IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
I TE KŌTI MATUA O AOTEAROA TE WHANGANUI-A-TARA ROHE
CIV-2021-404-2385
[2023] NZHC 1009
BETWEEN G K SHAW LIMITED
Applicant
AND
JOHN GREEN
First Respondent
AND
CENTREPORT LIMITED
Second Respondent
On the Papers Judgment:
1 May 2023
JUDGMENT OF ISAC J
[Costs]
Introduction
[1] In a judgment of 24 March 2023, I declined G K Shaw’s application for judicial review of an adjudicator’s decision n in a dispute under a construction contract.1
[2] The successful respondent, CentrePort Ltd, now seeks costs of $40,689.75, being 2B costs of $27,126.50 with a 50 per cent uplift. CentrePort says that an increased costs award is appropriate because G K Shaw’s claim was without merit and inherently unlikely to succeed.2 Further, it contends that the proceeding was a continuation of the abuse of process in the underlying proceeding whereby G K Shaw, having failed in a first adjudication, sought to litigate the same claim a second time before a different adjudicator.
1 G K Shaw Ltd v Green [2023] NZHC 605.
2 Pursuant to r 14.6(3)(b) of the High Court Rules 2016.
G K SHAW LTD v GREEN & ANOR [2023] NZHC 1009 [1 May 2023]
[3] G K Shaw agrees that costs should be awarded on a 2B basis, but takes issue with CentrePort’s claim for increased costs. It says that CentrePort’s 2B costs ought to be $24,354.15. G K Shaw submits that its behaviour in bringing and conducting the proceeding was entirely appropriate, and that the high threshold for increased costs has not been met. In the alternative, it suggests that the Court consider ordering that costs lie where they fall on the grounds that the proceeding concerned a matter of public interest.
Consideration
[4] All matters relating to costs are discretionary,3 although that discretion must be exercised on a principled basis. So far as possible the determination of costs should be predictable and expeditious.4
[5] While G K Shaw’s argument was novel and in an area not often litigated, I do not consider that the proceeding involved any significant public interest or important matter of public policy. Certainly, there was nothing to justify a departure from the ordinary principle that costs should follow the event.5 The question then is quantum. In that respect, the parties agree that the appropriate scale is 2B.
[6] The difference between the parties’ positions is less than $3,000. In essence, G K Shaw argues that CentrePort cannot claim costs for the preparation of case management conferences that did not occur (because they were vacated by consent in advance or were never scheduled), and should not be awarded the full scale in relation to the filing of joint memoranda which G K Shaw helped to prepare and file. In my view, CentrePort is entitled to costs for preparation for case management conferences which did not proceed on the basis of joint memoranda that were filed. It follows that I accept its claim for costs for the first case…
Keep reading for free
Create a free CaseChat account to read G K Shaw Limited v Green and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] NZHC 1009
- Decision Date
CaseChat Overview and Summary
The court considered the discretion in awarding costs, emphasizing the need for predictability and expeditiousness. It was noted that while the applicant's argument was novel and in an area not frequently litigated, the proceeding did not involve significant public interest or important public policy. The court found the appropriate scale for costs to be 2B, and it resolved the minor differences in cost claims between the parties. G K Shaw’s contention regarding costs for case management conferences that did not proceed was partially upheld, resulting in the court awarding CentrePort costs of $26,170.50.
Regarding increased costs, the court held that such costs may only be awarded in cases of unreasonable conduct, and it was not persuaded that G K Shaw’s conduct met the high threshold for increased costs. The applicant's challenge, though ultimately unsuccessful, raised a legitimate question regarding the jurisdiction of adjudicators under the Construction Contracts Act 2002, which was capable of bona fide argument. Therefore, the court did not find the threshold for increased costs to be met.
In conclusion, the court ordered G K Shaw Limited to pay CentrePort Limited's costs on a 2B basis of $26,170.50, plus disbursements of $110.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.