| IN THE SUPREME COURT OF NEW ZEALAND I TE KŌTI MANA NUI O AOTEAROA |
| SC 129/2022 [2023] NZSC 22 |
| BETWEEN | SRG GLOBAL REMEDIATION SERVICES (NZ) LIMITED |
| AND | BODY CORPORATE 197281 |
| Court: | Ellen France, Williams and Kós JJ |
Counsel: | C L Bryant and N P Gillies for Applicant |
Judgment: | 20 March 2023 |
JUDGMENT OF THE COURT
AThe application for leave to appeal by SRG Global Remediation Services (NZ) Ltd (SRG) is dismissed.
BThe application for leave to appeal by Body Corporate 197281 (the Body Corporate) is dismissed.
CThere is no order as to costs in relation to the applications for leave.
DThe application for a stay under r 30(5) of the Supreme Court Rules 2004 by the Body Corporate is dismissed.
EThe Body Corporate must pay SRG costs of $2,500 in relation to the stay application.
____________________________________________________________________
REASONS
Introduction
SRG Global Remediation Services (NZ) Ltd (SRG) and Body Corporate 197281 (the Body Corporate) are involved in proceedings relating to a construction contract to which the Construction Contracts Act 2002 applies. Both have filed applications for leave to appeal to this Court from a judgment of the Court of Appeal addressing aspects of the proceedings.[1] The Body Corporate also seeks a stay pending determination by this Court.
Background
[1]SRG Global Remediation Services (NZ) Ltd v Body Corporate 197281 [2022] NZCA 518 (French, Courtney and Dobson JJ) [CA judgment]. We treat the applications as two separate leave applications although only one Court file has been created.
The facts are set out in detail in the judgments of the High Court[2] and the Court of Appeal.[3] It is sufficient to highlight some features of the arrangements between the parties and to briefly summarise the course of the proceedings to date. In doing so, we refer to SRG as the other party to the contract with the Body Corporate although the original contracting party was a company called TBS Remcon Ltd.[4]
[2]Hellaby Resource Services Ltd v Body Corporate 197281 [2021] NZHC 554 (Associate Judge Gardiner) [HC judgment] at [6]–[22].
[3]CA judgment, above n 1, at [8]–[24].
[4]TBS was sold by its parent company (Hellaby Resource Services Ltd) in late 2018 and the debt owed by the Body Corporate was the subject of a deed of assignment. A question arose about the effectiveness of the assignment but is not in issue now.
Under the construction contract (which incorporated the general conditions of contract under NZS 3910:2013),[5] SRG carried out remediation work on the Body Corporate’s water‑damaged apartment building. The Body Corporate received over $10.2 million from the Ministry of Business, Innovation and Employment under the Government’s financial assistance package scheme towards the cost of the remediation work. This included a $2 million sum paid in December 2018. The Body Corporate confirmed to the Ministry these funds would be used to pay suppliers including…
Keep reading for free
Create a free CaseChat account to read SRG Global Remediation Services (NZ) Limited v Body Corporat... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2023] NZSC 22
- Decision Date
CaseChat Overview and Summary
The Court considered the Body Corporate's grounds for appeal, which focused on four main areas: the relationship between s 79 of the Construction Contracts Act and the power to stay enforcement of a judgment; the ability to pursue the counterclaim in the absence of a stay; the solvency of SRG; and various miscellaneous issues. The Court concluded that the Body Corporate's arguments had insufficient prospects of success, and that no question of general importance or commercial significance arose. As a result, the Court was not satisfied that the case was an appropriate vehicle to consider the issues raised.
The Court also considered SRG's grounds for appeal, which centred on the interpretation of art 8 of sch 1 of the Arbitration Act and cl 13 of NZS 3910:2013. The Court found that the issues raised would turn on a factual inquiry specific to the particular combination of circumstances, and that no question of public importance or commercial significance arose. The Court further noted that SRG's inaction to refer the matter to the Engineer in a timely manner pointed against the prospect of a miscarriage of justice.
The Court dismissed both the Body Corporate's and SRG's applications for leave to appeal, as well as the Body Corporate's application for a stay pending determination of the appeal. The Body Corporate was ordered to pay SRG costs of $2,500 in relation to the stay application.
In summary, the Supreme Court dismissed both leave to appeal applications and the stay application, finding that the appeals did not raise questions of general importance or commercial significance, and that there was no appearance of a miscarriage of justice. The Body Corporate was ordered to pay SRG costs of $2,500 in relation to the stay application.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi