Luxta Ltd v Capital Construction Ltd HC Auckland CIV 2009-485-1957

Case

[2010] NZHC 256

10 February 2010

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND

WELLINGTON REGISTRY

CIV-2009-485-1957

BETWEEN  LUXTA LIMITED

Applicant

ANDCAPITAL CONSTRUCTION LIMITED Respondent

Hearing:         8 February 2010

Appearances:  P. Withnall - Counsel for Applicant

H. Brown - Counsel for Respondent

Judgment:      10 February 2010 at 3.30 pm

JUDGMENT OF ASSOCIATE JUDGE D.I. GENDALL

This judgment was delivered by Associate Judge Gendall on 10 February 2010 at

3.30 pm pursuant to r 11.5 of the High Court Rules.

Solicitors:            Kensington Swan, Solicitors, PO Box 10246, Wellington 6143

Brandons, Solicitors, PO Box 36, Wellington

LUXTA LIMITED V CAPITAL CONSTRUCTION LIMITED HC WN CIV-2009-485-1957  10 February 2010

Introduction

[1]       This is an application to set aside a statutory demand issued by the respondent, Capital Construction Limited (“Capital Construction”), originally seeking the sum of $568,711.67. The statutory demand is based on a debt alleged to be due from the applicant, Luxta  Limited (“Luxta”), for services provided under a construction contract.

[2]       In its application, Luxta contends that the demand should be set aside on the basis  that  the  issue  of  the  demand  amounts  to  an  abuse  of  process  and  savours  of oppressive conduct.

Background Facts

[3]       Capital  Construction  and  Luxta  are  parties  to  a  construction  contract  (“the contract”) for the construction of a townhouse development in Karori, Wellington. Capital Construction is the contractor and Luxta is the principal.

[4]       The parties’ contract is in the standard form NZS 3915:2005 and is amended

by certain special conditions. In particular, general condition 12.2 of NZS3915.205 dealing with  Progress  Payment  Schedules  was  substituted  to  provide  for  Luxta’s payment obligations in the following way:

“Irrespective  of  what  NZS  3915:2005  provides,  the  Principal  has  seven working  days  from  the  receipt  of  the  Contractor’s  claim  to  issue  the Progress Payment Schedule and eight working days from the issue of the Progress Payment Schedule to pay the scheduled amount.”

[5]       On  25  June  2009,  Capital  Construction  served  a  purportedly final  payment claim on Luxta.   Luxta advised Capital Construction that the payment claim did not comply  with  clause  12.4.1  of  the  contract,  which  specified  that  the  final  payment claim  was  to  be  issued  no  later  than  two  months  after  the  expiry  of  the  defects liability period. Capital Construction then withdrew that payment claim.

[6]       On  31  July  2009,  Capital  Construction  submitted  an  alternative  payment claim   entitled   “payment   claim   19”   for   $544,946.04.   According   to   Capital Construction, the claim was discovered to contain clerical errors, and was therefore withdrawn  and  re-issued  on  3  August  2009  for  the  amount  of  $568,711.67  (“the payment claim”). The due date for payment was 24 August 2009.

[7]       Luxta, however, did not serve a payment schedule within seven working days

of  service  of  the  payment  claim,  and  also  failed  to  make  payment  of  the  claimed amount  by  24  August  2009.  It  appears  that,  given  that  Capital  Construction  had issued  three  payment  claims  19,  there  was  a  dispute  as  to  the  timing  of  Luxta’s obligation to pay for the amount specified in the payment claim.

[8]       Capital Construction referred the matter to an expert for determination under the alternative dispute resolution clause, together with  a  number  of  other  disputes that had arisen between the parties. The hearing took place on 15 September 2009.

[9]       Two days later, on 17 September 2009, Capital Construction served the statutory demand in question on Luxta under s  289  of  the  Companies  Act  1993. Luxta then filed an application to have the statutory demand set aside on 1 October

2009, and Capital Construction filed a notice of opposition on 12 October 2009.

[10]     On 13 November 2009, Luxta  made  a  payment  to  Capital  Construction  of

$126,781.85. This reduced the  amount  currently  claimed  to  be  outstanding  to

Capital Construction to $441,929.82.

Counsel’s Arguments and My Decision

[11]     Luxta brings this application pursuant to s 290 of the Companies Act 1993, which sets out the basis on which a statutory demand may be set aside:

“290 Court may set aside statutory demand

(1)         The Court may, on the application of the company, set aside a statutory demand.

(4)         The Court may grant an application to set aside a statutory demand if it

is satisfied that—

(a)   There is a substantial dispute whether or not the debt is owing or is due; or

(b)   The  company  appears  to  have  a  counterclaim,  set-off,  or  cross- demand and the amount specified in the demand less the amount of the   counterclaim,   set-off,   or   cross-demand   is   less   than   the prescribed amount; or

(c)   The demand ought to be set aside on other grounds.

[12]     The only ground effectively relied upon by Luxta in bringing this application

is that the statutory demand amounts to an abuse of process: s 290(1)(c). It submits

that, in invoking the expert  determination  process  under  the  contract,  Capital

Construction must have accepted that there was a “dispute or difference” in relation

to the payment claim, as provided for by section 13 of the contract. Luxta contends that, given the respondent’s decision to invoke the dispute resolution procedures, it should  have  recognised  that  this  was  not  an  appropriate  occasion  for  the  use  of  a statutory demand.

[13]     Counsel for Luxta refers to  the   Court   of   Appeal’s   decision   in   Link

Electrosystems Limited v GPC Electronics (NZ) Limited [2007] NZCA 501, (2007)

18 PRNZ 946 at [16], where the Court held that the statutory demand procedure is not to be used oppressively as a debt collection device. He argues that Capital Construction abused the coercive power of the statutory demand procedure by issuing a demand only two days after the dispute resolution hearing, and before the expert had issued a determination. It is submitted  that  the  purpose  of  issuing  the statutory demand was to pre-empt the outcome of the expert determination process,

or to pre-empt the time it would take for that process to run its course.

[14]     Luxta contends that the circumstances of the present case are very similar to those in Edge Computers Limited  v  Colonial  Enterprises  Limited  (1996)  9  PRNZ

621 at 625, where the Court of Appeal was satisfied that an application for winding

up while the real issues between the parties were awaiting resolution in the District Court was an abuse of process. In essence, Luxta asserts that Capital Construction is not entitled to reject the dispute resolution process “mid-stream” and replace it with “the draconian (and irreconcilable) alternative of a statutory demand”, as this would amount to a misuse of procedure.

[15]     It  appears to be common ground between the parties that  Luxta is not in a position to raise any dispute or counter-claim as to the debt for the purposes of setting aside the statutory demand. It is not disputed that the payment claim was a valid payment claim under s 20(2) of the Construction Contracts Act 2002 (“CCA”). Moreover, s. 22 provides that a payer becomes liable to pay a payment claim if it does not provide a payment schedule to the payee within the stipulated time. Where

no payment schedule is provided, failure to pay the claimed amount allows the payee

to recover the unpaid portion of the claimed amount as a debt due. In Salem Limited

v Top End Homes Ltd (2005) 18 PRNZ 122 at [11], the Court of Appeal observed that:

“The  fundamental  position  under  the  Act  is  that,  if  a  progress  claim  is made and the employer does not respond within the period stipulated in the construction contract or, by default, within the time specified in the Act, the amount of the claim becomes payable forthwith.”

[16]     Moreover, s 79 of the CCA provides that, in any proceedings for the recovery

of a debt under s 23, the court must not give effect to any counterclaim, set-off, or cross-demand unless it is for a liquidated amount, and judgment has been entered for that  amount  or  there  is  no  dispute  between  the  parties  in  relation  to  the  claimed amount. It is well established that s 79 is applicable to statutory demands under the Companies  Act  1993:  Laywood  v  Holmes  Construction  Wellington  Limited  [2009] NZCA 35.

[17]     Capital Construction submits that the claimed amount became a debt due pursuant to s 23 of the CCA when Luxta failed to provide a progress payment schedule under special condition 12.2 of the contract in response to  Capital Construction’s payment claim. It contends that no valid grounds exist to set aside the demand, and that the two payment claims that were both withdrawn are not relevant

to the issue of whether there is a debt due and owing to it.

[18]     Capital Construction argues that it is not precluded from recovering the amount owed to it by issuing a statutory demand  simply  because  the  dispute  is before an expert. It refers to the “pay now, argue later” regime of the CCA, relying

on  a  comment  by  Mallon  J  in  Gill  Construction  Company  Limited  v  Butler  HC Wellington  CIV-2009-406-203,  2  November  2009  at  [9]  that  “the  CCA  has  been described  as  a  ‘pay  now,  argue  later’  regime  and  as  giving  rise  to  a  ‘temporary’ debt”.   In her judgment, Mallon J. then continued to note that, because it is a debt that may be enforced, a statutory demand can be issued in respect of it.  On this see also the comments of Wylie J. in Greys  Avenue  Investments  Ltd  v  Harbour Construction Ltd High Court, Auckland CIV-2009-404-2026, 12 June 2009 at paras. [36] and [37].

[19]     In  light of  the  authorities  relied  upon  by Capital  Construction,  in  my view Luxta’s  application to set aside the demand on the basis of abuse  of process or oppressive conduct must fail. Unlike Edge Computers Limited v Colonial Enterprises Limited, which was not a case involving a construction contract under the CCA, the debt in the present case is enforceable despite commencement of the alternative dispute resolution process. The regime under the CCA establishes an obligation to pay for a payment claim, unless the principal (in this case Luxta) issues

a payment schedule within the required timeframe, regardless of whether the claim is disputed. It follows that issuing a statutory demand to enforce the payee’s right to recover  the  claimed  amount  cannot  amount to an abuse of process, even if an alternative dispute resolution process has been instituted in the meantime. And here,

first, Capital Construction and Luxta are both experienced commercial parties quite familiar  with  the  strict  payment  requirements  of  the  CCA  and  secondly  Capital Construction  has  been  denied  the  cash  flow  benefits  so  important  to  contractors under the CCA on this payment claim 19 for nearly 6 months now.

[20]     As I see it, Capital Construction is entitled here to recover the unpaid portion

of the amount claimed in the statutory demand, being $441,929.82. Luxta failed to respond to the payment claim within the timeframe required by the contract, and the debt thus became due and owing on 24 August 2009. And s. 290(5) Companies Act

1993  clearly  provides  that  an  overstatement  of  a  debt  in  a  statutory  demand  in circumstances  such  as  the  present  does  not  invalidate  the  demand  –  Brookers Company and Securities Law CA290.03(4) – the part payment here does not affect the demand.

Result

[21]   For the reasons outlined above, the present application fails.

[22]     As  to  costs,  Capital  Construction  has  succeeded  here  in  opposing  Luxta’s application and is entitled to costs which are awarded on a 2B basis, together with disbursements as fixed by the Registrar.

[23]     Luxta  has  sought  an  extension  of  time  for  compliance  with  the  statutory demand pursuant to s. 290(3) Companies Act 1993. This is appropriate here and an order is made that Luxta is to have a period of 10 working days from the date of this judgment  to  comply  with  the  statutory demand  and  pay the  unpaid  portion  of  the amount claimed being $441,929.82.

‘Associate Judge D.I. Gendall’

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

1

Statutory Material Cited

1