Appellant
Anneliese Day KC
Michele De Gregorio
(Instructed by DAC Beachcroft LLP (Bristol))
Respondent
Alexander Nissen KC
Tom Owen KC
(Instructed by Watson Farley & Williams LLP (London))
LORD Hamblen (with whom Lord Briggs, Lady Rose, Lord Richards and Lady Simler agree):
Introduction
- Under the Housing Grants, Construction and Regeneration Act 1996 ("the 1996 Act") there is a statutory right to refer to adjudication any disputes which arise under a "construction contract". Statutory adjudication is an expeditious and cost-effective dispute resolution procedure, typically before a trained adjudicator who is a specialist in construction related work. It results in legally enforceable decisions, which are binding on the parties unless and until there is a final determination by arbitration, litigation or agreement.
- It is common practice in the construction industry for "collateral warranties" to be provided to third parties, such as funders, purchasers and prospective tenants. This practice originally arose as a result of the restriction on the rights of third parties to make tortious claims for economic loss consequent upon the House of Lords decision in Murphy v Brentwood District Council [1991] 1 AC 398.
- Collateral warranties give third parties contractual rights against contractors should defects arise in respect of the works carried out by them. The central issue on this appeal is whether the collateral warranty given by the appellant to the respondent is a "construction contract" within the meaning of the 1996 Act so as to give rise to a right to adjudication and specifically whether it is an agreement "for ... the carrying out of construction operations" under section 104(1)(a).
- The appellant, Augusta 2008 LLP (Formerly Simply Construct (UK) LLP) ("Simply"), is the contractor under a JCT Design and Build Contract 2011, with bespoke amendments, dated 29 June 2015 (the "Building Contract") by which it was engaged by the employer, Sapphire Building Services Ltd ("Sapphire"), to design and build a 65 bedroom care home at Holders Hill Road, Mill Hill, London (the "Property"). The respondent, Abbey Healthcare (Mill Hill) Ltd ("Abbey") is the tenant of the Property.
- The Building Contract included the following provisions:
- The Building Contract contained provisions in respect of warranties. Clause 1.1 defined "P&T Rights" as the rights in favour of a "Purchaser" or "Tenant" set out in Schedule 5 in the form of a collateral warranty. Both Purchaser…
Factual background
(1) Clause 2.1 required Simply to "carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents".
(2) Clause 2.35 required Simply to remedy defective work that appeared within the Rectification Period.
(3) Under clause 7.1.3 Sapphire was entitled to novate the Building Contract to the owner of the Property, Toppan Holdings Ltd ("Toppan").
(4) Clause 7C obliged Simply, on notification by Toppan, to execute a collateral warranty for the benefit of a tenant or management company; and in favour of Toppan. There was an agreed form of warranty in Schedule 5 to the Building Contract.
(5) Clause 9.2 contained express adjudication provisions.
Keep reading for free
Create a free CaseChat account to read Abbey Healthcare (Mill Hill) Ltd v Augusta 2008 LLP (formerl... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] UKSC 23
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi