Coughlan v Abernethy HC Auckland CIV 2009-004-2374

Case

[2010] NZHC 2180

20 October 2010

No judgment structure available for this case.

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY

CIV-2009-004-2374

UNDER  The Weathertight Homes Resolution

Services Act 2006

IN THE MATTER OF     an appeal against a decision of the

Weathertight Homes Tribunal

BETWEEN  R COUGHLAN First Appellant

ANDT HUMPHREY Second Appellant

ANDV E ABERNETHY AND A R ABERNETHY

First Respondents

ANDTHE NORTH SHORE CITY COUNCIL Second Respondent

ANDSTOCKDALE INVESTMENTS AUCKLAND LIMITED

Third Respondent

ANDC I BEAZLEY Fourth Respondent

Hearing:         4 May 2010

Appearances: A Maclean for First and Second Appellants

M C Josephson and S E Mitchell for First Respondents
No appearances for Second, Third and Fourth Respondents

Judgment:      20 October 2010

RESERVED JUDGMENT OF WHITE J

This judgment was delivered by me on 20 October 2010

At 4 pm, pursuant to r 11.5 of the High Court Rules

Registrar/Deputy Registrar

Solicitors:      Alistair Maclean, PO Box 147-422, Ponsonby

Grimshaw & Co, PO Box 6646, Auckland 1141

COUGHLAN AND ANOR V  ABERNETHY AND ORS HC AK CIV-2009-004-2374  20 October 2010

TABLE OF CONTENTS

Introduction  [1] Factual background  [3] Tribunal decision  [9] The appeal and cross appeal  [21] Approach to appeal  [25] Duty of care  [31] Voluntary assumption of risk  [42] Liability of Mr Coughlan  [51] Mr Humphrey’s liability  [74] The cross-appeal  [86] Were Messrs Coughlan and Humphrey developers?  [88] Apportionment  [89] Remedial costs  [101] Mitigation and contributory negligence  [106] General damages  [114] Result  [121]

Introduction

[1]      In this appeal under the Weathertight Homes Resolution Services Act 2006

Richard Coughlan and Trevor Humphrey (Messrs Coughlan and Humphrey) challenge on some eight grounds of law and fact the decision of the Weathertight Homes  Tribunal  holding  them  jointly  and  severally  liable  to  pay  Vanessa  and Alan Abernethy  (the   Abernethys)   damages   of   $60,310.86   in   respect   of   the Abernethys’ “leaky home”.  The Abernethys cross-appeal challenging the Tribunal decision on some five grounds of law and fact.

[2]      Following the hearing of the appeal on 4 May 2010, the parties filed an agreed chronology and separate supplementary memoranda relating to a chronology of mitigation carried out by the Abernethys.  Counsel for the Abernethys also filed a

memorandum   dated   16   June   2010   drawing   the   Court’s   attention   to   the supplementary judgment of the Court of Appeal in Byron Avenue1  relating to the awards of general damages for the leaky homes in that case.

Factual background

[3]      In 1994 Stockdale Investments Auckland Limited (Stockdale), a company owned at material times by Messrs Coughlan and Humphrey, obtained consent from the  North  Shore  City  Council  to  build  a  house  on  a  property at  5/6 City View Terrace,   Birkenhead,   Auckland.      Mr   Coughlan   designed   the   house   and Mr Humphrey  administered  the  project.     When  the  house  was  completed  in December 1994, the Council issued a code compliance certificate.   Stockdale sold the property to a Korean family who occupied it for some nine years until they resold it to the Abernethys in 2003.

[4]      The original agreement for sale and purchase of the property for $446,000 dated  27  July 2003  was  conditional  on  the  Abernethys  receiving  a  satisfactory building  report  from  Futuresafe  Building  Inspections  Limited.    Mr Beazley,  an employee of Futuresafe Building Inspections Limited, inspected the property and prepared two reports identifying a number of defects which he considered had arisen largely because the property had not been properly maintained and which were estimated to cost around $10,000 to remedy.  On the basis of Mr Beazley’s reports, the Abernethys negotiated a $3,000 reduction in the purchase price and settlement took place in September 2003.    The Abernethys arranged for the repairs recommended by Mr Beazley to be carried out.

[5]      After noticing a new problem, bubbling paint inside near the front door, the Abernethys lodged a claim with the Weathertight Homes Resolution Service in late October    2003.       The    Weathertight    Homes    Resolution    Service    assessor, Mr Alan Light, carried out two investigations of the property.   In his first report dated 28 July 2004, Mr Light found that the Abernethys’ claim was eligible as a “leaky building” and estimated the cost of repair work at $10,597.50 over and above what the Abernethys had already spent doing the repairs recommended by

1 Byron Avenue [2010] NZCA 234. Leave to appeal has been granted: Byron Avenue [2010] NZSC

78.

Mr Beazley.   Although  the Abernethys lived in the house on the property until January 2005 when they left for Dubai and rented the property out, the work recommended by Mr Light was not carried out.

[6]      In Mr Light’s second report dated 21 June 2007 he estimated the costs of remediation at $115,500.23.

[7]     On 17 March 2009 the Abernethys filed a statement of claim with the Weathertight Homes Tribunal seeking damages for negligence of $334,846.10 (including GST), comprising $201,568.06 for repair costs, $39,100 for professional fees, $32,225 for consequential losses, $3,953.04 for costs incurred mitigating loss and $60,000 for general damages.  The claim was against Mr Coughlan as designer, Mr  Humphrey as  project  manager,  the  North  Shore  City Council,  Stockdale  as developer and Mr Beazley.  The claim listed the following defects:

a)        Lack of subfloor ventilation;

b)        Inadequate ground clearance;

c)        Lack of control joints to exterior cladding;

d)       Direct contact of the exterior fibre cement cladding with the ground;

e)        A flat topped timber capping to the deck barrier walls;

f)        Lack of saddle flashings to deck balustrades;

g)        Inadequate clearance between the cladding, decks and roof flashings;

h)        Inadequate jam flashings;

i)         Inadequate head flashings; and

j)         Gate post penetration to eastern wall.

[8]      The Tribunal hearing took place on 24 and 26 June 2009 with submissions on

1 July and supplementary written submissions on 8 and 9 July 2009.  Shortly after the hearing started the claim against the Council was settled for $90,000.

Tribunal decision

[9]      The Tribunal’s decision was issued on 12 February 2010.  After summarising the factual background and the expert evidence relating to the defects in the house, the Tribunal concluded:

[53]     Having regard to the experts’ evidence, the major causes of water ingress  and  damage  are  lack  of  sub-floor  ventilation;  lack  of  a  vertical control joint to exterior cladding at the back of the building, direct contact of the cladding with the deck stringer combined with inadequate drainage at the back of the building; inadequate installation of the window at the front of the east wall at the entrance; and the flat topped timber capping to the deck barrier walls or balustrades especially at the south front of the building.

[10]     On the question of the reasonable cost of repairs, the Tribunal accepted as a matter  of  commercial  reality that  the  Abernethys  would  have to  pay a total  of

$201,568.06 to effect remediation and that there should therefore be no deduction for betterment.   The Tribunal also accepted that the $39,100 claimed for professional fees was reasonable.

[11]     After   considering   the   relevant   evidence,   the   Tribunal   decided   that Mr Coughlan had been negligent as architectural designer in leaving vents out of the drawings when they should have been included and in omitting any reference to the manufacturer’s instructions on the plans, but not in any other respects.  The Tribunal did not accept that Mr Coughlan was negligent as project manager or as a developer. In summary the Tribunal found Mr Coughlan as the designer jointly and severally liable to the Abernethys in the sum of $60,310.86.

[12]     After considering the relevant evidence and after taking into account the decision  in  Body  Corporate  185960  v  North  Shore  City  Council,2   the  Tribunal decided that Mr Humphrey was liable as project manager.  The Tribunal said:

2    Body  Corporate  185960  v  North  Shore  City  Council  HC  Auckland  CIV-2006-404-3535,

22 December 2008.

[109]  Based on that principle, I find that as the project manager or administrator Mr Humphrey was responsible for supervising workmanship unless someone else was appointed to that role.  This position went beyond his role as a director of the company (just as Mr Coughlan’s position as designer went beyond his role as a director.)  I do not consider that the fact Mr Humphrey worked part-time as project manager is sufficient to conclude that he did not owe a duty of care in that capacity.  Accordingly I find that Mr Humphrey was in breach of his duty of care as project manager in not taking steps as project manager to ensure the workmanship on site was adequate.

The  Tribunal  did  not  accept  that  Mr  Humphrey was  liable  as  a  developer.    In summary the  Tribunal  found  Mr  Humphrey  as  the  project  manager  jointly and severally liable to the Abernethys in the sum of $60,310.86.

[13]     The Tribunal accepted that Stockdale was the developer and was responsible for the leaks and damage which arose from its negligence.   The Tribunal found Stockdale as the developer jointly and severally liable to the Abernethys in the sum of $60,310.86.

[14]     After considering the relevant evidence, the Tribunal made the following findings in relation to Mr Beazley:

[135]    I find that Mr Beazley was negligent in not identifying the lack of ventilation holes in the base of the building, but I do not find that there was a widespread failure on his part in the discharge of his duty to the claimants as they allege.  I do not find that his conclusion that these were maintenance issues was a negligent failure – there was a widespread lack of maintenance and neglect – or a negligent misstatement or a breach of the Fair Trading Act on his part.  On balance I do not accept that Mr Beazley was negligent as a pre-purchase inspector in his advice to Mr and Mrs Abernethy, given his brief and the limitation of not doing invasive testing, except for his failure to identify the lack of ventilation to the under floor space.

[136]    Mr Beazley’s liability relates to that failure.  Even that is mitigated to a degree by his belief that he was unable to remove interior panels to inspect the joists.

[137]    In summary I find Mr Beazley as pre-purchase inspector jointly and severally liable to the claimants for the limited amount only of $9,046.63, as set out in paragraphs 32 to 58, this section, and paragraph 138 onwards including 183/IV, arising from and limited to his failure to identify one important defect, the absence of vents, which could have been remedied in isolation.

[15]     The Tribunal then turned to consider how much of the cost of repairs was “compensable”.  The Tribunal did not consider that all the defects were the result of negligence.   The Tribunal concluded that the  remediation to repair parts of the

building was required because of the way the buildings were designed, approved and built at the time and that negligence was only part of the reason.  The Tribunal then considered the walls of the property and concluded that the costs of repairing the north and east walls should be compensated for, but that the costs of repairing the south and west walls should not be included.  On the basis of the quantity surveyor evidence,  the  Tribunal  then  decided  that  the  compensatable  proportions  of  the

$240,668.06 for repairs and professional fees should be 35 per cent (north wall) plus

15 per cent (east wall) making 50 per cent, that is $120,334.03.

