Greymouth Petroleum Holdings Limited v Todd Taranaki Limited HC WN CIV 2004-485-001651
[2008] NZHC 2425
•29 July 2008
IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV 2004-485-001651
BETWEEN GREYMOUTH PETROLEUM HOLDINGS LIMITED
First Plaintiff
ANDGREYMOUTH GAS KAIMIRO LIMITED
Second Plaintiff
ANDGREYMOUTH GAS COMPANY LIMITED
Third Plaintiff
ANDTODD TARANAKI LIMITED Defendant
Hearing: 1 October 2007
Counsel: M D O'Brien and P C S Sutherland for the Plaintiffs
H McIntosh and N Leslie for the Defendant
Judgment: 29 July 2008
JUDGMENT (NO. 4) OF WILD J: INQUIRY INTO DAMAGES SUSTAINED BY PLAINTIFFS
Introduction
[1] By application dated 24 July 2007 Greymouth applies for directions in respect of the inquiry into damages I ordered in my (first) judgment, delivered on 25
July 2006.
GREYMOUTH PETROLEUM HOLDINGS LIMITED AND ORS V TODD TARANAKI LIMITED HC WN CIV 2004-485-001651 29 July 2008
Factual background
[2] This is detailed in [6]-[45] of the judgment just referred to, with subsequent developments chronicled in [14] of my judgment (No. 3) of 29 June 2007.
[3] The salient points relevant to this judgment are:
a) Todd should have yielded occupation of the Ohanga-A well site to Greymouth, at the latest, when Todd’s lease of the well site expired on 31 August 2004.
b)The evidence established that the landowners of the well site (the Blakelocks) would have been prepared to give Greymouth a lease of the well site from 1 September 2004, had Todd not claimed an entitlement to a lease.
c) In April 2005 the Blakelocks changed the locks on the gates to the well site and on 22 April 2005 granted Greymouth a lease of the well site, subject to Todd not establishing a prior right to a lease.
d)Greymouth’s pleading in paragraph 50 of its fourth amended statement of claim of 12 December 2005 alleged that Todd’s occupation of the well site and exclusion of Greymouth from the site:
(d) has impeded (Greymouth’s) right to explore and/or mine the Ohanga land area and may thereby have caused damage to Greymouth, to an extent and in an amount which cannot be quantified without actual exploration and/or mining and enquiry.
Greymouth claimed an inquiry into the damages it had suffered.
e) The relevant parts of my 25 July 2006 judgment are:
[144] … (Greymouth) is entitled also to the inquiry into damages it seeks, and pursuant to r384 I order an inquiry accordingly.
…
[150] Greymouth is to submit for my approval a draft judgment which reflects these results, and includes the directions (pursuant to r385) it seeks as to the inquiry into damages I have ordered.
f) These orders were sealed in the following form:
(Greymouth) is entitled to and is hereby granted:
…
(c)An inquiry into damages suffered by the first and second plaintiffs as a consequence of (Todd’s) unlawful occupation of the Ohanga wellsite land, to proceed in accordance with directions to be made on the application by (Greymouth), such application to be filed and served within twelve months of the date of this judgment.
g) Todd did not vacate the well site until 27 July 2006: two days after my judgment of 25 July 2006. Greymouth then took physical possession of the well site.
h)Thereafter a Todd organised P&A of O-2 at the permit boundary was required, and was not completed until 28 February 2008, when Todd’s contractor, AWT, formally handed O-2 over to Greymouth.
i)In [30] of my judgment (No. 3) of 29 June 2007 I declined Greymouth’s application to extend the time for Greymouth to apply for directions as to the inquiry into damages, because Greymouth could still apply by the 25 July 2007 deadline.
j)Greymouth did not embark upon exploring O-1 or sidetracking O-2 until after Todd (its contractor AWT) completed the P&A of O-2 and handed the well site over to Greymouth on 28 February 2008.
Damages principles
[4] The measure of damages here is the tort measure: I effectively adjudged that
Todd was a trespasser on the well site after 31 August 2004.
[5] The tort measure aims to restore Greymouth, as the wronged party, to the position it would have been in but for Todd’s trespass: Gardiner v Metcalf [1994] 2
NZLR 8 (CA). There, Cooke P at 12 cited from the judgment of the High Court of
Australia in Haines v Bendall (1991) 172 CLR 60 at 63:
The settled principle governing the assessment of compensatory damages, whether in actions of tort or contract, is that the injured party should receive compensation in a sum which, so far as money can do, will put that party in the same position as he or she would have been in if the contract had been performed or the tort had not been committed …
[6] There were earlier statements by the Court of Appeal to similar effect in Stirling v Poulgrain [1980] 2 NZLR 402 at 419 and in McElroy Milne v Commercial Electronics Ltd [1993] 1 NZLR 39 at 49, and there have been subsequent reaffirmations by the Court of Appeal, for example in Hodge v Apple Fields Ltd (1999) 4 NZ ConvC 193,084 and Bloxham v Robinson (1996) 5 NZBLC 104,225.
