IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
I TE KŌTI MATUA O AOTEAROA TE WHANGANUI-A-TARA ROHE
CIV-2024-485-561
[2024] NZHC 3660
UNDER The Contract and Commercial Law Act 2017 and the Building Act 2004 IN THE MATTER
of a breach of contract for the construction of a house
BETWEEN
MATTHEW PAUL GERRIE AND KIRSTY FRANCES WEIR
Plaintiffs
AND
NEW VISION PROPERTIES LIMITED
Defendant
Hearing: 28 November 2024 Appearances:
M Freeman for Plaintiffs
Judgment:
4 December 2024
JUDGMENT OF McQUEEN J
Table of Contents
Para Nos
Introduction [1]
The requirements of formal proof [5]
Background [9]
The Contract [11]
Progress of the building work [18]
Cost of completion [53]
The claim [58]
GERRIE AND WEIR v NEW VISION PROPERTIES LIMITED [2024] NZHC 3660 [4 December 2024]
First cause of action repudiation/breach of the Contract [61]
Repudiation under s 36 of the CCLA [65]
Breach under s 37 of the CCLA [71]
Damages [83]
Second cause of action—breach of statutory warranties [95]
Deposit [106]
Interest and costs [111]
Orders [113]
Introduction
[1] Dr Matthew Gerrie and Dr Kirsty Weir purchased a section from the defendant, New Vision Properties Ltd (NVP), a builder/developer. Dr Gerrie and Dr Weir were required to contract with NVP to build a house on the section. Dr Gerrie and Dr Weir entered a building contract with NVP (the Contract).
[2] Dr Gerrie and Dr Weir terminated the Contract, for repudiation and breach, on 31 May 2024.
[3] Dr Gerrie and Dr Weir filed and served a statement of claim on 26 August 2024. No statement of defence has been filed by NVP in the time specified in the notice of proceeding accompanying the statement of claim. Both Dr Gerrie and Dr Weir have filed affidavits setting out the background to the claim. An affidavit confirming service of the Court documents on NVP has also been filed.1
[4]Dr Gerrie and Dr Weir now seek formal proof of the claim.
The requirements of formal proof
[5] Rule 15.9 of the High Court Rules 2016 (the Rules) provides for the formal proof of claims. This is available where the defendant does not file a statement of
1 An affidavit of service of the statement of claim and notice of proceeding must be filed before judgment by default can be sealed; High Court Rules 2016, r 15.4.
defence in accordance with the timeframe required by the notice of proceeding and the plaintiff seeks judgment by default for other than a liquidated demand.
[6] The plaintiff must, before or at the formal proof hearing, file affidavit evidence establishing, to a Judge’s satisfaction, each cause of action relied on and, if damages are sought, providing sufficient information to enable the Judge to calculate and fix the damages.2
[7] The relevant principles in relation to formal proof under r 15.9 of the Rules were considered by Duffy J in Ferreira v Stockinger.3 Her Honour said:
[33] Now r 15.9 of the High Court Rules applies to a formal proof hearing when no statement…
Keep reading for free
Create a free CaseChat account to read Gerrie v New Vision Properties Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NZHC 3660
- Decision Date
CaseChat Overview and Summary
The court was required to determine whether the plaintiffs were entitled to judgment by default based on the defendant's failure to respond and to assess the merits of the plaintiffs' claims for repudiation, breach of contract, and statutory warranties under the Building Act 2004. The court also needed to decide on the appropriate quantum of damages, including the cost of completion, remedial work, wasted expenditure, and the return of the deposit.
The court found that the defendant had repudiated the contract by its conduct, including the failure to progress the building work and its refusal to continue unless additional payments were made. The court concluded that the plaintiffs were entitled to cancel the contract under sections 36 and 37 of the Contract and Commercial Law Act 2017. The court further determined that the defendant had breached multiple obligations under the contract, fulfilling the criteria for cancellation under section 37. The plaintiffs were entitled to damages calculated as the cost to complete the building work, the cost of remedial work for defective framing, and wasted expenditure on joinery that was never supplied. The court also found that the plaintiffs were entitled to the return of their deposit and awarded interest on the judgment sum and costs.
In summary, the court granted the plaintiffs' claims, ordering the defendant to pay the judgment sum, return the deposit, and cover interest and costs.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.