[16]     Turning then to the question of other damages, the Tribunal accepted the figure of $30,225 for consequential losses (reduced or lost rental income including lost rent while repairs were being carried out), but did not accept that a figure of

$60,000 for general damages was reasonable because the Abernethys had not lived in  the  house  for  over  four  and  a  half of  the  six  years  since  they bought  it  in September 2003.  For this reason the Tribunal reduced the claim for general damages to $7,500 for Mrs Abernethy, who had borne the major share of the burden, and
$5,000 for Mr Abernethy.  The Tribunal accepted the claim for $3,953.04 for costs incurred in mitigating the loss.   On this basis the overall claim was reduced to

$167,012.07.

[17]     On the question of contributory negligence and failure to adequately mitigate loss by the Abernethys, the Tribunal found that there was an element of contributory negligence in that they knew that the building was built of risky materials; that it had been badly neglected by the vendors; and that it was likely moisture had already penetrated the building envelope.  The Tribunal said:

[164]    It was not Mr and Mrs Abernethy’s fault that the building was in such a poor condition when they bought it, but nor was that the respondents’ fault either.   Mr and Mrs Abernethy did take a calculated risk that such a building would not turn out to be leaky.

[165]    For those reasons, notwithstanding that the precautions and steps they took were reasonable, Mr and Mrs Abernethy must share in the above costs  of  its  having  turned  out  to  be  a  ‘bad  buy’.    They  should  not  be penalised for having obtained pre-purchase reports; but neither does their having done so absolve them from having to take some responsibility for their decision to purchase this townhouse.   I find Mr and Mrs Abernethy were also negligent, for those reasons.

[18]   Taking into account the Abernethys’ failure to mitigate their losses by immediately taking steps to have ventilation installed and sheeting laid over the ground in the sub-floor area after the first Weathertight Home Resolution Service report was received and deciding to live abroad in January 2005 when the problems with the house that Mr Light had identified in July 2004 were still unresolved, the Tribunal decided that the figure of $167,012.07 should be reduced by 10 per cent giving a final figure of $150,310.86.

[19]     The Tribunal next considered the impact on the claim of the settlement with the Council for $90,000 and decided that that amount needed to be deducted from the   claim,   leaving  $60,310.86   still  to  be   recovered.     On   the   question   of apportionment of damages, the Tribunal decided, after considering the provisions of s 17 of the Law Reform Act 1936 and after taking into account the fact that the Council took a commercial risk in settling with the claimants, that it would not be fair on the other liable parties for there to be some apportionment of the liability of the Council with the other parties.  The Tribunal then concluded:

[181]   Having regard to all the evidence, I consider that Stockdale as developer bears the greatest responsibility for the losses, and Mr Coughlan as the designer and Mr Humphrey as the project manager bear a greater share of the responsibility than Mr Beazley as pre-purchase inspector.  A fair and equitable apportionment is – Stockdale 45%, Mr Coughlan 20% and Mr Humphrey 20%. Mr Beazley’s share is 15%.

[20]     On this basis the Tribunal’s formal orders were:

I.       Richard Coughlan is ordered to pay Vanessa Abernethy and Alan Abernethy the sum of $60,310.86 within 30 days of the date of this determination.  Richard Coughlan is entitled to recover a contribution of   up   to   $48,248.69   from   Trevor   Humphrey   and   Stockdale Investments  Auckland  Liminted  including  up  to  $9,046.63  from

Cedric  Beazley,  for  any  amount  Mr  Coughlan  pays  in  excess  of

$12,062.17.

II.     Trevor Humphrey is ordered to pay Vanessa Abernethy and Alan Abernethy the sum of $60,310.86 within 30 days of the date of this determination.  Trevor Humphrey is entitled to recover a contribution of   up   to   $48,248.69   from   Richard   Coughlan   and   Stockdale Investments Auckland Limited including up to $9,046.63 from Cedric Beazley, for any amount Mr Humphrey pays in excess of $12,062.17.

III.     Stockdale Investments Auckland Limited is ordered to pay Vanessa Abernethy and Alan Abernethy the sum of $60,310.86 within 30 days of the date of this determination.   Stockdale Investments Auckland Limited is entitled to recover a contribution of up to $33,170.97 from Richard Coughlan and Trevor Humphrey including up to $9,046.63 from Cedric Beazley, for any amount Stockdale pays in excess of

$27,139.89.

IV.     Cedric  Beazley  is  ordered  to  pay  Vanessa  Abernethy  and  Alan Abernethy the sum of $9,046.63 within 40 days of the date of this determination.

V.      To summarise the decision, and without limiting I to IV above, if the four respondents meet their obligations under this determination, this will result in the following payments being made by the respondents to the claimants, and I so order:

Richard Couglan, first respondent

$12,062.17

Trevor Humphrey, second respondent

$12,062.17

Stockdale     Investments     Auckland

Limited, fourth respondent

$27,139.89

Cedric Beazley, fifth respondent

$ 9,046.63

VI.     As regards the summary in order V immediately above, I order that if Stockdale Investments Auckland Limited cannot pay, and without limiting  I  to  IV  above,  the  payments  to  the  claimants  are  to  be

$25,632.12  by  Mr  Coughlan,  $25,632.12  by  Mr  Humphrey  and
$9,046.63 by Mr Beazley.

The appeal and cross-appeal

[21]     Messrs Coughlan and Humphrey appealed against the Tribunal’s decision initially to the District Court, but on the application of the Abernethys the appeal was subsequently transferred  by consent  to  this  Court:  see  minute  of  Allan  J  dated

25 February 2010: Abernethy v Coughlan.3

3 Abernethy v Coughlan HC Auckland CIV-2010-404-910, 25 February 2010.

[22]     The  grounds  of  appeal  in  the  notice  of  appeal  of  Messrs  Coughlan  and

Humphrey are that the Tribunal was wrong to:

a)        impose a duty of care on them when the Abernethys had received two pre-purchase reports disclosing significant defects in the property;

b)impose a duty on Mr Humphrey to supervise and control the work of the independent contractors who constructed the unit given his finding that Stockdale delegated responsibility for the quality of the work to the contractors and Mr Humphrey was not engaged as a site manager and did not undertake any responsibility for the quality of the work;

c)       find that the lack of sub-floor ventilation was as a result of a breach of Mr Coughlan’s duty of care given blocklayer incorporated sub-floor ventilation in the other two units of the development;

d)find that the lack of sub-floor ventilation was a material cause of damage;

e)       find that the lack of any reference to control joints in the plans and specifications prepared by Mr Coughlan was a breach of the duty of care he owed to the Abernethys or that this omission was a material cause of damage to the walls of the unit;

f)        find that Messrs Coughlan and Humphrey were responsible for the leaks  occurring  around  the  windows  or  that  their  conduct  in  this regard was a material cause of damage to the walls of the unit;

g)       reject  the  submission  for  Messrs  Coughlan  and  Humphrey  that causation was to be determined in accordance with the principles set out in Gray v Tulip Holdings Limited;4 and

h)find that the Abernethys’ contribution to the loss they suffered was only 10 per cent.

[23]     The  Abernethys  filed  a  notice  of  cross-appeal  on  the  grounds  that  the

Tribunal’s decision was wrong in fact and/or law in the following respects:

4 Gray v Tulip Holdings Limited Weathertight Homes Tribunal Claim No 499, 30 June 2006.

a)       in finding that Messrs Coughlan and Humphrey were not developers of the property;

b)not   taking   into   account   the   North   Shore   City  Council   when apportioning damages between the parties;

c)       in  finding  that  Messrs  Coughlan  and  Humphrey,  the  Council, Stockdale and Mr Beazley were responsible only for the cost of repairing the north and east walls;

d)in finding the Abernethys contributed to the loss they suffered and in reducing the quantum of damages by 10 per cent when they took adequate precautions before purchasing the property, relied on the expert advice they received and at all times acted reasonably in their own interests; and

e)        in  only  awarding  $7,500  general  damages  to  Mrs  Abernethy  and

$5,000 to Mr Abernethy when these awards for general damages are not in line with the prevailing law and did not adequately reflect the burden of coping with the distress they experienced.

[24]     In the written submissions for the parties and at the hearing of the appeal, counsel divided their arguments into the following parts: the question of the impact of the Abernethys’ knowledge on the appellants’ duty of care; issues arising from the claim against Mr Coughlan; issues arising from the claim against Mr Humphrey; contributory  negligence  by  the  Abernethys;  and  quantum  of  damages  issues, including apportionment.

Approach to appeal

[25]     There is a general right of appeal under s 93 of the Weathertight Homes

Resolution Services Act 2006. Section 93(1) provides:

A party to a claim that has been determined by the Tribunal may appeal on a question of law or fact that arises from the determination.

On an appeal the High Court has power to confirm, modify, or reverse the determination or any part of it and may exercise any of the powers that could have been exercised by the Tribunal in relation to the claim to which the appeal relates: s 95(1).

[26]     The appeal is to be determined in accordance with Part 20 of the High Court Rules: cf Hartley v Balemi.5     Rule 20.18 provides that the appeal is by way of rehearing.   This means  that the well-established approach to  general  appeals in Austin, Nichols & Co Inc v Stichting Lodestar,6  as confirmed in K v B,7  applies to appeals under s 93 of the Weathertight Homes Resolution Services Act 2006: Burns v Argon Construction Ltd,8  Boyd v McGregor9  and Chee v Star East Investment Ltd.10   The principles that may be derived from Austin, Nichols are set out at [4] and [5] and may be summarised as follows:

a)       The appellant bears an  onus of satisfying the appeal court  that it should  differ  from  the  decision  under  appeal.    It  is  only  if  the appellate court considers that the appealed decision is wrong that it is justified in interfering with it.

b)The appeal court may or may not find the reasoning of the Tribunal persuasive in its own terms.  The Tribunal may have had a particular advantage (such as technical expertise or the opportunity to assess the credibility of witnesses, where such assessment is important).

c)       The extent of the consideration an appeal court exercising a general power of appeal gives to the decision appealed from is a matter for its judgment.

5 Hartley v Balemi HC Auckland CIV-2006-404-2589, 29 March 2007 at [39]–[41].

6 Austin, Nichols & Co Inc v Stichting Lodestar [2008] 2 NZLR 141 (SC).

7 K v B [2010] NZSC 112 at [31]-[32].

8 Burns v Argon Construction Ltd HC Auckland CIV-2008-404-7316, 18 May 2009 at [14].

9 Boyd v McGregor HC Auckland CIV-2009-404-5332, 17 February 2010.

10 Chee v Star East Investment Ltd HC Auckland CIV-2009-404-5255, 1 April 2010.

d)On a general appeal, the appeal court has the responsibility of arriving at its own assessment of the merits of the case.

