentation submitted to Aalborg CSP shall not be considered as approved and shall not relieve the Supplier from its responsibility.3.9If a party becomes aware or reasonably should have been aware of an inconsistency in the documents, the party shall promptly inform the other party thereof.The Supplier shall store project information for at least 10 years.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

On the evidence adduced on the summary judgment application, Aalborg established a reasonably arguable answer of misleading conduct and the Master erred in finding otherwise. Whether all of the elements of such an answer will be established at trial can only be determined after all of the evidence is adduced at trial.Conclusion For the above reasons we allowed the appeal, set aside the orders made by the Master and remitted the matter to proceed to trial. We will hear the parties as to costs.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.