IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
CIV-2016-419-287 [2017] NZHC 286
UNDER The Companies Act 1993 BETWEEN
GREEN MEADOWS FARM COMPANY LIMITED
Applicant
AND
TECHNI-PLAN LIMITED Respondent
Hearing: 22 February 2017 Appearances:
Mr J Forsey for Applicant
M K Badcock for RespondentJudgment:
3 March 2017
JUDGMENT OF ASSOCIATE JUDGE J P DOOGUE
This judgment was delivered by me on
03.03.17 at 3.30 p.m., pursuant to
Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date……………
GREEN MEADOWS FARM COMPANY LIMITED v TECHNI-PLAN LIMITED [2017] NZHC 286 [3 March
2017]
Background and introduction
[1] The present dispute arises out of construction work which was carried out on a dairy shed and bridge, both of which are located on rural land near Otorohanga. The construction work was carried out by the respondent company, Techni-Plan Ltd (“TPL”). The managing director of TPL was Mr Daniel Roberts. The respondent submitted a quotation for the dairy shed in February 2016 and the price was
$435,000. The respondent also submitted a quotation in the same month to build the bridge for a sum of $56,840.
[2] While there is clarity about the identity of the party which was to do the construction work, one of the key issues that arise in this case is the identity of the party which was to be the principal under the contract.
[3] The respondent says that the correct party to the contract was Green Meadows Farm Co Ltd (“GMFCL”), while the applicant, GMFCL, says that it was Hammond Dairy Farm Ltd (‘HDFL”).
[4] It is common ground that in February 2016 two documents, which were intended to be construction contracts, were entered into. One was for the construction of a dairy shed and the other a bridge. It is further agreed that the company required to carry out the construction was the respondent. There is a dispute, though, about which of the two companies named above the respondent actually contracted with.
[5] Because of that dispute, the parties are unable to agree that invoices rendered for partial construction of the dairy shed and bridge were payable by GMFCL, which is the company from which the respondent has claim to payment. The applicant agrees that the contract was entered into, but it says that the principal under that contract was HDFL.
[6] The background to how the dispute comes before the Court is as follows. The respondent has claimed that it served payment claims on GMFCL under the Construction Contracts Act 2002 (“CCA”). They say that GMFCL did not effectively respond by way of payment schedules, with the result being that GMFCL
became liable for the costs of the construction. The respondent seeks to enforce what it sees as its right to recover payment by serving a statutory demand upon GMFCL under s 289 of the Companies Act 1993. The applicant has applied to set aside that statutory demand pursuant to s 290 of the Act.
[7] It is common ground that GMFCL is…
Keep reading for free
Create a free CaseChat account to read Green Meadows Farm Company Limited v Techni-Plan Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] NZHC 286
- Decision Date
CaseChat Overview and Summary
The Court examined the contractual documents, which referred to "GMFCL-Hammond" but did not specify a legal entity. TPL argued that GMFCL was the principal, while GMFCL contended that HDFL was the correct party. The Court considered the lack of clarity in the contracts, the subsequent conduct of the parties, and the absence of any clear evidence indicating the intended principal. The Court concluded that there was a substantial dispute concerning the identity of the contracting party, and thus the statutory demand could not be enforced without further clarification.
The Court ordered that the statutory demand be set aside and directed that the matter be resolved in ordinary proceedings. GMFCL was awarded costs on a 2B basis, along with disbursements to be fixed by the registrar.