IN THE SUPREME COURT OF NEW ZEALAND
SC 3/2006
[2006] NZSC 44
BETWEENELLERSLIE PARK HOLDINGS LIMITED
Applicant
ANDTHE ATTORNEY-GENERAL
Respondent
Hearing:12 June 2006
Court:Blanchard, Tipping and McGrath JJ
Counsel:B O'Callahan and G S Erskine for Applicant
M T Scholtens QC and C J Mathieson for Respondent
Judgment:20 June 2006
JUDGMENT OF THE COURT
1.The application for leave to appeal is dismissed.
2.The applicant must pay to the respondent $2,000 in costs plus any reasonable disbursements, to be fixed by the Registrar.
REASONS
[1] Ellerslie Park Holdings Limited has applied for leave to appeal against a judgment of the Court of Appeal, striking out claims by the applicant, and other parties, against the Attorney-General.
[2] The plaintiffs in the proceeding are the body corporate for, and individual apartment owners of, a complex known as the “Sacramento” development in Manukau City. The complex is affected by leaky building syndrome. The applicant is a defendant builder, alleged by the plaintiffs to have constructed the complex negligently. The Attorney-General is another defendant, sued in respect of the liabilities of the former Building Industry Authority, which were assumed by the Crown under the Building Act 2004.
[3] The Authority was a statutory regulator of building practices, and is alleged to be liable for the leaky building syndrome damage as a result of negligence in the performance of those functions. The plaintiffs allege that the Authority owed them various duties of care, in particular as clients of the building certifier who certified compliance with the building code, and in the approval of the use of face-fixed monolithic cladding over untreated timber.
[4] The applicant cross-claimed against the Authority for contribution, repeating the plaintiffs’ allegations of its breaches of duty and adding that it was also a breach of duty to the applicant for the Authority to approve, as part of its “Acceptable Solution B2/AS1”, the use of untreated kiln dried timber at all.
[5] The Attorney-General applied to the High Court to strike out the various claims brought against the Crown. Williams J dismissed the application in so far as it had sought to strike out claims concerning the Authority’s approval of Acceptable Solution B2/AS1, its refusal to amend or revoke that approval, its review of the approval of the building certifier for the project, and its alleged failure to arrange adequate insurance cover for the certifier.
[6] The Attorney-General appealed to the Court of Appeal. The Attorney-General’s submissions in that Court were structured to address the findings of the High Court and followed the same course. The applicant’s cross-claim was not dealt with separately from those of the plaintiffs in the Attorney‑General’s submissions but treated as if part of the plaintiffs’ claims.
[7] The Attorney-General and the plaintiffs were represented by counsel at the hearing of the appeal but the applicant was not. In a memorandum filed on 21 October 2005, shortly before the hearing, the applicant notified the Court of Appeal that it would not appear or make submissions for economic reasons, adding that…
Keep reading for free
Create a free CaseChat account to read Ellerslie Park Holdings Ltd v AG and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] NZSC 44
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi