| IN THE COURT OF APPEAL OF NEW ZEALAND |
| CA456/2012 [2012] NZCA 620 |
| BETWEEN HARRY ROY LAW AND SUK CHING LIAUW AND OTHERS |
| AND TAN CORPORATE TRUSTEE LIMITED AND OTHERS |
| CA458/2012 |
| BETWEEN CBD INVESTMENTS LIMITED |
| AND TAN CORPORATE TRUSTEE LIMITED AND OTHERS |
| Hearing: 30 October 2012 |
| Court: Arnold, Randerson and Wild JJ |
| Counsel: G A Muir for Appellants in CA456/2012 |
| Judgment: 21 December 2012 at 11am |
JUDGMENT OF THE COURT
A The appeals are dismissed.
B The appellants in CA456/2012 must each pay, jointly and severally, costs to the second respondents as for a standard appeal on a Band A basis with usual disbursements.
CThe appellant in CA458/2012 must pay costs to the second respondents as for a standard appeal on a Band A basis with usual disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Randerson J)
Table of Contents
Para No Introduction [1] The construction of the building [10] The Council notice [11] The additional repairs required to the exterior of the building [13] The validity of the BC rules The genesis of the rules [14] The statutory scheme [15] The relevant BC rules [20] Is r 2.1(e) ultra vires the 1972 Act? [22] Does default r 1(e) in the Second Schedule of the 1972 Act apply and, if so, what is its scope? [29] Is BC r 2.2(g) valid? [31] Was the Judge correct to find that it was inappropriate to make orders under s 37(12) of the 1972 Act? [37] Did the Judge err in approving the scheme under s 48 of the 1972 Act and in settling its terms relating to the apportionment of repair costs amongst the unit owners? [47] Grounds of appeal on the terms of the s 48 scheme [68] Discussion on the terms of the s 48 scheme [73] Conclusion [85]
Introduction
The Endeans Building at the foot of Queen Street, Auckland has stood for over a century. It is a building of considerable charm and heritage value. But, like many buildings in the city, it has developed serious weathertightness issues. This led the Auckland City Council to issue a Notice to Fix. The cost of carrying out the repairs required by the Council notice is likely to be at least $2 million. In addition, cracks and other damage to the exterior walls of the building have emerged. The cost of repairing the additional wall damage has yet to be assessed but is expected to be substantial.
Unfortunately, the 37 unit owners in the building have been unable to reach agreement about how the cost of repairs should be apportioned between them. The Body Corporate (BC), established under the Unit Titles Act 1972 (the 1972 Act) in respect of the building, brought proceedings in the High Court seeking declaratory relief as to the validity of some…
Keep reading for free
Create a free CaseChat account to read Law v Tan Corporate Trustee Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NZCA 620
- Decision Date
CaseChat Overview and Summary
The Court of Appeal found that BC rule 2.1(e) was ultra vires as it conflicted with the invalidity of rule 2.2(c), which imposed an obligation on the BC to repair and maintain the exterior walls, windows, and roof of the building. Consequently, default rule 1(e) in the Second Schedule of the 1972 Act applied, imposing an obligation on unit owners to repair and maintain their units. The Court also found BC rule 2.2(g) to be ultra vires, as it limited the liability of the ground floor unit owners from certain levies. The Judge was correct in finding that it was inappropriate to make orders under section 37(12) of the 1972 Act, as the unit owners had no obligation to repair and maintain the facade, which was private property. The Judge correctly exercised her discretion to approve the scheme under section 48, as it was necessary to ensure the timely and comprehensive repair of the building and the damage to its exterior. The approved scheme, which apportioned repair costs based on the physical area occupied by each unit, was fair to all unit owners and in the best interests of the unit holders as a group. The appeals were dismissed, and the appellants were ordered to pay costs to the second respondents.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established