[7] In Stirling v Poulgrain at 418 Cooke J observed, of the assessment of damages for breach of contract, that it was:
… a field which is governed more by broad principles than by hard-and-fast rules and in which there is considerable room for the exercise of discretionary judgment by the trial Court. …
[8] The same is equally true of the assessment of damages in tort, indeed in
Chase v de Groot [1994] 1 NZLR 613 at 627, Tipping J stated:
… The object of damages in tort is to put the plaintiff into the same position as would have prevailed if there had been no tort. Assessment of damages is essentially a question of fact. Any rules or principles constitute guidance only. The object is to be fair to both sides.
[9] Generally, damages are to be assessed at the date of the breach or wrong, but the Court of Appeal has made it clear that that general rule yields to the Court’s power to fix damages at such other date as will best achieve justice in the particular case: Stirling v Poulgrain per Cooke J at 420 and Richardson J at 424. This approach was confirmed in McElroy Milne per Cooke P at 44.
[10] Any required balancing should be struck in favour of Greymouth as the wronged party. As Megaw LJ said in Dodd Properties Ltd v Canterbury City Council [1980] 1 WLR 433 (CA) at 452:
If a balance had to be struck (between the interests of plaintiff and defendant), surely it would be right, even in a climate of indulgence to contract-breakers or tortfeasors, that the scales should be more heavily in the favour of the innocent party as against the wrongdoer, in any comparison of respective disadvantages or unfairness?
[11] Mr McIntosh submitted that difficulties in determining damages have never been a bar to the Court awarding them, referring to Chaplin v Hicks [1911] 2 KB 786 (CA). That is correct, but a Court must also do “the best it can” to assess damages in a way that is fair to both parties. For example, in Tai Hing Cotton Mill Ltd v Kamsing Knitting Factory [1979] AC 91, Lord Keith, delivering the judgment of the Privy Council, said at 106:
… In the result, their Lordships have come to the conclusion that the ends of justice would best be served if they were to fix a new figure of damages as best they can upon the available evidence, such as it is. …
That requirement to assess as accurately as the available evidence permits, argues for postponement of the inquiry, to a time when Greymouth will be best placed to provide evidence of the results of its exploration/mining from the well site.
Greymouth’s position
[12] Mr O’Brien submitted damages should be assessed after a period, equal to the
23 month trespass period, running from completion by Todd of the P&A of O-2, that allows Greymouth to explore and, if warranted, mine, as it could have done but for Todd’s trespass.
[13] That will enable accurate quantification of the revenues Greymouth would have earned but for Todd’s trespass. The alternative of relying on seismic survey and other available data is unattractive. Such data is notoriously uncertain, and any assessment of damages based on it would be nothing more than a speculative guess.
[14] Greymouth’s damages will comprise:
• Its loss resulting from the delayed receipt of mining revenues; and
•Any permanent loss of mining production and thus of revenues consequent upon the earlier exploitation of ‘across boundary’ reservoirs by adjoining miners, that would not have been lost but for the delay resulting from Todd’s trespass.
[15] Greymouth submitted that the order the Court made based on Greymouth’s pleading ([3]d) and e) above) precluded Todd from arguing now that the inquiry can proceed without actual exploration and (if warranted) mining.
[16] By consent (Greymouth having conceded Todd’s counterclaim), the Court ordered that Todd was obliged and entitled to P&A O-2 at the permit boundary. That was reflected in the sealed judgment as:
…
8. In respect of the defendant’s fifth counterclaim, by consent, the defendant is entitled and obliged, at the defendant’s cost and risk, to engage an IO to plug and abandon Ohanga-2 at the boundary between PMP 38150 and PEP 38762 (now PMP 38161) on terms to be agreed with the plaintiffs and submitted to the Court for approval.
[17] That obligation/entitlement arose when Todd’s right to explore/mine O-2 ended with the expiry of PPL 38705 on 31 January 2003. This was well before either:
• The expiry of Todd’s well site lease on 30 August 2004; and
•My judgment of 25 July 2006, which declared existing rights and obligations and did not create new ones.
[18] Todd’s proper course was to P&A O-2 at the permit boundary, promptly after
31 January 2003 when PPL 38705 expired. This course would have recognised that
Todd no longer had the right to mine using the top-hole section of O-2. [19] Had Todd done that:
a) Greymouth would have had the unimpeded access to the well site it was entitled to from 27 July 2006; and
b)An inquiry 23 months after 27 July 2006 could not reasonably have been opposed by Todd.
