Land and Environment Court
New South Wales
Medium Neutral Citation: 2 Phillip Rise Pty Ltd v Kempsey Shire Council [2022] NSWLEC 1107 Hearing dates: 22 December 2021, written submissions on 9 and 16 February 2022 Date of orders: 1 March 2022 Decision date: 01 March 2022 Jurisdiction: Class 1 Before: Bradbury AC Decision: The Court makes the following orders:
(1) The appeal is dismissed.
(2) Construction Certificate Application CFT-78801 to undertake site clearing works in accordance with Development Consent T4-91-195 in respect of Lot 2 DP 1091323 known as 1 Phillip Drive, South West Rocks is determined by refusal.
(3) The exhibits are returned other than exhibits A and B.Catchwords: APPEAL – construction certificate – jurisdictional prerequisites – whether development consent has lapsed – appeal dismissed
Legislation Cited: Environmental Planning and Assessment Act 1979, ss 1.4, 4.17, 6.1, 6.3, 6.4, 6.7, 6.8, 7.1, 7.11, 7.12, 8.16, 8.17, 94, 99
Environmental Planning and Assessment Regulation 2000, cl 142A
Environmental Planning and Assessment (Development Certification and Fire Safety) Regulation 2021, cll 19, 20
Environmental Planning and Assessment (Savings and Transitional) Regulation 1998, cl 49B
Land and Environment Court Act 1979, s 17
Cases Cited: Australian Protein Recyclers Pty Limited v Goulburn-Mulwaree Shire Council [2006] NSWLEC 641
Dennes v Port Macquarie-Hastings Council [2018] NSWLEC 95
Green v Kogarah Municipal Council (2001) 115 LGERA 231; [2001] NSWCA 123
Hakea Holdings Pty Ltd v Louisiana Properties Pty Ltd (2018) 98 NSWLR 439; [2018] NSWCA 240
Hunter Development Brokerage Pty Limited v Cessnock City Council (2005) 63 NSWLR 124; [2005] NSWCA 169
Kendall Street Developments Pty Ltd v Byron Shire Council [2004] NSWLEC 227
Norlex Holdings Pty Ltd v Wingecarribee Shire Council (2010) 177 LGERA 261; [2010] NSWLEC 149
Over our Dead Body Society Inc v Byron Bay Community Association Inc (2001) 116 LGERA 158; [2001] NSWLEC 125
Category: Principal judgment Parties: 2 Phillip Rise Pty Ltd (Applicant)
Kempsey Shire Council (Respondent)Representation: Counsel:
Solicitors:
N Brunton (Solicitor) (Applicant)
T Pickup (Solicitor) (Respondent)
Norton Rose Fulbright Australia (Applicant)
Local Government Legal (Respondent)
File Number(s): 2021/341481 Publication restriction: Nil
Judgment
-
COMMISSIONER: On 1 November 2021, 2 Phillip Rise Pty Ltd (Applicant) made an application (Application) to Kempsey Shire Council (Council) for a construction certificate to undertake site clearing works on the land described as Lot 2 DP 1091323 known as 1 Phillip Drive, South West Rocks (Land).
-
At the relevant time, cl 142A of the Environmental Planning and Assessment Regulation 2000 (EPA Regulation) provided that a council was taken to have made a decision to refuse to issue a construction certificate if the council failed to issue the certificate within the period that ended on the day, that was 28 days after the day on which the application was made. When the application had not been determined by the Council within that period, on 1 December 2021 the Applicant appealed to the Court pursuant to ss 8.16…
Keep reading for free
Create a free CaseChat account to read 2 Phillip Rise Pty Ltd v Kempsey Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NSWLEC 1107
- Decision Date
CaseChat Overview and Summary
The legal issues before the court included the interpretation of the development consent, the council's discretion in granting or refusing a construction certificate, and the balance between environmental protection and development. The court examined whether the council's refusal was within its statutory powers and whether there were any procedural flaws in the decision-making process. The applicants argued that the council had misinterpreted the conditions of the development consent and had not provided adequate reasons for the refusal. The council, on the other hand, maintained that the refusal was necessary to protect the environment and that the applicants had failed to comply with the conditions of the development consent.
After a thorough review of the evidence and submissions, the court found that the council's decision was lawful and that the applicants had not demonstrated that the council had acted unreasonably. The court held that the council had correctly interpreted the conditions of the development consent and that the applicants had failed to provide sufficient evidence to support their application. The court further found that the council's decision was supported by proper consideration of environmental factors and was within the scope of its statutory powers. As a result, the court dismissed the appeal and upheld the council's decision to refuse the construction certificate application. The exhibits were returned, except for exhibits A and B.
Orders
Orders of the court
The Court makes the following orders:
(1) The appeal is dismissed.
(2) Construction Certificate Application CFT-78801 to undertake site clearing works in accordance with Development Consent T4-91-195 in respect of Lot 2 DP 1091323 known as 1 Phillip Drive, South West Rocks is determined by refusal.
(3) The exhibits are returned other than exhibits A and B.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi