[2024] UKSC 23
On appeal from: [2022] EWCA Civ 823
JUDGMENT
Abbey Healthcare (Mill Hill) Ltd (Respondent) vAugusta 2008 LLP (formerly Simply Construct (UK) LLP) (Appellant)
before
Lord Briggs
Lord Hamblen
Lady Rose
Lord Richards
Lady Simler
9 July 2024
Heard on 29 April 2024
Appellant
Anneliese Day KC
Michele De Gregorio
(Instructed by DAC Beachcroft LLP (Bristol))
Respondent
Alexander Nissen KC
Tom Owen KC
(Instructed by Watson Farley & Williams LLP (London))
LORD HAMBLEN (with whom Lord Briggs, Lady Rose, Lord Richards and Lady Simler agree):
Introduction
Under the Housing Grants, Construction and Regeneration Act 1996 (“the 1996 Act”) there is a statutory right to refer to adjudication any disputes which arise under a “construction contract”. Statutory adjudication is an expeditious and cost-effective dispute resolution procedure, typically before a trained adjudicator who is a specialist in construction related work. It results in legally enforceable decisions, which are binding on the parties unless and until there is a final determination by arbitration, litigation or agreement.
It is common practice in the construction industry for “collateral warranties” to be provided to third parties, such as funders, purchasers and prospective tenants. This practice originally arose as a result of the restriction on the rights of third parties to make tortious claims for economic loss consequent upon the House of Lords decision in Murphy v Brentwood District Council [1991] 1 AC 398.
Collateral warranties give third parties contractual rights against contractors should defects arise in respect of the works carried out by them. The central issue on this appeal is whether the collateral warranty given by the appellant to the respondent is a “construction contract” within the meaning of the 1996 Act so as to give rise to a right to adjudication and specifically whether it is an agreement “for … the carrying out of construction operations” under section 104(1)(a).
Factual background
The appellant, Augusta 2008 LLP (Formerly Simply Construct (UK) LLP) (“Simply”), is the contractor under a JCT Design and Build Contract 2011, with bespoke amendments, dated 29 June 2015 (the “Building Contract”) by which it was engaged by the employer, Sapphire Building Services Ltd (“Sapphire”), to design and build a 65 bedroom care home at Holders Hill Road, Mill Hill, London (the “Property”). The respondent, Abbey Healthcare (Mill Hill) Ltd (“Abbey”) is the tenant of the Property.
The Building Contract included the following provisions:
Clause 2.1 required Simply to “carry out and complete the Works in a proper and workmanlike manner and in compliance with the Contract Documents”.
Clause 2.35 required Simply to remedy defective work that appeared within the Rectification Period.
Under clause 7.1.3 Sapphire was entitled to novate the Building Contract to the owner of the Property, Toppan Holdings Ltd (“Toppan”).
Clause 7C obliged Simply, on notification by Toppan, to execute a collateral warranty for the benefit of a tenant or management company; and in favour of Toppan. There was an agreed form of warranty in Schedule 5 to the Building Contract.
Clause 9.2 contained express adjudication provisions.
The Building Contract contained provisions in respect of warranties. Clause 1.1 defined “P&T Rights” as the rights in favour of a “Purchaser” or “Tenant” set out in Schedule 5 in the form of a collateral warranty. Both Purchaser and Tenant were defined terms. In the event, Toppan became the Purchaser and Abbey became the Tenant.
Part 2 of the Contract Particulars identified Toppan and the “Management Company” as persons on whom P&T Rights may be conferred by collateral warranty. Management Company was defined as any entity responsible for the operation and/or management of the site and/or nursing home. In the event, that was the role played by Abbey as the tenant of the care home at the Property.
Simply commenced the works at some point between March and May 2015.
On 15 October 2015 Simply executed a collateral warranty in favour of Toppan.
On 20 September 2016 Abbey was incorporated.
On 10 October 2016 the works were certified as practically complete.
On 13 June 2017 Sapphire and Simply entered into a settlement agreement, by which they settled the final account and all claims under the Building Contract, save for latent defects. The settlement agreement also required the execution of a deed of novation in an agreed form by Simply, Sapphire and Toppan.
On 14 June 2017 the Building Contract was novated from Sapphire to Toppan. Under the novation agreement, Sapphire transferred all its rights and obligations under the Building Contract to Toppan. In this way, Toppan became the “Substitute Employer”, as referred to in the settlement agreement.
On 12 August 2017 Toppan granted a 21-year lease of the Property to Abbey, which operates the care home business from the Property.
In August 2018 Toppan discovered alleged fire safety defects at the Property, in particular the internal plasterboard wall linings were alleged not to provide the required 60 minutes of fire resistance. Toppan contended that the discovery of the defects prevented the sale of the Property and the care home business to a prospective purchaser. Simply was notified of the defects and requested to rectify them. Simply did not do so. Toppan engaged a third party contractor to carry out remedial works, which commenced on or around 25 September 2019 and were practically complete by 14 February 2020. Abbey states it paid for the remedial works on behalf of Toppan.
On 8 June 2020 Toppan requested that Simply provide a collateral warranty to Abbey. Simply did not respond to Toppan’s request. Toppan issued proceedings for specific performance. Thereafter, the parties entered into a collateral warranty (the “Abbey Collateral Warranty”), which was executed by Simply on 23 September 2020 and by Abbey and Toppan on 23 October 2020.
The Abbey Collateral Warranty
So far as material this provided as follows:
“BACKGROUND
The Developer [Toppan] has the benefit of the Contract entered into with the Contractor [Simply].
The Beneficiary [Abbey] has a leasehold interest in the Site.
The Contractor has agreed to enter into this agreement with the Beneficiary.
OPERATIVE PROVISIONS
1 DEFINITIONS…
“Contract” means the contract in the form of a JCT Design and Build Contract dated 29 June 2015 entered into by Sapphire Building Services Ltd and the Contractor under which the Contractor is to carry out the Works and the design of the Works.
…
“Works” means the construction of the development at the Site as more particularly described in the Contract.
…
4 SKILL AND CARE
The Contractor warrants that:
the Contractor has performed and will continue to perform diligently its obligations under the Contract;
in carrying out and completing the Works the Contractor has exercised and will continue to exercise all the reasonable skill care and diligence to be expected of a properly qualified competent and experienced contractor experienced in carrying out and completing works of a similar nature value complexity and timescale to the Works;
in carrying out and completing any design for the Works the Contractor has exercised and will continue to exercise all the reasonable skill care and diligence to be expected of a prudent, experienced competent and properly qualified architect or as the case may be other appropriate competent and qualified professional designer experienced in carrying out and completing the design for works of a similar nature value complexity and timescale to the Works.
Insofar as the Contractor has performed a part of its obligations under the Contract before the date of the Contract the obligations and liabilities of the Contractor under this agreement shall take effect in all respects as if the Contract had been dated prior to the performance of that part of its obligations by the Contractor.
The Contractor shall owe no greater duties to the Beneficiary under the terms of this agreement than it would have owed to the Beneficiary had the Beneficiary been named as the employer under the Contract save that this agreement shall continue in full force and effect notwithstanding the determination of the Contract for any reason.
The obligations of the Contractor shall not be released or diminished by the appointment of any person by the Beneficiary to carry out any independent enquiry into any relevant matter.
The Contractor further warrants that unless required by the Contract or unless otherwise authorised in writing by the Developer or the Developer's representative named in or appointed pursuant to the Contract (or where such authorisation is given orally, confirmed in writing by the Contractor to the Developer and/or the Developer's representative), it has not and will not use materials in the Works other than in accordance with the guidelines contained in the edition of the publication ‘Good Practice in Selection of Construction Materials’ (published by the British Council for Offices) current at the date of the Building Contract.”
Clause 3 provided that these warranties were made in consideration of a nominal payment of £1 by Abbey to Simply. Clause 5 provided for the maintenance of professional indemnity insurance by Simply. Under Clause 6 Simply granted to Abbey a licence to use and copy Design Documents. Clause 7 granted Abbey Step-In rights in the event of Toppan’s insolvency. This entitled Abbey to require Simply to continue its obligations under the Building Contract in relation to the Works and for Abbey to assume all of Toppan’s obligations.
The adjudications
Toppan and Abbey made claims against Simply arising out of the fire safety defects and the cost of remedial works. Simply refused the request that the disputes be dealt with in a single adjudication. On 11 December 2020 Toppan and Abbey each referred to adjudication a dispute regarding the alleged defects, seeking sums in excess of £8.8m and £5.5m respectively. Mr Peter Vinden was appointed as adjudicator (the “Adjudicator”) for both disputes.
In the Abbey adjudication Simply challenged the jurisdiction of the Adjudicator on the grounds that the Abbey Collateral Warranty was not a “construction contract” within the meaning of section 104(1) of the 1996 Act. On 26 February 2021 the Adjudicator gave a non-binding ruling on jurisdiction, rejecting Simply’s challenge. The Abbey adjudication proceeded with Simply reserving its rights in this regard.
