Isaac Construction Ltd v Nu-Way Energy (NZ) Ltd

Link copied
Case Copied 78 min read

IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY

I TE KŌTI MATUA O AOTEAROA ŌTAUTAHI ROHE

CIV-2015-409-670

[2017] NZHC 1775

BETWEEN

ISAAC CONSTRUCTION LIMITED

Plaintiff

AND

NU-WAY ENERGY (NZ) LIMITED

Defendant

Hearing:

28 September - 5 October 2017, 27-30 November 2017, and

26-27 March 2018

Appearances:

C Shannon and L McLoughlin-Ware for the Plaintiff C Langstone and B Alcorn for the Defendant

Judgment:

18 July 2018


JUDGMENT OF MANDER J


ISAAC CONSTRUCTION LTD v NU-WAY ENERGY (NZ) LTD [2017] NZHC 1775 [18 July 2018]

Contents

Background  [2]

The bitumen plant  [2]

The burner  [6]
Installation of new burner  [12]

The fire  [15]
Events after the fire  [19]

Isaac Construction’s claim  [22]

Contract  [26]

Negligence  [27]

The prime issue – did the burner cause the fire?  [29]

Mr Jenkins’ theory of how the burner caught fire  [34] Mechanical damage to the tappet (seal holder) and the inner seal  [36] Blocked oil gallery and the testing of Mr Jenkins’ theory  [49]

Temperature of the oil  [71]

Atomisation  [75]
Ignition, burn back, and location of fire inside burner  [79]
The flame detector and the question of clean burning or incomplete

combustion  [83]

Failure of the burner housing  [91]
Conclusion relating to Mr Jenkin’s fire theory  [101]

The status or legality of the Nu-Way burner  [102]

Prototype or new design  [104]

Unregistered burner  [110]
Modification of the burner to run on diesel  [112]
Conclusions relating to the status of the burner  [114]

Sequence of alarms  [120]

Conclusions regarding sequence of alarms  [126]

Alternative causes of the fire  [128]

The thermal oil heater’s exhaust duct  [129]
Electric motor for the centrifuge pump  [132]

Thermal oil leak  [134]

Conclusion as to source of the fire  [140]

The question of liability  [154]

Alleged breach of contract  [155]

Fit for purpose at common law  [158]

Negligence  [174]
Alleged cause of breaches of duty of care  [175]
The burner did not have WorkSafe approval and could not be legally used  [176]
Failing to take appropriate steps having been told the burner was a

prototype  [179]

Res ipsa loquitur  [186]

The monitoring of the burner  [193]

Contributory negligence  [216]
Conclusion as to liability  [221]

Quantum  [222]

Replacement of the tank room (plant replacement)  [224]

Building interruption claim  [236]

Interest  [242]

Result  [243]

[1]    Isaac Construction Ltd (Isaac Construction) is a roading company which operates a bitumen plant. In April 2014, a new industrial burner was supplied and installed by the defendant, Nu-Way Energy (New Zealand) Ltd (Nu-Way), at Isaac Construction’s plant. Hours after the commissioning of the burner, a fire occurred at the plant. Isaac Construction claims the burner was the cause of the fire and sues Nu-Way for its resulting losses. Nu-Way denies liability.

Background

The bitumen plant

[2]    The bitumen plant consisted of a number of buildings, which included a large shed which housed holding tanks that contained bitumen. In order for bitumen to have sufficient viscosity to be in a usable state it is required to be kept at a certain temperature. The plant used a…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Isaac Construction Ltd v Nu-Way Energy (NZ) Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2018] NZHC 1775
Decision Date

CaseChat Overview and Summary

Isaac Construction Limited (Isaac Construction) sued Nu-Way Energy (NZ) Limited (Nu-Way) for damages following a fire at Isaac Construction's bitumen plant. Isaac Construction alleged that the fire was caused by a burner supplied and installed by Nu-Way. Nu-Way denied liability. Isaac Construction brought a claim for breach of contract, alternatively for negligence. The High Court held that Nu-Way had breached an implied term of reasonable fitness for purpose by supplying a faulty burner. The Court further held that Nu-Way had been negligent in its failure to adequately monitor the burner after it was installed. The Court found that Nu-Way's negligence was a material and substantial cause of the fire and the losses suffered by Isaac Construction. Isaac Construction was awarded damages in the sum of $428,540.95 (exclusive of GST) and interest. Nu-Way was ordered to pay Isaac Construction's costs of the proceeding on a 2B basis.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.