[20] The time the P&A has taken is attributable to Todd and not to Greymouth, save for the four month period from late February to late June 2007, during which Greymouth declined to agree to AWT being appointed as independent contractor.
[21] The point is that the P&A of O-2 was not completed until 23 February 2008, and Greymouth did not have unimpeded access to the well site until then. Thus, Greymouth asks that the inquiry be postponed for 23 months from 23 February 2008. Greymouth is not seeking damages for that delay in impeding its operations on the well site; its claim is for the delayed receipt of production revenues from mining wells drilled from the well site.
[22] Todd’s contention that Greymouth could have utilised the top-hold section of O-2 by drilling a new well from outside the well site should be rejected. The considerable extra time and expense involved should not be visited on Greymouth, since the cause would be Todd’s default in discharging its P&A obligations promptly.
[23] Similarly, Todd’s contention that Greymouth could have begun operations on O-1 after 27 July 2006 should be rejected. Greymouth was entitled to wait until Todd had completed its P&A of O-2 and had unimpeded access to the well site.
[24] No prejudice to Todd would result from an inquiry deferred as Greymouth requests.
Todd’s position
[25] The Court did not intend that Greymouth should have time actually to explore and/or mine before its loss was quantified.
[26] Granting the extra time sought by Greymouth is inconsistent with established damages principles:
a) Greymouth’s loss can be assessed now without prejudice to
Greymouth.
b)Greymouth can, and should, be compensated for the actual opportunity that was lost to it, assessed in the context that existed at the time, not for an equivalent but later period of time. Damages for deprivation of a commercial opportunity can be assessed on a “loss of a chance” basis. That involves the Court assessing the prospects of success of that opportunity had it been pursued. Difficulty in assessing damages has never been a bar to awarding them. Where there exists a clear method such as this for assessing damages, justice does not require or permit the parties to wait for actual loss to be suffered at some point in the future. Loss of chance damages can always be determined at the date of breach;
c) There is no legal basis for the Court to permit Greymouth to attempt to replicate the lost opportunity so as to be able to quantify it; and
d)Todd would be prejudiced if denied its right to have its liability determined now.
[27] The Court did not intend “to give Greymouth any additional opportunity to create an actual loss scenario”:
a) What is now sought was not claimed or argued at trial, or granted in the 25 July 2006 judgment.
b)In its 29 June 2007 judgment, the Court refused Greymouth an extension of time to apply for directions as to the inquiry into damages.
[28] The directions sought are not necessary properly to compensate Greymouth. In particular, an inquiry such as this is not to be an opportunity to replicate a lost opportunity so as to create a substitute loss figure.
[29] The damages can be assessed at the time of breach on a standard loss of chance basis. They could be assessed today. Todd seeks a direction that Greymouth be directed to file its statement of losses within one month (of 1 October 2007).
[30] The evidence indicates that Greymouth had no intention of drilling from the well site during the term of PEP 38762. That term was two years from 8 March
2004. Greymouth’s work programme did not focus on the Ohanga wells. Todd was aware of that, and assessed its risk accordingly.
[31] Greymouth’s suggested 23 month trespass period is “an entirely arbitrary period of time”. Logically, Greymouth’s argument would justify deferring the inquiry indefinitely.
[32] Deferring the inquiry would be pointless because any evidence adduced by Greymouth of subsequent exploration/mining would be inadmissible in the inquiry. It would be about damage from a different time period, with Greymouth having different – and superior – knowledge e.g. knowledge acquired from drilling its Turangi well in the interim.
[33] Greymouth has had ample time to quantify its loss having had uninterrupted access to the well site since 27 July 2006. Factually, the P&A of O-2 has not prevented Greymouth assessing its loss.
[34] Even if the Court were minded to grant Greymouth an equivalent “replacement” period of time to assess its damages, that period should only be the 15 months running from 23 April 2005 (when the Blakelocks gave Greymouth a conditional lease of the well site) to 27 July 2006 (when Todd vacated the well site).
Decision
[35] I hold that Todd should have attended to the P&A of O-2 at the permit boundary after PPL 38705 expired on 31 March 2003. Beyond that date, Todd had no right to explore or mine O-2 from the well site.
[36] Had Todd done that, the P&A would have been completed by the time Todd’s lease of the well site expired 17 months later on 30 August 2004. I base that finding on the 18 months the now completed P&A actually took, less the four month delay which Greymouth accepts resulted from its refusal to accept AWT as an appropriate independent contractor for the P&A operation (i.e. the periods referred to in [3]h) and [20] above, respectively).
[37] I accept Greymouth’s submission that, had Todd done that, Greymouth would have had unimpeded access to the well site when it took possession on 27 July
2006.