[27]     In confirming the approach to general appeals mandated by its decision in Austin, Nichols & Co, the Supreme Court in K v B at [32] has distinguished in this context a general appeal from an appeal against a decision made in the exercise of a discretion. For appeals against the exercise of a discretion, the criteria for a successful appeal are stricter and require: an error of law or principle; the taking account of irrelevant considerations; a failure to take account of a relevant consideration; or that the decision is plainly wrong. In an appeal of the present nature under the Weathertight Homes Resolution Services Act 2006 the aspects of the Tribunal’s decision that can be said to be “discretionary” are those relating to apportionment of damages under s 17 of the Law Reform Act 1936 and s 3 of the Contributory Negligence Act 1947 and the amount of an award of general damages:

cf Findlay and Sandelin v Auckland City Council.11

[28]     In an appeal under the Weathertight Homes Resolution Services Act 2006 it is also important to recognise that the purpose of the Act is to provide owners of leaky homes “with access to speedy, flexible and cost-effective procedures for assessment and resolution of [their] claims”: s 3.   Like its predecessor, the Weathertight Homes Resolution Services Act 2002, the 2006 Act “provides a comprehensive   regime   for   investigating,   evaluating,   and   resolving   claims”:

cf Auckland City Council v Weathertight Homes Resolution Service.12   The new Act

responded to the rise of large multi-unit claims and introduced a Tribunal to perform the adjudication functions for leaky buildings: Hartley v Balemi.13   As s 4 of the Act (the overview section) indicates, there is provision for mediation and compulsory adjudication of claims: cf Kay v Dickson Lonergan Ltd.14   Sections 13–18 prescribe eligibility criteria.   There are mechanisms for homeowners to submit claims, for claims to be evaluated, and for home owners to receive assessor’s reports: ss 31-44 and Auckland City Council v Weathertight Homes Resolution Service.15   Whereas the

11  Findlay v Sandelin v Auckland City Council HC Auckland CIV-2009-404-6497, 16 September

2010.

12  Auckland City Council v Weathertight Homes Resolution Service HC Auckland CIV-2004-404-

4407, 28 September 2004 at [5].

13 Hartley v Balemi HC Auckland CIV-2006-404-2589, 29 March 2007 at [25].

14 Kay v Dickson Lonergan Ltd HC Auckland CIV-2005-483-201, 31 May 2006.

15 Above n 12.

2002 Act contained provisions for the appointment of adjudicators, the 2006 Act provides for adjudication by the Weathertight Homes Tribunal: s 60.  The Tribunal has wide powers to determine the liability of parties and remedies: ss 73 and 29. Significantly, under s 73(1)(a), the Tribunal may “conduct the proceedings in any manner it thinks fit, including adopting processes that enable it to perform an investigative role”.

[29]     When  the  purpose  and  scheme  of  the  Weathertight  Homes  Resolution Services Act 2006 are taken into account, it is apparent that Parliament intended the Tribunal to have wide and flexible powers and that while there is a general right of appeal on questions of law or fact arising from the determinations of the Tribunal, a Court on appeal needs to recognise the specialist position of the Tribunal and the purpose of the Act to provide owners of leaky homes with access to speedy, flexible, and  cost-effective  procedures  for  assessment  and  resolution  of  their  claims:

cf Hartley v Balemi.16   This reinforces the approach mandated by the Supreme Court

in Austin, Nichols & Co that an appellate court will need to be persuaded on the basis of compelling grounds that the Tribunal’s decision is wrong.

[30]     I propose to consider the issues raised on this appeal on an issue by issue basis with reference to the submissions made by the parties in the context of each issue.

Duty of care

[31]     For Messrs Coughlan and Humphrey, it was submitted that they owed no duty  of  care  to  the  Abernethys  because  the  Abernethys  were  aware  from Mr Beazley’s pre-purchase reports, which identified the problem leading to their claim, that the house was   a “leaky home” before they purchased it.   In this case there was no “latent defect” and the Abernethys were “not innocent purchasers”:

cf Bowen v Paramount Builders (Hamilton) Ltd17  and Puller v The Secretary of

Education.18    It was submitted that the Tribunal failed to address this submission, which had been made to it as well.

16 Above n 13 at [49]–[53].

17 Bowen v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394 (CA).

18 Puller v The Secretary of Education [2007] NZCA 389 at [14].

[32]     For the Abernethys, it was submitted that their knowledge did not impact on the well-established duties of care owed to subsequent owners by architects,

builders, project managers and developers.  Intermediate inspection by a third party will  not  in  most  cases  exculpate the original  tortfeasor:  Steiller  v  Porirua  City Council.19   Mr Beazley’s pre-purchase report in this case essentially categorised the problems as deferred maintenance.  The Abernethys, who were not building experts, were entitled to rely on Mr Beazley’s expertise.  He estimated that the repairs would cost about $10,000.  The Abernethys had no actual knowledge of the extent of the

problems.  Mr Beazley’s report did not identify all of the causes of water entry and damage.   Any negligence on Mr Beazley’s part could not be attributed to them: Morton v Douglas Homes Ltd.20     The Abernethys arranged for the repairs recommended by Mr Beazley, but they were not sufficient.

[33] There is little doubt that the Tribunal did find that Messrs Coughlan and Humphrey owed a duty of care to the Abernethys. In the case of Mr Humphrey there is an express finding to that effect: at [109]. In the case of Mr Coughlan there is an implicit finding by virtue of the Tribunal’s decision as to the negligence and liability of Mr Coughlan. The question on appeal is whether the Tribunal was wrong in making these findings in the circumstances of this case.

[34]     It was not disputed that a house designer and a project administrator owe duties  to  use  reasonable  care  to  prevent  damage  to  persons  whom  they should reasonably expect to be affected by their work, including subsequent purchasers, and that they will be liable to such third persons for the negligent creation of a latent or

hidden  defect  in  the  property:  Bowen  v  Paramount  Buildings  (Hamilton) Ltd,21

Mount Albert Borough Council v Johnson,22  Invercargill City Council v Hamlin,23

Pullar v The Secretary of Education,24 and Sunset Terraces.25

[35]     An opportunity to inspect or examine a property before purchase to discover a hidden defect will not abrogate liability for breach of the duty of care unless there is  a  sufficiently  strong  expectation  of  such  inspection  or  examination.     In

19 Stieller v Porirua City Council [1986] 1 NZLR 84 (CA) at 95.

20 Morton v Douglas Homes Ltd [1984] 2 NZLR 548 (HC).

21 Above n 17.

22 Mount Albert Borough Council v Johnson [1979] 1 NZLR 234 (CA).

23 Invercargill City Council v Hamlin [1996] 1 NZLR 513 (PC) at 516-522.

24 Pullar v The Secretary of Education [2007] NZCA 389 at [14].

25  Sunset Terraces [2010] NZCA 64 at [25]-[26], [45] and [82]. Leave to appeal has been granted:

Sunset Terraces [2010] NZSC 79.

Stieller v Porirua City Council26 in the judgment of the Court of Appeal delivered by

McMullin J it was said:

Mr  Hancock [counsel for the Council]  submitted that the decided  cases showed that  an  opportunity for  intermediate  examination  may break the relationship of proximity upon which the liability of the local authority rests. In Dutton v Bognor Regis Urban District Council [1972] 1 QB 373, Lord Denning MR, in dealing with an argument that the duty ought to be limited to those immediately concerned and not to purchaser after purchaser down the line, said:

"There is a good deal in this, but I think the reason is because a subsequent purchaser often has the house surveyed. This intermediate inspection, or opportunity of inspection, may break the proximity. It would certainly do so when it ought to disclose the damage. But the foundations of a house are in a class by themselves. Once covered up, they will not be seen again until the damage appears. The inspector must know this or, at any rate, he ought to know it" (ibid, 396).

This lack of opportunity on the part of an occupier to inspect the premises may account for the readiness of the Courts to impose liability or set a high standard of care in respect of such items as foundations and drainage work which will, with the progress of the construction, be covered up and hidden from view. Mr Hancock submitted that in the present case the defective weather-boards remained available for inspection and that, as the Stiellers had the opportunity to examine these, there was good reason for restricting recovery to only such items in the house as would not have been reasonably apparent on a visual inspection of it; therefore no claim should lie in respect of  the  weather-boards. The  latter, he  said,  were  not  the  "building time- bomb", to use the graphic language which Lawton LJ applied in Dennis v Charnwood Borough Council [1982] 3 All ER 486, 495.

There is no reason why the Stiellers should have been expected to subject the weather-boards to a critical examination before buying the house. Mr Stieller said in evidence that on the second or third occasions he and Mrs Stieller saw the house before taking possession, it looked attractive and there was nothing about the whole structure which alerted him to the real problems which were later experienced. The weather-board cladding was on the upper storey and except for one side it was not easy to examine it. However, as a matter of law, a person who creates a dangerous situation cannot escape liability on the ground of expectation of intermediate examination unless the expectation is strong enough to justify him in regarding the contemplated inspection as an adequate safeguard to persons who might otherwise suffer harm: Bowen v Paramount Builders Ltd [1977] 1 NZLR

394; Jull v Wilson & Horton [1968] NZLR 88.

(emphasis added)

[36]     As  the  decision  in  Stieller  shows,  the  question  whether  there  was  a sufficiently  strong  expectation  of  intermediate  inspection  or  examination  is  a question of fact in the circumstances of the particular case.  In the present case there

26 Above n 19.

was   no   suggestion   of   any   sufficiently   strong   expectation   on   the   part   of Messrs Coughlan and Humphrey in 1994 that subsequent purchasers of the property, such as the Abernethys in 2003, would obtain a pre-purchase report or that any pre- purchase report that was obtained would or should have identified the problems that were subsequently discovered in the property.  The absence of any such expectation in 1994 is reinforced by the decision of the Court of Appeal in Hamlin27 which was delivered in  1994.   Richardson J  observed that  it was not  the practice in New Zealand in the 1970s and 1980s for purchasers to commission pre-purchase inspections.28     While Richardson J discussed the legislative changes in the early

1990s in detail,29  the Court at no point referred to any new expectation of pre-

purchase inspections in the early 1990s.   On the contrary, Casey J noted that the obtaining of surveyors’ or engineers’ reports by house purchasers “is virtually unknown in this country”.30  The Court of Appeal’s judgment was upheld by the

Privy Council31 and was approved with detailed consideration in Sunset Terraces.32

Accordingly, I am not prepared to find such an expectation existed in 1994.

[37]     The decision in Pullar v The Secretary of Education, relied on by Messrs Coughlan and Humphrey, may be distinguished as the Court there was dealing with the question of a defect for the purposes of limitation.   It was held that a plaintiff may not extend limitation periods through wilful blindness.33   Not all elements of the damage need exist for the cause of action to accrue, but that did not mean that whenever  a  plaintiff  purchases  a  property  with  some  known  defects  and  other,

hidden defects, that no duty of care exists.

