Neumayer v Kapiti Coast District Council

Link copied
Case Copied 6 min read

IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY

CIV-2012-485-2677 [2014] NZHC 417

BETWEEN  SEBASTIAN NEUMAYER and LA DENE RAINA NEUMAYER Plaintiffs

ANDKAPITI COAST DISTRICT COUNCIL First Defendant

NEW CENTURY REAL ESTATE LIMITED

Second Defendant

KLAUS TAMERLER Third Defendant

Hearing:                   10 March 2014

Counsel:                  P A Robertson for Plaintiffs and First Defendant No appearance for First and Second Defendants E S K Dalzell for Third Defendant

Judgment:                10 March 2014

ORALJUDGMENT OF THE HON JUSTICE KÓS (Application for leave to defend)

[1]      This is a leaky home case.  It concerns a property at 7 Sylvia Way, Te Horo. The plaintiffs, Mr and Mrs Neumayer, have reached settlement with the first defendant  Council.    In  that  settlement  agreement  they have settled their  claims against the Council for $150,000.  They have assigned to it their causes of action against the second and third defendants New Century Real Estate Limited and Klaus Tamerler.

[2]      On 14 May 2013 the plaintiffs and Council applied for judgment by default against the second and third defendants.   That was because neither New Century

Real Estate nor Mr Tamerler had filed a statement of defence.  In my judgment the

NEUMAYER & ANOR v KAPITI COAST DISTRICT COUNCIL [2014] NZHC 417 [10 March 2014]

following day, I pointed out that the judgment by default procedure was not available in this case.   In particular because the claims were not for a “liquidated demand”. Accordingly r 15.7 did not apply.  But r 15.9 was applicable, providing for entry of judgment following formal proof.  In my judgment I said that:

(a)      If the plaintiffs or Council wished to proceed with formal proof, they could apply.

(b)Given the degree of default by the second and third defendants, no statement of defence could now be filed by them without application for leave to do so.

(c)      Absent leave, they were debarred from defending the claim and cross- claims against them.

That was in May 2013.

[3]      In the ensuing 10 months the plaintiffs and first defendant have taken steps to bring the matter forward to a formal proof hearing.  An application has been made. A copy was served on the defaulting defendants.  The application was set down for hearing this morning.   Then, on Thursday 6 March, an application was made by Mr Tamerler for leave to defend.

[4]      That application on any view is atrociously late.  The delay in bringing the application has caused the plaintiffs to incur significant costs.  Not least, potentially, the hearing fee for the formal proof hearing.  Affidavits from Mr Tamerler and his wife,  Ms  Simons,  were  filed.    In  the  affidavits  Mr  Tamerler  sets  out  various responses to the plaintiffs’ claim.   He denies that he was a formal agent for the property, although he accepts he did act as a sales representative.  He denies that he portrayed himself as a builder or having substantial building experience.  He denies knowing  the  property  well.    He  denies  making  the  representations  alleged  by Mr Neumayer.

[5]      As to the reasons for delay, it comes down…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Neumayer v Kapiti Coast District Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NZHC 417
Decision Date

CaseChat Overview and Summary

The case of Neumayer v Kapiti Coast District Council involved the plaintiffs, Mr and Mrs Neumayer, who had reached a settlement agreement with the Kapiti Coast District Council regarding claims pertaining to a leaky home property located at 7 Sylvia Way, Te Horo. The plaintiffs had assigned their causes of action against the second and third defendants, New Century Real Estate Limited and Klaus Tamerler, to the Council. Following the failure of the second and third defendants to file a statement of defence, the plaintiffs and the Council applied for judgment by default against them. However, the court ruled that judgment by default was not applicable in this case and instead, the plaintiffs and the Council could apply for entry of judgment following formal proof.

The legal issues before the court involved determining whether the court should grant the third defendant, Klaus Tamerler, leave to defend the claims against him, despite his significant delay in doing so. The court had to consider whether Tamerler had a substantial ground of defence, whether his delay was reasonably explained, and whether the plaintiffs would suffer irreparable injury if leave was granted belatedly.

The court found that Tamerler had presented an arguable defence, which was sufficient to amount to a “substantial ground of defence.” However, the court held that his delay in seeking leave to defend was not reasonably explained, as he had failed to act promptly despite being served with documents and receiving advice from his former employer. Nonetheless, the court ruled that the plaintiffs would not suffer irreparable injury if leave was granted, as long as Tamerler paid the costs incurred by the delay. The court granted Tamerler leave to defend, subject to him paying costs and filing a statement of defence within 14 days.

The court's decision did not affect the earlier ruling that barred the second defendant, New Century Real Estate Limited, from defending the claims against it.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.