Senio Holdings Ltd v Evergreen Homes & Construction Ltd

Link copied
Case Copied 23 min read

IN THE HIGH COURT OF NEW ZEALAND INVERCARGILL REGISTRY

I TE KŌTI MATUA O AOTEAROA WAIHŌPAI ROHE

CIV-2022-425-53

[2023] NZHC 1191

UNDER the Companies Act 1993

IN THE MATTER

of an application to set aside a statutory demand pursuant to section 290 of the Act

BETWEEN

SENIO HOLDINGS LTD

Applicant

AND

EVERGREEN HOMES & CONSTRUCTION LTD

Respondent

Hearing: 2 May 2023

Appearances:

A L Pinnock and M C Ryan for Applicant B B Gresson for Respndent

Judgment:

17 May 2023


JUDGMENT OF ASSOCIATE JUDGE PAULSEN


This judgment was delivered by me on 17 May 2023 at 4.00 pm pursuant to Rule 11.5 of the High Court Rules

Registrar/Deputy Registrar Date:

SENIO HOLDINGS LTD v EVERGREEN HOMES & CONSTRUCTION LTD [2023] NZHC 1191 [17 May 2023]

[1]    The respondent, Evergreen Homes & Construction Ltd (Evergreen), is a builder. It entered into a building contract with Senio Holdings Ltd (Senio) to construct three household units at Cromwell. During the course of the building contract, Evergreen rendered to Senio invoice 20399 for $17,607.62 which it identified as progress claim 11A. Senio disputed the progress claim and did not pay it. In July 2022, Evergreen issued to Senio a statutory demand under s 289 of the Companies Act 1993 in respect of the progress claim and suspended work. Senio now applies to set the statutory demand aside pursuant to s 290(4) of the Companies Act.

[2]    Senio says there is a substantial dispute as to whether the amount claimed in the statutory demand is owing or due because progress claim 11A is not a payment claim under the Construction Contracts Act 2002 (the Act) as required by the building contract, and it has paid the full amount that could be due under the building contract. In addition, Senio says that if progress claim 11A was a payment claim for the purposes of the Act it issued a payment schedule to Evergreen in response to it. It further says that it has set-offs and/or counterclaims against Evergreen which exceed the amount of the demand. Finally, Senio says the issue of the statutory demand was an abuse of process.

[3]    Evergreen takes a commendably simple position in response to Senio’s application. It does not engage with Senio’s evidence concerning the existence of set- offs and counterclaims except in one respect, which is not now relied upon by Senio.1 Senio’s evidence in relation to those matters is effectively uncontested. Evergreen says there is no genuine dispute as to Senio’s liability for the amount claimed in the statutory demand because the building contract, as properly interpreted, did not require it to issue payment claims under the Act and Senio cannot raise set-offs or counterclaims because there is a no set-off clause in the building contract.

[4]    It is not in dispute that progress claim 11A was not a payment claim under the Act. Mr Gresson, appearing for Evergreen, also accepted that if Evergreen was required by the terms of the building contract to issue its progress claims as…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Senio Holdings Ltd v Evergreen Homes & Construction Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] NZHC 1191
Decision Date

CaseChat Overview and Summary

Senio Holdings Ltd, the applicant, applied to set aside a statutory demand issued by Evergreen Homes & Construction Ltd, the respondent, pursuant to s 290(4) of the Companies Act 1993. The statutory demand was issued in respect of progress claim 11A for $17,607.62. Senio contends that there is a substantial dispute as to whether the amount claimed is owing or due because progress claim 11A was not a payment claim under the Construction Contracts Act 2002 (the Act) as required by the building contract and it has paid the full amount that could be due under the building contract. In addition, Senio says it has set-offs and/or counterclaims against Evergreen which exceed the amount of the demand. Evergreen contends that there is no genuine dispute as to Senio’s liability for the amount claimed in the statutory demand because the building contract, as properly interpreted, did not require it to issue payment claims under the Act and Senio cannot raise set-offs or counterclaims because there is a no set-off clause in the building contract. The primary issue is whether the building contract required Evergreen to issue payment claims under the Act, which is determinative of the application. The building contract required Evergreen to issue payment claims complying with the requirements of the Act. This conclusion is based on an objective approach to contractual interpretation. The contractual language must be interpreted within its overall context broadly viewed. The building contract contained numerous references to “payment claim” and, in particular, cl 13 and Schedule 1A of the building contract which deal with payments under the building contract. It is a mandatory requirement of the building contract that Evergreen issue payment claims in accordance with the Act. The conduct of the parties is not helpful in supporting Evergreen’s interpretation of the building contract. Senio has established there is a substantial dispute as to whether the sum claimed is due or owing. As Evergreen accepts that if it was obliged to issue payment claims the statutory demand must be set aside, there will be an order to that effect. The issue of the no set-off provision and the question of abuse of process do not need to be considered in light of Evergreen’s concession that the progress claim was not a payment claim for the purposes of the Act. The statutory demand is set aside. Senio is entitled to costs on a 2B basis, but not in respect of any steps taken in relation to the application to be represented by its director, Ms Brosnan. If the parties cannot reach agreement on the quantum of costs they may file memoranda of no longer than five pages within 21 days and I will deal with the issue on the papers.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.