[38]     The  question  whether  the  pre-purchase  reports  which  the  Abernethys obtained from Mr Beazley in 2003 in fact identified the “leaky home” problems so that the defects were not hidden when the Abernethys purchased the property and they  were   therefore   not   “innocent   purchasers”   is   a   separate   question.      If Mr Beazley’s reports did in fact identify the problems so that there were no hidden defects  when  the  Abernethys  purchased  in  2003,  the  question  is  then  one  of

27 Invercargill City Council v Hamlin [1994] 3 NZLR 513 (CA).

28 Ibid at 525-526.

29 Ibid at 526.
30 Ibid at 530.

31 Invercargill City Council v Hamlin [1996] 1 NZLR 513 (PC).

32 Sunset Terraces [2010] NZCA 64 at [9]-[77].

33 Pullar v The Secretary of Education [2007] NZCA 389 at [14].

voluntary assumption of risk (volenti non fit injuria) rather than no duty of care or no breach of duty.  As pointed out in The Law of Torts in New Zealand: 34

We need to distinguish between cases involving the plaintiff’s assumption of the risk and those which on their true analysis involve no breach of the duty. The question to ask is whether the conduct would be actionable apart from the plaintiff’s alleged knowledge and acceptance of the risk.  If it would not, the plaintiff’s state of mind is irrelevant and there is simply no breach of duty.  If the conduct is otherwise actionable and the plaintiff knows or ought to know of the risk, the volenti doctrine or, it may be, the principles of contributory negligence come into play.

(emphasis added)

[39]     The distinctions between the separate questions of duty of care, voluntary assumption of risk and contributory negligence have been recognised by the Court of Appeal  in  the  context  of  leaky  homes.    In  Sunset  Terraces35   Baragwanath  J, delivering the judgment of the Court, said:

34 Stephen Todd (ed) The Law of Torts in New Zealand (5th ed, Thomson Reuters, Wellington, 2009)

at 1007.

35 Sunset Terraces [2010] NZCA 64.

[82]      Purchasers generally must be able to claim against those responsible for the condition of the leaky building unless they have such knowledge, or means  of  knowledge,  as  entails  acceptance  of  its  condition.     The Council’s submission that any liability could only be to the original owner is untenable.  It is commonly the case that the original owner knows or should know that there is deficiency in the workmanship.  But that says nothing about the position of later buyers who are to be judged on what they know or should know. They may be caught by the ten year limitation under s 91.  But there is no good reason to visit them with matters of which they are unaware.

(emphasis added).

Then in Byron Avenue Baragwanath J said:36

[60]      But  there  is  need  to  examine  the  extent  of  the  right  of  general reliance. I agree with the Judge that, in the period prior to issue of a code compliance certificate, failure to seek a LIM which would have disclosed problems  or  alternatively to  make  other enquiry of the Council goes  to contributory negligence rather than constituting a bar to claim.

...

[63]      If contributory negligence is sufficiently great the reduction will be of  100  per  cent,  which  may  take  the  case  into  the  zone  embraced  by voluntary assumption of risk.

[40]     Accordingly, where a prospective purchaser receives a pre-purchase report, but fails to undertake the further investigations recommended in that report, that is likely to constitute contributory negligence.   That contributory negligence may be sufficiently great to amount to voluntary assumption of risk, but it will not negate the existence of a duty of care.

[41]     In the present case the conduct of Messrs Coughlan and Humphrey would be actionable apart from the Abernethys’ alleged knowledge and acceptance of the risk on receipt of the pre-purchase reports from Mr Beazley.  The question therefore is whether the Abernethys assumed the risk.  Although the appeal was not argued for Messrs Coughlan and Humphreys on this basis, I shall proceed as though it had been because the argument was presented for both sides in the context of whether the Abernethys did in fact voluntarily assume the risk that the property was a “leaky home”.   Counsel for Messrs Coughlan and Humphrey submitted that their contributory negligence should have been assessed at near 100 per cent to reflect their voluntary assumption of risk.

36 Byron Avenue [2010] NZCA 65.

Voluntary assumption of risk

[42]     It is well-established that a person will not have voluntarily assumed a risk unless it is shown that he or she had full knowledge of the nature and extent of the risk and, with that full knowledge, in fact incurred it: Heard v New Zealand Forest Products Ltd.37     Unlike contributory negligence, which is determined objectively, voluntary assumption of risk is determined subjectively: The Law of Torts in New Zealand.38    The onus of proof is on the party alleging voluntary assumption of risk by the other party to establish the allegation: James v Wellington City.39

[43]     In the present case the question therefore is whether Messrs Coughlan and Humphrey established that the Abernethys in fact had full knowledge of the nature and extent of their “leaky home” problems, which ultimately led to their claim for repairs  totalling  $201,568.06,  from  the  pre-purchase  reports  they  obtained  from Mr Beazley in 2003.

[44]   An examination of Mr Beazley’s two reports does not suggest that the Abernethys would have been made fully aware of the nature and extent of their “leaky home” problems before they purchased the property.  The first report dated

29 July 2003 included the following statements:

37 Heard v New Zealand Forest Products Ltd [1960] NZLR 329 (CA).

38 Above n 34 at [21.4.02].

39 James v Wellington City [1972] NZLR 978 (CA).

Generally  in  reasonable  condition  only  as  this  unit  has  been  poorly maintained during its life but with a regular maintenance schedule put in place after remedial action should require little in the way of significant remedial work for some years to come.

...

Upon inspection and testing for possible moisture saturation of this dwelling it is considered there are current ingress problems to what degree is still to be discovered.   The ground floor level readings fluctuated slightly this is however a common occurrence as minimal moisture is still being drawn through the concrete slab.  The current condition of this property is what can only be considered as reasonable with the majority of all defects noticed to the exterior walls it is suggested that further intrusive inspections are recommended to ascertain the degree of moisture penetration to the internal framing if any.

[45]     Mr Beazley carried out a subsequent “semi-intrusive” inspection of the rear entry, downstairs WC, laundry, both top floor bathrooms, and the ensuite.  His report dated 4 August 2003 read as follows:

Rear entry

Non-intrusive moisture readings were taken at floor level just above the skirting line and recorded between 17-32% this is considered to be very high suggesting further intrusive inspection is required.

The first intrusive  readings  were taken  to the left side of the door  and recorded  at  32%  this  is very  high  however  the  hammer  was  needed  to penetrate the framing timber suggesting there are no  significant  wet  rot problems appearing at present.   The removal of the wall lining is recommended in the near future as this will assist in the drying process and then a full visual inspection of the framing timber will be available.

The second intrusive readings were taken to the right side of the door and recorded at 20% this reading would be acceptable to most council inspectors however wall lining manufacturers require the moisture reading to be at 18% or lower again the hammer was needed to penetrate the framing timber suggesting there are no significant wet rot problems appearing at present. The removal of the wall lining is recommended in the near future as this will assist in the drying process and then a full visual inspection of the framing timber will be available.

The floor directly in front of the rear door was tested with this large area of flooring showing all the signs of deterioration that extends some 1.2mtrs from the door and appears to be approximately 600mm wide.   The only course of action in this case is to have this flooring replaced with inspection of the joists below carried out.  All readings within this area were well in excess of 40%.

WC

The WC intrusive readings were taken to the right rear corner and recorded in excess of 40% again the hammer was needed to penetrate the framing timber suggesting there are no significant wet rot problems appearing at

present. The removal of the wall lining is recommended in the near future as this will assist in the drying process and then a full visual inspection of the framing timber will be available.

Readings were taken to the left and right rear corners and recorded 23% again the hammer was needed to penetrate the framing timber suggesting there are no significant wet rot problems appearing at present.  The removal of the wall lining is recommended in the near future as this will assist in the drying process and then a full visual inspection of the faming timber will be available.

Laundry

Readings  were  taken  to  the  exterior  wall  and  recorded  27%  again  the hammer was needed to penetrate the framing timber suggesting there are no significant wet rot problems appearing at present.  The removal of the wall lining is recommended in the near future as this will assist in the drying process and then a full visual inspection of the faming timber will be available.  During the inspection it was noticed that the floor was wet with a number of personal items covering this damp it is therefore considered that the smell emanating within this room is a direct result of this.

Top Floor Bathroom

Readings were taken to the right rear corner and along the exterior wall and recorded 18% indicating while there is some moisture present it is at an acceptable level according to wall lining manufacturers requirements again the hammer was needed to penetrate the framing timber suggesting there are no significant wet rot problems appearing at present.

The pressure relief pipe from the hot water cylinder appears to be leaking as a large damp spot is being created at the foot of the rear door this will need to be attended to by a qualified plumber in the near future.

Ensuite

The ensuite was also tested with all recorded readings registering 16-17%

this is considered low with no immediate problems evident.

Summary

There appears to be a number of issues that need to be addressed in terms removing wall linings to give the framing a chance to dry.   In the first instance however the external cracks evident need to be repaired, as this will limit the present ingress.

[46]     While Mr Beazley’s second report did identify a number of the water ingress problems which ultimately made the property a “leaky home”, it did not identify them all.  Nor did it alert the Abernethys to the full nature and extent of the risk they were running in purchasing the property.   Mr Beazley did not identify the lack of subfloor vents.  Though he recommended an inspection of the subfloor, it cannot be said that the Abernethys possessed full knowledge of this risk.  Mr Beazley reported

that the windows had been installed correctly, but the Tribunal found that some had not been.  Mr Beazley did not identify the absence of vertical control joints.

[47]     Most significantly, the Abernethys were left with the clear impression that the problems identified by Mr Beazley would be able to be overcome with repairs estimated to cost around $10,000.   This figure appears in a contemporaneous document, being a facsimile from the Abernethys’ then solicitors, Bell Gully, to the respondents’ then solicitors, Haigh Lyon, dated 5 August 2003.  While I accept that Mr Beazley did not give this figure as a reasoned assessment or conclusion, I am satisfied  that  the  Abernethys  genuinely  and  reasonably  believed  that,  based  on Mr Beazley’s reports, the cost of repairs would be around that figure.

[48]     The view that the Abernethys were not aware of the full nature and extent of the risk is reinforced by –

a)       The Tribunal’s unchallenged findings that Mr Beazley was negligent only to the extent of not identifying the lack of ventilation holes in the base of the building and that he was not negligent in concluding that the problems were largely maintenance issues;

b)The Tribunal’s finding that the Abernethys’ “calculated risk” in purchasing the property constituted contributory negligence; and

c)       Mrs Abernethy’s statement under cross-examination that she “took a chance”  that  repair  costs  might  be  “slightly  different”  from  the

$10,000 figure, and her consistent evidence to that effect.   The Abernethys had no idea from Mr Beazley’s reports that the cost of repairs  to  their  leaky  home  would  ultimately  amount  to  over

$200,000.