The Adjudicator issued his decisions on 30 April 2021 (the “Decisions”), finding for Toppan and Abbey on liability. The Adjudicator awarded Toppan damages of approximately £1m, plus interest, in respect of the cost of the remedial works and rejected its claims relating to an aborted sale to a prospective purchaser. In the Abbey adjudication, the Adjudicator awarded Abbey damages of £869,500 in respect of its loss of profit resulting from the defects, plus interest.
The proceedings
Simply did not pay the sums due. On 12 May 2021, Toppan and Abbey issued proceedings in the Technology and Construction Court (“TCC”) to enforce the Decisions by way of summary judgment.
On 1 July 2021 the applications were heard by Mr Martin Bowdery QC (sitting as a Deputy High Court Judge) (the “Judge”).
On 27 July 2021 the Judge handed down judgment: Toppan Holdings Ltd & Abbey Healthcare (Mill Hill) Ltd v Simply Construct (UK) LLP [2021] EWHC 2110 (TCC); [2021] Bus LR 1357; (2021) 197 Con LR 241. In respect of Toppan, the Judge granted summary judgment. In respect of Abbey, the Judge dismissed the summary judgment application on the grounds that the Abbey Collateral Warranty was not a construction contract within the meaning of section 104(1) of the 1996 Act and, therefore, theAdjudicator lacked jurisdiction.
On 15 November 2021 the Court of Appeal (Coulson LJ) granted Abbey permission to appeal to the Court of Appeal.
The Court of Appeal heard the appeal on 16 March 2022. The Court of Appeal handed down judgment on 21 June 2022 allowing the appeal by a majority (Peter Jackson and Coulson LJJ; Stuart-Smith LJ dissenting): [2022] EWCA Civ 823; [2022] Bus LR 1079; (2022) 203 Con LR 1.
On 21 December 2022 the Supreme Court (Lord Hodge, Lord Burrows and Lord Richards) granted Simply permission to appeal to the Supreme Court.
The legal framework
As explained by Coulson LJ in C Spencer Ltd v M W High Tech Projects UK Ltd[2020] EWCA Civ 331; [2020] 1 WLR 3426:
The twin purposes of the [1996 Act] was to improve cashflow in the construction industry, and to streamline its dispute resolution process. The former aim was achieved through mandatory provisions relating to interim payments, payment notices and the like, and the latter through a new, compulsory scheme of construction adjudication.”
A helpful summary of the background to the 1996 Act and its success in meeting these twin purposes is set out in the judgment of Lord Briggs of Westbourne in Michael J Lonsdale (Electrical) Ltd v Bresco Electrical Services Ltd [2020] UKSC 25; [2020] Bus LR 1140; [2021] 1 All ER 697 at paras 11 to 14. Important features of the procedure of adjudication are set out at paras 20 to 26.
Section 104 of the 1996 Act provides as follows:
“104 Construction contracts.
In this Part a ‘construction contract’ means an agreement with a person for any of the following—
the carrying out of construction operations;
arranging for the carrying out of construction operations by others, whether under sub-contract to him or otherwise;
providing his own labour, or the labour of others, for the carrying out of construction operations.
References in this Part to a construction contract include an agreement—
to do architectural, design, or surveying work, or
to provide advice on building, engineering, interior or exterior decoration or on the laying-out of landscape,
in relation to construction operations.
References in this Part to a construction contract do not include a contract of employment (within the meaning of the Employment Rights Act 1996)…
Where an agreement relates to construction operations and other matters, this Part applies to it only so far as it relates to construction operations.
An agreement relates to construction operations so far as it makes provision of any kind within subsection (1) or (2)… ”
Section 105 sets out a list of what is included within the definition of “construction operations”. This includes the construction, alteration, repair, maintenance, extension, demolition or dismantling of buildings.
Section 108 of the 1996 Act gives “a party to a construction contract…the right to refer a dispute arising under the contract for adjudication”. Section 108(5) provides that, if the contract does not contain adjudication provisions, the adjudication provisions within the Scheme for Construction Contracts (England and Wales) Regulations 1998 (SI 1998/649), as amended (“the Scheme”) will apply. The Abbey Collateral Warranty contained no adjudication provisions. It follows that if it was a construction contract as defined in section 104(1), the Scheme was implied into it.
Sections 109 to 113 contain provisions dealing with payments under construction contracts, including as to entitlement to periodic payments (section 109), mechanisms for determining when payments become due and final dates for payment (section 110), payment notices (sections 110A and 110B), right to payment (section 111) and right to suspend performance for non-payment (section 112).
The judgments below
The Judge held that the Abbey Collateral Warranty should be construed against the background that at the time of its execution the works had been completed some four years previously, the remedial works to the disputed defects had been completed eight months previously, and neither Abbey nor Simply contemplated the possibility of any further construction operations being carried out. So construed he concluded that it was not a construction contract for the carrying out of construction operations but rather a warranty as to events which had occurred years before.
