IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV-2011-485-268
CIV-2011-485-269 [2014] NZHC 1765
UNDER
IN THE MATTER
the Commerce Act 1986
of an intended appeal to the Court of Appeal under s 52Z(6) and s 97(1) of the Act
BETWEEN
THE MAJOR ELECTRICITY USERS’
GROUP INC Applicant
AND
COMMERCE COMMISSION, VECTOR LIMITED, POWERCO LIMITED, TRANSPOWER NEW ZEALAND LIMITED and WELLINGTON ELECTRICITY LINES LIMITED Respondents
Hearing:
Court:
6 June 2014
Clifford J, Mr R Davey (lay member) and Mr R Shogren (lay member)
Counsel:
N Pender and S Franks for The Major Electricity Users’ Group
Inc.
V Casey and D Laurenson for the Commerce Commission
A Butler, C Marks and N Lambie for Vector Limited V L Heine and B A Davies for Powerco Limited and Transpower New Zealand Limited
No appearance for Wellington Electricity Lines Limited
(appearance excused)
Judgment:
28 July 2014
JUDGMENT OF THE COURT
THE MAJOR ELECTRICITY USERS’ GROUP INC v COMMERCE COMMISSION [2014] NZHC 1765 [28
July 2014]
Introduction
[1] This is an application by the Major Electricity Users’ Group Inc (MEUG) for leave to appeal against the decision of this Court in Wellington International Airport Ltd v Commerce Commission (WIAL v Commerce Commission).1 This Court, amongst other things, dismissed MEUG’s appeal pursuant to s 52Z of the Commerce Act 1986 against the decision of the Commerce Commission (the Commission) that the cost of capital input methodologies (IMs) for the electricity distribution businesses (EDBs)2 and Transpower Limited (Transpower)3 should be determined by
reference to the Commission’s 75th percentile estimate of the weighted average cost
of capital (WACC) range. MEUG’s argument that the 50th percentile estimate should be used, or alternatively that the 75th percentile should be applied only to new investment was not accepted.
[2] MEUG also asks this Court to make an order under s 97(3) of the Commerce Act that, if leave to appeal is granted and MEUG is unsuccessful, costs in the Court of Appeal should only be awarded against MEUG if it pursues its appeal unreasonably.
[3] The respondents, Vector Limited (Vector), Powerco Limited (Powerco) and Transpower oppose us granting MEUG leave to appeal. They also oppose the costs order MEUG seeks. Wellington Electricity Lines Limited (WELL) does not actively oppose MEUG’s leave application but wishes to preserve its position as a respondent if MEUG’s application is granted.
[4] Vector applied for leave to cross-appeal. In circumstances to which we refer later, Vector confirmed that it no longer pursued that application.
[5] A question of the formal status of Vector, Powerco, Transpower and WELL is raised. MEUG originally cited only the Commerce Commission as the respondent to
its intended appeal. Vector, Powerco, Transpower and WELL subsequently applied
1 Wellington International Airport Ltd v Commerce Commission [2013] NZHC 3289.
2 Commerce Act (Electricity Distribution Services Input Methodologies) Determination 2010
Decision 710, 22 December 2010.
3 Commerce Act (Transpower Input Methodologies) Determination 2010 Decision 713,
22 December 2010.
to be joined as respondents, rather than as interested parties on…
Keep reading for free
Create a free CaseChat account to read Major Electricity Users' Group Inc v Commerce Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NZHC 1765
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.