[49]     For these reasons I am not satisfied that Messrs Coughlan and Humphrey have  discharged  the  onus  of  proof  of establishing that  the  Abernethys  had  full knowledge of the nature and extent of their “leaky home” problems before they purchased the property in September 2003.

[50]     Accordingly, I find that the Abernethys’ knowledge at the time of purchase does not alter any duty of care that Messrs Coughlan and Humphrey owed to them as prospective purchasers, and that this duty of care is not negated by the defence of voluntary assumption of risk.   I will return to the issue of contributory negligence later, after considering the other issues as to liability.

Liability of Mr Coughlan

[51]     It was not in dispute that Mr Coughlan was the designer of the house on the property at 5/6 City View Terrace and that in that capacity, subject to the previous issue, he owed a duty of care to the Abernethys as subsequent purchasers of the property to carry out his design work with reasonable care and skill.  Instead it was submitted that the Tribunal was wrong “in fact and law” in finding that Mr Coughlan was negligent in omitting any reference in the plans for the house to the subfloor vents and the manufacturers’ instructions. The following specific points were made:

a)       The Tribunal was wrong to rely on non expert opinion evidence in finding that  the  omission  of  subfloor  vents  from  the  plans  was  a breach of the designer’s duty of care;

b)There was no evidence of any general practice to include reference to manufacturers’ instructions concerning windows and control joints in Building Consent plans;

c)       The manufacturer’s instructions did not require jamb flashings to be fitted to windows and the method adopted by the builders complied with accepted practice at the time of construction;

d)The cracking and water ingress around the windows was due to a lack of maintenance and not the result of a construction defect;

e)       There is no evidence that a lack of vertical control joints caused any damage to the unit;

f)        The designer did not cause poor workmanship or decisions made on site: Gray v Tulip Holdings Limited;

g)        The subfloor damage would have occurred in any event; and

h)The Abernethys’ failure to mitigate known damage at the rear of the house limits any loss associated with this area to $10,597.50 including GST.

[52]     I have considered each of these points and the detailed submissions made by Mr Maclean for Messrs Coughlan and Humphrey in support of them, but, for the following reasons, which are largely based on the submissions in response for the Abernethys,  I  am  not  persuaded  that  the  Tribunal  was  wrong  to  decide  that Mr Coughlan, as designer of the house, was in breach of his duty of care to the Abernethys.  In reaching this conclusion I have taken into account the nature of the hearing before the Tribunal under the Weathertight Homes Resolution Service Act

2006 and the advantage which the Tribunal had in evaluating the evidence for the parties at the hearing.

[53]     First,  there  was  sufficient  evidence  before  the  Tribunal  to  support  the Tribunal’s conclusion that Mr Coughlan was negligent in leaving the vents out of the drawings when they should have been included.  The Tribunal was entitled to accept the evidence of Mr Higham, who had worked as Building Control Manager for the Franklin District Council in 1994, that the vents should have been included in the plans.  The fact that Mr Higham may have had no architectural or design experience and was called as a witness for the Council did not mean that in the context of a hearing before the Weathertight Homes Tribunal the Tribunal was not entitled to accept his evidence as to general practice in 1994.

[54]     The evidence of Mr Coughlan that he was not negligent in omitting the vents because he was entitled to rely on competent tradesmen to include standard and well- known construction details in plans prepared for the purpose of obtaining a building consent was, contrary to the submission of Mr Maclean, challenged under cross- examination.    Reference  to  the  transcript  of  the  cross-examination  shows  that Mr Coughlan was cross-examined by counsel for the Abernethys about his reliance

on the Council and the builders for the level of detail in his plans, and the generally inadequate nature of his plans was put to him in the following exchange:

MR JOSEPHSON:  Thank you.  Mr Cartwright for the claimants will give evidence, in his views the plans for this particular unit are no more than concept plans, let alone intended for instruction purposes and are deficient and fail to address construction detailing and the exterior cladding and furthermore the specification was out of date and not specific to this project. Can I take it you disagree with that?

MR COUGHLAN:    Oh yes.

Although the Tribunal did not refer to the unchallenged evidence of Mr Cartwright, an ex-council building inspector called as an expert by the Abernethys, in support of his conclusion as to the inadequacies in Mr Coughlans’ plans, the evidence does provide further support for that conclusion.

[55]     The authorities relied on by Mr Maclean for Mr Coughlan to challenge the

Tribunal’s finding of negligence do not provide the necessary support:

a)       It is no defence that the plans were accepted by the Council: Blair & Co Ltd v Queenstown Lakes District Council.40

b)Mr Coughlan was not entitled to rely on the Council’s inspections as a Council owes no duty to an architect or designer: Bell v Hughes41 and The Law of Torts in New Zealand.42

c)       The decisions in Sunset Terraces may be distinguished on the facts.

In the High Court in Sunset Terraces43 there were findings that in the circumstances of that case Mr Coughlan had been able to rely on the competent tradesmen involved and the developer, Mr Barton, to supervise the construction and to ensure compliance with relevant manufacturers’  specifications.    The  reference  to  this  issue  by  the Court of Appeal in Sunset Terraces44  was based on the High Court findings.  No such similar findings were made by the Tribunal in the

40 Blair & Co Ltd v Queenstown Lakes District council [2010] NZSC 44 at [3].

41 Bell v Hughes HC Hamilton A110/80, 10 October 1984.

42 Stephen Todd (ed) The Law of Torts in New Zealand  (5th ed, Thomson Reuters, Wellington, 2009)

at [6.4.04].

43 Body Corporate 188529 v North Shore City Council [2008] 3 NZLR 479 at [523]-[531].

44 Sunset Terraces [2010] NZCA 64 at [120]-[121].

present case.  On the contrary, as will be seen from [81]–[83] of his decision, he made quite different findings.  Here, where labour-only tradesmen   were   employed   by   Stockdale,   as   developer,   and Mr Humphrey’s role, as project manager, was limited, it was open to the Tribunal to reach a different conclusion on the facts.

d)Even  where  a  defendant’s  conduct  meets  the  standard  of  general practice, he or she may be found negligent if the general practice falls below  the  required  standard:  McLaren  Maycroft  & Co  v  Fletcher Development & Co Ltd45 and Dicks v Hobson Swan Construction Ltd (In Liquidation).46

e)       The Tribunal decision in Gray v Tulip Holdings Ltd47, which is not binding on the Court, may be distinguished on the facts because in that case it was found that the plans and specifications did specify that the cladding was to be fixed “to the manufacturer’s latest recommendations”.  In the present case, as the Tribunal pointed out at [82], there was no reference in Mr Coughlan’s plans to the manufacturer’s instructions.

[56]     Second, there  was sufficient evidence before the Tribunal to support  the Tribunal’s conclusion that Mr Coughlan was negligent in omitting any reference to the manufacturer’s instructions on the plans.  The Tribunal summarised its views as follows:

45 McLaren Maycroft & Co v Fletcher Development & Co Ltd [1973] 2 NZLR 101 (CA).

46 Dicks v Hobson Swan Construction Ltd (In Liquidation) (2006) 7 NZCPR 881 at [76].

47 Gray v Tulip Holdings Ltd Claim 499, 30 June 2006 at [130].

[81]      Concerning the alleged failure to include James Hardie’s instructions with the plans, Mr Coughlan said that the instructions were known by the tradesmen at the time.   The specifications stated: “EXTERIOR WALLS: Selected plaster finish to Hardibacker.  Where shown on plan, exterior walls from top of base to eaves to be sheathed with selected hardibacker as shown on plans, fixed true in line, level and plumb at all angles.”

[82]     It  is  acceptable  for  the  manufacturer’s  specifications  not  to  be attached  to  the  plans  as  long  as  the  plans  make  reference  to  the manufacturer’s instructions, but there was no such reference here.  There is a complication  because  Hardibacker  was  replaced  by  Harditex.    Even  so, Mr Higham said it was acceptable for there to be such a change without Council approval.

[83]     I  gained  the  distinct  impression  that  Mr  Coughlan  was  relying entirely on the builders knowing what the James Hardie requirements were or having access to them for either Hardibacker or Harditext. ...

[57]     As counsel for the Abernethys pointed out, the Tribunal’s conclusion was supported by:

a)       The unchallenged evidence of Mr Cartwright that it was critical that the manufacturer’s technical literature was specified on the plans and included in the building consent application.

b)The  Tribunal’s  questioning  of  Mr  Coughlan  about  the  lack  of reference to the manufacturer’s literature and the fact that the cladding used (Harditex) was not the same as the cladding specified on the plans (Hardibacker).

c)       The distinguishing features in Sunset Terraces and Gray to which reference has already been made.

[58]     Third,  there  was  sufficient  evidence  before  the  Tribunal  to  support  the

Tribunal’s conclusion that the way in which the windows were originally installed in

1994 was defective and that, consequently, the claim in respect of damage to the east and north walls was established.  The Tribunal summarised its views as follows:

North Wall

...

[143]    The surface water lying against the rear of the house has clearly been a contributing cause of the damage to the rear north wall.   This is an extraordinary cause, not of itself the result of negligence on the first, second

and fourth respondents’ parts.  However it is external water penetrating the building.  I have concluded that for that reason, and because of the lack of vents, the probable lack of a vertical control joint, and the number of windows, the whole cost for repairing the north wall should be compensable.

East Wall

[144]    The eventual failure of the east wall is in part due to the failure to install the windows near the entry way correctly.   That is proven to have caused damage.  The cracks in the east wall may be the result of a lack of control joints, and a lack of maintenance.  All these factors may have led to timber shifting.  (This house has yet to be repaired so some of the causes are unknown.  Also it is not known how much long term damage was caused by the previous owners’ neglect in the last year before they sold the property when a repaint was overdue).

[145]    So while the need to replace the east wall is not wholly the result of the first, second and fourth respondents’ proven negligence, given the importance of the windows on this wall at the entry way, I find their negligence contributed to the extent that the whole of the cost of replacing the east wall should be included in the compensable figure.

(emphasis added).

[59]     As counsel for the Abernethys pointed out, the Tribunal’s conclusions as to the defective installation of the windows as a contributing factor to the problems in respect of the north and east walls of the house were supported by:

a)       The independent expert evidence of Mr P J O’Hagan, a registered building surveyor, called by the Abernethys.   Mr O’Hagan gave evidence that the lack of jamb flashings and/or adequate sealing to the windows  was  where  the  major  problem  was  coming  from.    He referred to E2/AS1 (September 93 to the August 94 edition) which required windows and doors to have head flashings and scribers or proprietary   seals   between   facings   and   the   building   cladding. Mr O’Hagan went on to say that in this case all the windows had was a “lick of sealant which was never going to work” and that, when he pulled out some of the cladding alongside the window jambs, there did not appear to be any sealant or foam strip.

b)The  independent  expert  evidence  of  Mr  Light,  the  Weathertight Homes Resolution Service Assessor.  Mr Light gave evidence that the July 1992 acceptable solution required joints between cladding and the exterior joinery to be waterproofed by the use of flashings and

sealing systems and that this was a general requirement at the time. Mr Light went on to say that:

The issue for me is that it is clear there are gaps and they could be filled and they should have been sealed if the windows are opening up as they seem.

In relation to the windows, Mr Light gave evidence that:

When I did my second report I was very concerned about the amount of ingress I found in windows and I changed my view from – well, actually from no repairs required on the handrail, on any of the cladding, to a reclad, on the basis of the high moisture I was finding at window junctions and the such.

c)       The independent expert evidence of Mr A J Roxburgh, a building consultant engaged by the Council.  Mr Roxburgh confirmed that the windows would need to comply with E2/AS1, and would therefore need to have either a proprietary seal or a scriber.

d)The independent expert evidence of Messrs O’Hagan, Light and Roxburgh was sufficient to answer the evidence to the contrary of Mr Higham.  On this issue it was open to the Tribunal to prefer the evidence of the former to the latter.

e)       The fact that all the experts agreed that the remedial work to the windows was consistent with accepted practice at the time is not relevant because the Abernethys have not made any claims in relation to failed repairs to the windows.

[60]    Fourth, there was sufficient evidence before the Tribunal to support the Tribunal’s conclusion that the cracking and water ingress around the windows was the result of a construction defect rather than due to a lack of maintenance.   As counsel for the Abernethys pointed out:

a)       Mr Beazley identified cracks around the windows in his reports and advised the Abernethys that they should undertake maintenance work to repair cracking around the windows.  Accordingly, cracking around the  windows  existed  in  2003.     The  Abernethys  undertook  the

maintenance work, as recommended by experts.  The evidence is that the maintenance work was satisfactorily carried out.   However, the problems still existed and became worse.

b)There was evidence that cracking was caused by the lack of vertical control joints and inadequate installation of windows.  Mr Light listed nine possible causes of cracking to the texture coating.  It is therefore unreasonable to assert that the cracking was a result of failure to maintain and that the Abernethys were responsible for cracking and water ingress around the windows.

c)       The Abernethys undertook reasonable steps to  maintain the house and, subject to later consideration of their cross-appeal, at least some steps to mitigate their loss.  They relied on the advice they received and did what could reasonably have been expected of them.

d)The submission for Messrs Coughlan and Humphrey that Mr Light’s recommendation that the unit needed to be reclad was based on problems that were inherent in the cladding system itself was misleading.  Mr Light was asked by Mr Maclean whether the system was inherently flawed, to which Mr Light responded: “I can’t say that

...” and went on to say that it was not in every case that these cladding systems failed.

[61]     Fifth,  there  was  sufficient  evidence  before  the  Tribunal  to  support  the Tribunal’s conclusion that a lack of vertical control joints caused damage to the house. The Tribunal summarised the relevant evidence and its views as follows:

Lack of control joints to exterior cladding

[41]      Mr O’Hagan stated in his witness statement that there was a lack of horizontal control joints to the exterior cladding at inter story level at the floor joist centres, and that vertical control joints should have been created on the east and south walls at 5.4 metres.

[42]     Mr  Light’s  view  was  that  it  is  impossible  to  tell  if  there  are horizontal control joints because at that time, the coating was applied over the control joints.  He said it was possible that vertical control joints could have been obscured later and that sometimes cracks indicate that control

joints are working.   Mr Light placed less emphasis on the alleged lack of vertical control joints that Mr O’Hagan did, as a cause of leaks and damage.

[43]     The experts’ evidence shows that there appears to be a horizontal control joint to the exterior cladding at the rear of the property, the north wall, but there is uncertainty as to whether proper vertical control joints, called relief joints, were installed on that face.

[44]      Mr O’Hagan was of the view that the vertical control joints had not been installed on the north wall because there was no indication of them when he felt underneath.   The lack of vertical control joints has probably contributed to cracking on this wall.

[45]      On the east wall, it is possible that a lack of vertical control joints has contributed to leaks and damage.

[46]      Mr O’Hagan’s view that there is a lack of vertical control joints to the front south wall causing damage contrasts with Mr Light’s view.   He emphasises the failure of the balustrades as the cause of damage on that face.

...

Summary of defects

[53]     Having regard to the experts’ evidence, the major causes of water ingress  and  damage  are  lack  of  sub-floor  ventilation;  lack  of  a  vertical control joint to exterior cladding at the back of the building, direct contact of the cladding with the deck stringer combined with inadequate drainage at the back of the building; in adequate installation of the window at the front of the east wall at that entrance; and the flat topped timber capping to the deck barrier walls or balustrades especially at the south front of the building.

[62]     Contrary to the submissions for Messrs Coughlan and Humphrey, it is clear from the Tribunal’s decision that it considered the relevant expert evidence and preferred the evidence of Mr O’Hagan to the evidence of Mr Light on this issue. There was, and could be, no suggestion that the Tribunal was wrong to do so in the context of this case.  The submission for Messrs Coughlan and Humphrey that there was no evidence to support the Tribunal’s conclusion on this issue is incorrect.

[63]     Sixth,  the  Tribunal  did  not  err  in  not  accepting  the  submission  for Mr Coughlan  that  he  was  not  liable  because  the  defects  were  caused  by  poor workmanship and decisions made on site rather than by his plans and specifications. While there is no express reference in the Tribunal’s decision to this submission for Mr Coughlan, it is implicit in the Tribunal’s conclusions as to the inadequacies in Mr Coughlan’s plan and their effect that the submission was rejected.

[64]     It is well-established that an architect or designer like Mr Coughlan owes a duty of care to subsequent purchasers such as the Abernethys to ensure that plans are drawn with due skill and care to avoid foreseeable losses to them arising out of his or her work:  Bowen v Paramount Builders Ltd48 and Sunset Terraces.49

[65]     An architect or designer may not avoid liability for foreseeable losses arising from his or her lack of due skill and care by shifting responsibility to a labour-only builder for failing to build something that is not detailed in the plans or according to a manufacturer’s technical information when the information is not referred to in the plans or attached to them.  In the absence of adequate supervision, as in the present case, the plans and specifications should have been sufficiently detailed so that the contractors did not have to guess at details of construction.

[66]     As already mentioned, the Tribunal decision in Gray v Tulip Holdings Ltd is not binding and may be distinguished.  In the present case where the Tribunal found that Mr Coughlan’s plans omitted the vents and any reference to the manufacturer’s instructions there was therefore no basis on which Mr Coughlan was able to avoid liability by relying on the builders.

[67]     Seventh, there was sufficient evidence before the Tribunal to support the Tribunal’s conclusion that the lack of sub-floor ventilation was partly responsible for the repairs necessary at the rear of the house and that the damage would not have occurred in any event.  The Tribunal summarised the relevant evidence and its views as follows:

Lack of sub-floor ventilation

[33]     There was disagreement amongst the experts as to the extent of damage  caused  by the  absence of  vents  in the foundation  blocks.   The WHRS  assessor,  Mr  Light,  took  the  view  that  the  lack  of  sub-floor ventilation has been an ongoing significant cause of damage to the sub-floor, floor and framing of the dwelling.  Mr Roxburgh, the expert engaged by the Council, like Mr Light, considered that it would have been prudent to place plastic sheeting over the soil in the rear sub-floor as a vapour barrier.

[34]     On the other hand, Mr McLintock, engaged by the first, second and fourth  respondents,  was  of  the  view  that  the  volume  of  exterior  water striking  the  dwelling  at  the  base  of  the  rear  was  such  that  sub-floor ventilation would not have prevented damage.   Mr McLintock’s evidence

48 Bowen v Paramount Builders Ltd [1977] 1 NZLR 394 (CA) at 406-408.

49 Sunset Terraces [2010] NZCA 64 at [121].

related to the large volume of surface water in the vicinity of the north wall under the ground level deck at the back of the house.   The other experts commented upon this.  All the experts and Mr Beazley have identified that as a problem.

[35]      There was disagreement as to how much of this water under the deck flowed from the chamber that was installed at the back of the section to re- direct ground water being piped from a cesspit in the section at the rear,

3 Pupuke   Road,  across  5/6   City  View  Terrace’s   section  and  away. Mr McLintock stated that he saw the sink-hole or chamber overflowing and

that was caused by lack of maintenance of the chamber.

[36]      Mr Roxburgh wrote that he agreed with Mr McLintock that the soak pit ought to have been adequate to cope with any excess ground water. However it appears that this chamber was designed and installed solely to deal with water being piped from the section above, not the water on this property’s section.   That is Mr O’Hagan’s view.   He stated in his witness statement in reply that there is a lack of sub-soil drainage at the rear wall to deal with the accumulating water.

[37]      In any event, there was consensus that the long-term saturation of the soil under the rear ground level deck shows there is a problem with drainage on the sloping ground at the back of the unit.

[38]      I conclude that the damage at the rear of the property, to the sub- floor framing, the floor and to a degree the framing and cladding, is in part due to surface and subsoil water at the base of the building arising from inadequate drainage.  I conclude that the lack of submission-floor ventilation is also partly responsible for the repairs necessary at the rear of the house.

[68]     Contrary to the submission for Messrs Coughlan and Humphrey, it is clear from  the  Tribunal’s  decision  that  it  considered  the  relevant  expert  evidence, including the evidence of Mr McLintock, the registered civil engineer, which they relied on, and accepted the evidence of Messrs Light, Roxburgh and O’Hagan that had vents been installed they would have made a difference.  While Mr McLinctock gave evidence that he did not think ventilation would have had a significant effect on taking the moisture away, he accepted that it would have had some effect.  In light of the relevant evidence on this issue, the Tribunal was entitled to reach the conclusion that it did.  The Tribunal was not wrong to do so.

[69]     As  counsel  for  the  Abernethys  also  pointed  out,  the  lack  of  sub-floor ventilation did not have to be the sole cause of the damage or to cause all of the damage.  It was sufficient if it materially contributed to the damage in whole or in part,  and  if  so,  Messrs  Coughlan  and  Humphrey  were  liable  for  the  full  loss:

Bonnington  Castings  Ltd  v  Wardlaw50,  Findlay  and  Sandelin  v  Auckland  City

Council51 and The Law of Torts in New Zealand.52

[70]     Eighth, the Tribunal did not err in not accepting that the Abernethys had failed to mitigate known damage at the rear of the house so that any loss associated with that area should be limited to $10,597.50 including GST.