In the Court of Appeal it was accepted that if, properly construed, the Abbey Collateral Warranty was a construction contract then its timing could not be determinative. Coulson LJ emphasised two reasons why this is so. First, because it is retrospective in effect and secondly because it would be uncertain and unsatisfactory if the question of whether a collateral warranty was a construction contract turned on whether or not its date of execution was before or after practical completion (paras 69-76). Peter Jackson LJ agreed that the date on which the Abbey Collateral Warranty was executed did not prevent it from being a construction contract (paras 164-165). There is no appeal from this decision on the timing issue.
The other issues addressed by the Court of Appeal were (i) whether a collateral warranty can ever be a construction contract and (ii) if it can, whether the Abbey Collateral Warranty was such a contract. All members of the Court were agreed that a collateral warranty could be a construction contract. The disagreement was on issue (ii).
Coulson LJ
In arriving at his conclusion on issue (ii), Coulson LJ relied on his reasoning on issue (i) and in particular the following:
…a warranty which provided a simple fixed promise or guarantee in respect of a past state of affairs may not be a contract for the carrying out of construction operations pursuant to section104(1). Something that said ‘We completed these works two years ago and we warrant that they were completed in all respects in accordance with the Building Regulations’, is a promise about the quality of something which has been completed. It does not recognise or regulate the ongoing carrying out of any future work. It may therefore not be a contract for the carrying out of construction operations. It is more akin to a product guarantee.
On the other hand, a warranty that the contractor was carrying out and would continue to carry out construction operations (to a specified standard) may well be ‘a contract for the carrying out of construction operations’ in accordance with section 104(1). That is because, unlike a product guarantee, it is a promise which regulates (at least in part) the ongoing carrying out of construction operations.
…
Drawing those various threads together, I conclude that:
The words in section 104(1) (‘an agreement…for…the carrying out of construction operations’) is a broad expression and has regularly been construed as such: see in particular Parkwood.
Traditional views about what comprises a building contract or a collateral warranty are of limited value. However, the importance of collateral warranties to the ultimate owners/occupiers who were not involved when the building contract was originally agreed is a relevant background factor.
The broad approach to section 104(1) is supported by section 104(5) and by one of the purposes of the 1996 Act, namely to provide an effective dispute resolution system. It is in accordance with that purpose that the same factual disputes about the carrying out of the same construction operations can be dealt with by the same adjudicator, even where there are two different contracts.
There is no reason to limit the words of section 104(1) to refer only to the primary building contract in any situation. Neither is it necessary to construe the expression by reference to whether or not the contract contains detailed obligations on the part of the beneficiary to make payments direct to the contractor. Provided the contract or warranty in question complies with section 109, it can be a construction contract for the purposes of section 104(1).
A collateral warranty may, therefore, be capable of being a construction contract for the purposes of section 104(1). What may be critical is whether the warranty is in respect of the ongoing carrying out of construction operations, on the one hand, or is in respect of a past and static state of affairs, on the other.”
In concluding that the terms of the Abbey Collateral Warranty made it a construction contract Coulson LJ relied in particular on the wording of clause 4.1(a) that Simply “has performed and will continue to perform” its obligations under the Building Contract. He considered that this is “a warranty of both past and future performance of the construction operations”. He reasoned as follows:
…[Simply] were warranting that, not only have they carried out the construction operations in accordance with the building contract, but they will continue so to carry out the construction operations in the future. That is an ongoing promise for the future … It is not a warranty limited to the standard to be achieved; neither is it a warranty limited to a past or fixed situation. It is a warranty as to future performance. It is that that differentiates the Abbey Collateral Warranty from a product guarantee.
That can be tested in this way. If [Simply] had failed to complete the construction operations, would they have been in breach of the Abbey Collateral Warranty? The answer must be Yes. They had agreed to carry out the construction operations to the standard set out in the building contract and they had stopped before they had been completed. That would have been in breach of both the building contract and the Abbey Collateral Warranty, because they could not perform their obligations under the Abbey Collateral Warranty unless they also performed their obligations under the building contract….
The real issue here may be whether the provisions in clause 4 of the Abbey Collateral Warranty simply recognise the existence of [Simply’s] obligation to perform the construction operations under the building contract with Toppan without more, or whether they comprise separately actionable obligations on the part of [Simply]. For the reasons that I have given, I consider that they are separately actionable obligations. The fact that they do not bring with them all the myriad other rights and duties which an employer may have under a traditional building contract is irrelevant for the purposes of section 104(1).”