[38] I also accept Greymouth’s point that Todd could not reasonably have objected to an inquiry proceeding 23 months later i.e. after the equivalent of the period during which Todd wrongfully claimed to have a right to a lease of the well site, shutting Greymouth out.
[39] That would have given Greymouth the 23 month opportunity or chance to explore and mine from the well site that was lost to it as a result of Todd’s trespass.
[40] An inquiry into the damages suffered by Greymouth, conducted as at 27 June
2008 (23 months after 27 July 2006), would be broadly in accordance with the judgment of the High Court of Australia in Johnson & Ors v Perez (1988) HCA 64; (1988) 82 ALR 587, relied upon by Todd. I say ‘broadly’, because the approach of Mason CJ in awarding damages at the notional trial date(s) differed slightly from that of the majority, who awarded damages as at the date the plaintiff’s personal injury claims against his employer were struck out.
[41] What has delayed Greymouth from starting exploration and mining is the
P&A of O-2 spanning the 18 months from September 2006 to February 2008.
[42] I hold that it was reasonable for Greymouth to postpone exploration and mining from the well site until the P&A of O-2 was completed and Greymouth had the unimpeded use of the well site.
[43] I also hold that it was reasonable for Greymouth to restrict its exploration and mining to the well site, using the existing well bores. I reject Todd’s submission that Greymouth could and should have mined O-2 reservoirs by drilling a new well from outside the well site. I treat that as a plea that Greymouth has failed to mitigate its losses. But the material available to me does not support that submission.
[44] I have already held that Todd should have completed the P&A of O-2 by 27
July 2006. Greymouth is not to be disadvantaged by Todd’s default in not completing that P&A in a timely way. Or, to put the matter round the other way, Todd is not to be permitted to take advantage of its own default: Moreton v Montrose [1986] 2 NZLR 496, in which Cooke J said at 503:
“The rule that a party cannot take advantage of his own wrong is fundamental: New Zealand Shipping Co Ltd v Societe des Ateliers et Chantiers de France [1919] AC 1; Panamena Europea Navigacion (Compania Limitada) v Frederick Leyland & Co Ltd [1947] AC 428,
436.”
[45] Todd’s opposition to Greymouth’s application to defer the inquiry into damages is based on Greymouth’s claim being one for damages resulting from loss of opportunity. Todd argues that such losses can be assessed equally accurately at any time. For two reasons, I reject that.
[46] First, the primary component of Greymouth’s claim is not one for damages for loss of opportunity. The components of Greymouth’s claim are as I have set them out in [14] above. Those are claims for losses resulting from the delays consequent upon Todd’s trespass: loss resulting from delayed receipt of production revenues; permanent loss of such revenues resulting from the earlier exploitation of
‘across boundary’ reservoirs by other miners.
[47] The first of those two heads of claim is not one for damages for loss of opportunity, in the sense that that term is generally understood in the law of damages. With rare exceptions (Chirnside v Fay (No. 2) [2005] 3 NZLR 689 may be one) the loss of opportunity cases involve permanent loss of the opportunity. Greymouth still has the opportunity to earn revenues from mining petroleum from O-1 and/or O-2, or a third well drilled from the well site. It is simply that those revenues will be received considerably later than would have been the case, but for Todd’s trespass. So the first claim is essentially for the time cost of money. The second head of claim (for revenues lost permanently) is a claim for damages for lost opportunity.
[48] Second, deferring the inquiry to give Greymouth 23 months of unimpeded exploration and mining from the well site cannot prejudice Todd in that it will give Greymouth a “further substantive advantage over its original position”. The knowledge position will be exactly as it would have been had the inquiry proceeded as at 27 June 2008 i.e. it will be with the benefit of 23 months of unimpeded mining and exploration by Greymouth.
[49] Certainly the damages may be higher because the delay period is longer, but the responsibility for that delay rests with Todd.
[50] Similarly, Todd has only itself to blame for any prejudice resulting from an inability to have its liability determined now.
[51] Accordingly, I grant Greymouth’s application and direct:
a) By 23 September 2009 Greymouth is to file and serve a statement detailing the losses it alleges it has suffered as a consequence of Todd’s unlawful occupation of the Ohanga well site from 31 August
2004 to 27 July 2006.
b)Todd is to file and serve any statement in response/opposition to Greymouth’s statement of losses within 30 days of service upon it of Greymouth’s statement.
[52] I reserve to both parties leave to apply at any time for further direction. [53] Todd is to pay Greymouth’s costs of this application on a 3B basis.
Solicitors:
Bell Gully, Wellington for the Plaintiffs
Russell McVeagh, Wellington for the Defendant
0
3
0