[71]     On this issue, I accept the submissions for the Abernethys in response that:

a)       The problems at the rear of the house were not fully identified in the pre-purchase reports and the Abernethys were not aware of the extent or causes of the problems.  The Abernethys carried out a number of the  items  suggested  as  remedial  work  and  attempted  to  instruct experts and contractors to carry out further remedial work.

b)The  submission  for  Mr  Coughlan  that  no  further  maintenance  or repair work was done to the house between January 2005 and the date of the hearing is incorrect.  The Abernethys arranged for a number of repairs and maintenance issues to be addressed during this period of time.   In this respect, subject to later consideration of their cross- appeal, the Abernethys took at least some steps to mitigate their loss.

c) The Tribunal accepted the evidence that the property required a full reclad and that the remedial costs claimed by the Abernethys were reasonable: at [57]. There was no debate about the remedial costs between the experts.

d)The Tribunal found that the cost to repair the north wall (including the damage caused by the defects in relation to the sub-floor) was 35 per cent of the total cost of the repairs: at [153]. Part of the damage to the north wall elevation was caused by the failure to design and install vents, it was also found to be caused by a failure to install vertical

50 Bonnington Castings Ltd v Wardlaw [1956] AC 615 (HL).

51  Findlay and Sandelin v Auckland City Council HC Auckland CIV-2009-404-6497, 16 September

2010 at [46].

52 Stephen Todd (ed) The Law of Torts in New Zealand (5th ed, Thomson Reuters, Wellington, 2009)

at [20.2.02].

control  joints  and  a  failure  to  adequately  seal  and/or  flash  the windows.

e)       The damage that Mr Coughlan was held liable for was not isolated to the vents.  There were a number of defects that were causative of the damage requiring repair.

f)        Mr Light’s estimated figure to repair the sub-floor area in 2004 bore no resemblance to the 2009 figure for repairing the whole house. There   was   therefore   no   foundation   for   the   submission   that Mr Coughlan’s liability should be capped at $10,597.50.

[72]     In summary, in relation to the liability of Mr Coughlan, I have not accepted any of the grounds of appeal advanced on his behalf.   In respect of the grounds where it was alleged that there was no evidence to support the Tribunal’s findings I have held that there was evidence or that the Tribunal was entitled to prefer the evidence of particular witnesses.  In respect of the grounds based on submissions of law I have preferred the submissions for the Abernethys in response.

[73]     I now turn to consider the appeal in relation to the liability of Mr Humphrey.

Mr Humphrey’s liability

[74]     For Mr Humphrey, it was submitted that he was not liable because –

a)        He was not the project manager;

b)He was not engaged to supervise the contractors and did not in fact manage the project;

c)        He therefore owed no duty of care to the Abernethys;

d)Alternatively, the builders were not negligent so Mr Humphrey was not negligent either;

e)        Any negligence on the part of Mr Humphrey did not cause any loss beyond the sum of $10,597.50 including GST.

[75]     It  is  convenient  to  set  out  in  full  the  Tribunal’s  findings  in  relation  to

Mr Humphrey’s liability:

Was Mr Humphrey liable as project manager?

[99]      Mr Humphrey said his role was that of a quantity surveyor.   He acted as a co-ordinator.  He organised materials and subcontractors but he did not control the site.   That was part of the terms of arrangement with Mr Coughlan.  The labour-only contractors were independent in their work and were used to taking responsibility.   They worked from start to finish without overseers.  He was never employed at that time as a site manager.

[100]    Mr Humphrey said he obtained quotes, for the windows etc, and arranged delivery dates.  He did a lot of the work as and when required, a lot of it on his cell phone.  He would telephone the suppliers.

[101]    When  the  problem was  discovered  with  the  water  flowing  from

3 Pupuke Road, the Council instructed what the remedy was and a drain layer was engaged.

[102]    Concerning the question of whether anybody was responsible for the quality of building work, Mr Humphrey said the Council inspectors were (responsible) in those days – they passed work or rejected it.

[103]    Mr Humphrey said he was a builder by profession and did quantity surveying for this job as it was simple, quoting for the building elements.  It was important to keep costs to a minimum as they had a mortgage.  He only took the same amount as Mr Coughlan took for drawing the plans and obtaining consent.  Mr Humphrey said he had to earn a living.  He was paid, from memory, $6,000.00.  He did other work at the same time at other jobs to support himself.  The earlier units built on that general site were on the same basis.

[104]  He said that construction went ahead smoothly as there were experienced contractors.  He did not remember who they were.  The industry changed from waged workers to labour-only contractors.   There was no reason to treat such contractors any differently than plumbers or drain layers

– they were only labour-only too.

[105]    The building contractors installed the cladding.  Mr Humphrey said he did not recall the change from Hardibacker to Harditex.  He said that he was not an expert on the difference.

[106]    I accept Mr Humphrey’s evidence that Stockdale and its directors left it to the three labour-only builders and other contractors to run the site, and I accept Mr Humphrey’s evidence that he was not managing the project in the sense that he was personally controlling or supervising the site.  He was engaged by Stockdale to work part-time administering the project by engaging labour only contractors and ordering supplies to be delivered at the times the contractors on site said that they were required.  This was a three unit development and Mr Humphrey carried out his duties part time.

[95]     In  exercising  the  power  to  apportion  liability  between  respondents,  the Tribunal should therefore follow the approach stipulated by s 17(2) of the Law Reform Act 1936 which provides:

In any proceedings for contribution under this section the amount of the contribution recoverable from any person shall be such as may be found by the Court to be just and equitable having regard to the extent of that person's responsibility for the damage; and the Court shall have power to exempt any person from liability to make contribution, or to direct that the contribution to be recovered from any person shall amount to a complete indemnity.

[96]     In the present appeal, as the submissions for the parties recognise, the issue is whether the Tribunal ought to have exercised its power to apportion liability between the respondents, that is the Council, Stockdale, Messrs Coughlan and Humphrey, and Mr Beazley, when the Council settled with the Abernethys at the hearing and played no further part so that in fact there was, as the Tribunal pointed out in its decision at [175]–[178], no basis on which it could, in fairness, apportion the Council’s liability between the other respondents.

[97]     It is correct, as was submitted for the Abernethys, that settlement with one joint tortfeasor does not of itself prevent subsequent apportionment of liability between all joint tortfeasors: Baylis v Waugh, Body Corporate 191608 v North Shore

61 Patel v Offord HC Auckland CIV-2009-404-301, 16 June 2009 at [34]-[37].

City Council,62  and The Law of Torts in New Zealand.63    But, as the decisions in Baylis and Body Corporate 191608 and the authorities referred to in Todd indicate, the party which settles must pursue its claim for contribution against the other joint tortfeasor(s) so that the Court is in a position to determine on a “just and equitable” basis the appropriate level of apportionment between the joint tortfeasors, including the party which settled.  As the Tribunal rightly recognised in this case, the absence of the Council from the hearing after it settled with the Abernethys and its failure to pursue its cross-claims against the other respondents meant that the Tribunal was not in a position to determine and apportion the Council’s liability.   Having not determined the Council’s liability, the Tribunal did not have power to apportion the Council’s liability under s 72(2) of the Weathertight Homes Resolution Services Act

2006 and s 17(1)(c) of the Law Reform Act 1936 or to decide what apportionment of the Council’s liability would be “just and  equitable” under s 17(2) of the  Law Reform Act 1936.   In this respect the position of apportionment of contribution between joint tortfeasors is to be distinguished from the position of a claimant whose contributory  negligence  must  be  assessed  in  light  of  the  fault  of  all  potential

tortfeasors: cf Findlay and Sandelin v Auckland City Council.64     The question of

apportionment between joint tortfeasors depends on a claim for contribution by a tortfeasor  against  another  tortfeasor  and  does  not  affect  the  claimant’s  right  to recover damages awarded against any of the tortfeasors on a joint and several basis.

[98]     The  Abernethys  may  have  been  under  an  obligation  in  terms  of  their settlement with the Council to raise the issue before the Tribunal, but to do so during final submissions was too late.  The Tribunal decided that it was not in a position to determine the issue.  I do not accept that it erred in reaching this conclusion.

[99]     I also agree with counsel for Messrs Coughlan and Humphrey that in the circumstances of this case the High Court is not in a position to carry out a new liability  apportionment  exercise  as  suggested  by  counsel  for  the  Abernethys: cf s 95(1)(b) of the Weathertight Homes Resolution Services Act 2006.

62  Body Corporate 191608 v North Shore City Council HC Auckland CIV-2008-404-2358, 9 June

2010.

63 Stephen Todd (ed) The Law of Torts in New Zealand (5th ed Thomson Reuters, Wellington, 2009)

at [24.3.02].

64  Findlay and Sandelin v Auckland City Council HC Auckland CIV-2009-404-6497, 16 September

2010 at [51]-[58].

[100]   For completeness I note that I have not reached my conclusion on this ground of cross-appeal on the basis of the submission for Messrs Coughlan and Humphrey that the Abernethys  “discontinued” their claim  against the Council in the sense contemplated by the High Court Rules because a formal “discontinuance” of that nature  would  have  required  the  written  consent  of  all  the  other  respondents: r 15.20(4) of the High Court Rules.  I have approached this ground of appeal on the basis that it was for the Abernethys to show that the Tribunal erred in the exercise of its discretionary decision on apportionment.   I am not satisfied that in the circumstances of this case arising from the Council’s settlement and withdrawal that the Tribunal did err in declining to determine and apportion the Council’s liability.

Remedial costs

[101]   On this ground of their cross-appeal, the Abernethys argue that the Tribunal’s decision to award them only 50 per cent of the total cost of repairs and professional fees of $240,668.06 was plainly wrong and a conclusion not reasonably available on the evidence because, according to well-established principles, they were entitled to recover as compensatory damage the sum required to put them in the position they would have been if the wrong had not been committed and that, confronted with the prospect of having to repair two walls, they had no option but to repair four walls.

[102]   For Messrs Coughlan and Humphrey, it was submitted in response that it is well-established that, where it is practicable to determine the extent of the contribution between tortious and non-tortious causes, damages should be apportioned  between  the  different  causes and  here  the  Tribunal’s  approach  was correct because the evidence before the Tribunal established that the damage to each wall of the house was separately identifiable and the remedial costs quantifiable.

[103]   The legal principles relied on by the parties are well-established:  The Law of Torts in New Zealand.65   The question is whether the damage is indivisible or not so that in practical terms the cost of repairs is able to be apportioned between the different areas of damage and their causes.   The question is a question of fact dependant on the circumstances of the particular case.

65 Above n 63 at [25.2.01] and [20.2.02].

[104]   In the present case, as the Tribunal held at [138]–[154], the evidence before the Tribunal did establish that the damage to each wall of the house was separately identifiable and the remedial costs quantifiable.   As counsel for Messrs Coughlan and Humphrey pointed out, the relevant evidence comprised:

a)        The supplementary report by Mr Light, the WHRS assessor, dated

20 June 2007, and the plans for the proposed re-cladding of the house which distinguished in practical terms between the south, east and north elevations (or walls) of the house.

b)The  Kwanto  Estimate  of  Remedial  Costs  prepared  for  O’Hagan Building Consultants Ltd dated 6 July 2007, which contained a separate breakdown of estimates of remedial costs for the north ($19,122.50), west ($0.00), south ($37,793.50) and east ($14,318.00) elevations.

c)       The Boss Projects Ltd tender price, which used the Kwanto estimate, was the successful tender.

[105]   On the basis of this evidence, the Tribunal was entitled to conclude that it was practicable to distinguish between the four walls, the causes of the damage to them and the costs of repairing them, for the purpose of deciding that “the compensable proportion” should be 35 per cent (north wall) plus 15 per cent (east wall) making 50 per cent or $120,334.03.   I am therefore not satisfied that the Tribunal was wrong to reach this conclusion.

Mitigation and contributory negligence

[106]   On this ground of their cross-appeal, the Abernethys argue that the Tribunal’s decision to reduce their damages by 10 per cent for contributory negligence and failure to mitigate their loss was based on flawed methodology and did not have an evidential basis.   The Tribunal’s methodology was flawed because contributory negligence, which involves a percentage apportionment, should not have been combined with failure to mitigate, which requires proof of a dollar amount.

[107]   For Messrs Coughlan and Humphrey, it was argued that the 10 per cent contribution was too low and that an award of somewhere near 100 per cent was required to reflect the Abernethys’ voluntary assumption of risk and relative responsibility  for  their  loss.     It  was  agreed  that  the  Tribunal  had  confused contributory negligence and failure to mitigate loss which were two distinct matters.

[108]   The Tribunal addressed the issues of contributory negligence and failure to mitigate loss in the following paragraphs of its decision:

[163]    I have had regard to Mr and Mrs Abernethy’s evidence and their valuer’s report, and their solicitor’s memorandum of 31 July 2003 to the vendors’ solicitor.   This states that Mr and Mrs Abernethy had received Mr Beazley’s first report and had concerns about a downpipe, the condition of and numerous cracks in the exterior cladding, and some areas of potential water leakage.  They asked through their solicitors for consent for invasive tests to be carried out.  As it has turned out, Mr Beazley did not receive such consent.   But nonetheless, having regard to his second report, I find that there was an element of contributory negligence by the Abernethys.  They knew that the building was built of risky materials; that it had been badly neglected by the vendors; and that it was likely moisture had already penetrated the building envelope.

[164]    It was not Mr and Mrs Abernethy’s fault that the building was in such a poor condition when they bought it, but nor was that the respondents’ fault either.   Mr and Mrs Abernethy did take a calculated risk that such a building would not turn out to be leaky.

[165]    For those reasons, notwithstanding that the precautions and steps they took were reasonable, Mr and Mrs Abernethy must share in the above costs  of  its  having  turned  out  to  be  a  ‘bad  buy’.    They  should  not  be penalised for having obtained pre-purchase reports; but neither does their having done so absolve them from having to take some responsibility for their decision to purchase this townhouse.   I find Mr and Mrs Abernethy were also negligent, for those reasons.

[166]    The  question  also  arises  whether  the  overall  figure  for  damages should be reduced because they did not mitigate their losses by immediately taking steps to have ventilation installed and sheeting laid over the ground in the sub-floor area after the first WHRS report was received.   Mr and Mrs Abernethy have addressed a number of relatively minor issues since Kwanto the quantity surveyor’s engagement, amounting to the $3,953.04.

[167]    Nevertheless,  Mr  and  Mrs  Abernethy  decided  to  live  abroad  in January 2005 when the problems with the house that Mr Light had identified in July 2004 were still unresolved.  Even though Mr Kime was appointed, he apparently did not know when they left New Zealand that the house was, officially, leaky.  Mrs Abernethy did arrange with Mr Kime to obtain quotes but they received conflicting advice as to what they should do.   Two contractors were unwilling to undertake work because they were uncertain how the house should be further repaired.  The first engineer engaged was let go because of the conflict of interest, before Mr O’Hagan was engaged in

2007.

[168]    As a result, the recommendations in Mr Light’s first report have never been implemented or fully implemented, including installing sub-floor vents.  Nor has the problem with drainage been addressed by the laying of new pipes across the back of the section.

[169]    While they needed to be sure of what needed to be done, Mr and Mrs Abernethy’s decision to live abroad must be seen as a factor in the delay in addressing the problems and damage that were coming to light before they left.

[170]    Taking all those factors into account, especially their assumption of risk given the materials and previous lack of maintenance, and the delay, the figure of $167,012.07 should be reduced by 10%, $16,701.21, giving a final

figure of $150,310.86.  The first respondent, the second respondent, at least by implication and at least to the extent of $90,000.00 the third respondent, and the fourth respondent are all jointly and severally liable to the claimants for this amount. Mr Beazley the fifth respondent’s liability is more limited.

[109]   In considering the submissions of the parties on appeal in relation to this part of the Tribunal’s decision, I take into account the following points:

a) I have already decided that Messrs Coughlan and Humphrey did not discharge the onus of proof of establishing that the Abernethys had full knowledge of the nature and extent of their “leaky home” problems before they purchased the property in September 2003 so that the defence of voluntary assumption of risk was not available: at [42]–[50] above.

b)I have also already decided that the Tribunal was not wrong in finding Messrs   Coughlan   and   Humphrey   liable   to   the   Abernethys   in negligence for breach of their respective duties of care as designer and project manager: at [72] and [85] above.

c)       The defences of contributory negligence and failure to mitigate loss are conceptually different and should therefore be considered separately: The Law of Torts in New Zealand.66     Under s 3 of the Contributory Negligence Act 1947, when damage is caused by fault on  the  part  of  both  defendant  and  plaintiff,  the  Court  may in  its discretion apportion responsibility between them.  Ordinary principles of causation and remoteness apply.   Failure to mitigate loss arises because a plaintiff is under a duty, which is not particularly onerous,

to take reasonable steps to mitigate loss and thereby minimise the damages the defendant will be required to pay.   Contributory negligence is concerned with identifying the plaintiff’s fault contributing to the damage and apportioning responsibility for it (by way of a percentage), whereas breach of the duty to mitigate loss requires identification of the “reasonable steps” the plaintiff ought to have  taken  and  assessment  of  the  amount  by  which  the  damages should be reduced as a result of the plaintiff’s failure to take such

steps.  Apportionment of responsibility to reflect a factual finding of contributory negligence and reduction of damages to reflect a factual finding of a failure to mitigate loss are different exercises, involving different findings and, in the case of contributory negligence, a discretion in apportioning responsibility.   The exercises should therefore be carried out separately so that it is clear that the correct approach has been followed in each case, particularly if the separate

66 Ibid at [21.2] and [25.2.03].

approaches may be the subject of examination on appeal.

d)In this case the Tribunal made separate factual findings in relation to the Abernethys’ contributory negligence (at [163]–[165]) and their failure to mitigate their losses (at [166]–[169]), but then, instead of apportioning their responsibility for contributory negligence and assessing the amount by which their damages should be reduced as a result of their failure to mitigate, simply decided that the damages of

$167,012.07 should be reduced by 10 per cent ($16,701.21) to give a final figure of $150,310.86.  It is therefore not possible to determine from the Tribunal’s decision what the apportionment was for contributory negligence or what the amount for the reduction in damages was for the failure to mitigate loss.

[110]   The  contributory  negligence  issues  on  appeal  are  therefore  whether  the Tribunal was right to make a factual finding of contributory negligence on the part of the Abernethys and, if so, whether it exercised its discretion appropriately to apportion their responsibility at some unknown figure less than 10 per cent.   The failure to mitigate loss issues are whether the Tribunal was right to make a factual finding that the Abernethys had not taken reasonable steps to mitigate their loss and, if so, whether it correctly assessed the reduction in damages for that failure at some unknown figure less than $16,701.21.

[111]   I  agree  with  counsel  for  the  Abernethys  that  they  acted  reasonably  in obtaining the pre-purchase reports from Mr Beazley and in negotiating a reduction in the purchase price to reflect part of the cost of the repairs he identified.  At the same time, however, they proceeded with the purchase of the house knowing from the reports and the fact that full invasive tests, as recommended by Mr Beazley, had not been carried out that they were running some risk in doing so, particularly as they also knew there was significant deferred maintenance.  On the basis of Mr Beazley’s reports, the risk was minor, but it cannot be said that the Tribunal was wrong to take it into account in finding an element of contributory negligence and in apportioning it at a figure below 10 per cent.

[112]   I  also  agree  with  counsel  for  the  Abernethys  that,  as  their  mitigation chronology shows, they did take various steps to mitigate their loss over the period from September 2003 to August 2008.   At the same time, however, there were significant delays in carrying out the work recommended by Mr Light, the WHRS assessor, in his first report of 28 July 2004, particularly after the Abernethys decided to live abroad in January 2005.   On the basis of the evidence summarised in the Tribunal’s decision, it cannot be said that the Tribunal was wrong to find that the Abernethys had not taken all reasonable steps to mitigate their loss and that their damages should be reduced by a figure less than $16,701.21.

[113]   While I accept that it is not satisfactory to be unable to examine the actual amounts involved in the Tribunal’s apportionment for contributory negligence and reduction for failure to mitigate loss, in the circumstances of this case and taking into account the amounts involved in the two exercises I am not prepared to conclude that when taken together the 10 per cent reduction was wrong.

General damages

[114]   On this ground of their cross-appeal, the Abernethys argue that the Tribunal’s decision to award general damages of $7,500 for Mrs Abernethy and $5,000 for Mr Abernethy was inconsistent with relevant authorities and not justified by the evidence.  For Messrs Coughlan and Humphrey, it was argued that the Abernethys had not shown that the Tribunal’s decision was unreasonable or an entirely erroneous estimate of the general damages to which the Abernethys were entitled.

[115] The Tribunal addressed the issue of general damages in the following paragraphs of its decision:

[157]    However I do not accept that a figure of $60,000.00, for general damages, $30,000.00 each for Mr Abernethy and Mrs Abernethy, is reasonable.

[158]    This is because they have not lived in the house for over four and a half years of the six years since they bought it in September 2003.   They occupied the house only for 16 or 17 months until January 2005.

[159]   The High Court has given weight to the detrimental effects of occupation on owners of leaky homes.   The Abernethys have been spared much of that.  They have continued to bear the burden of coping with the

implications of its being a leaky building.   This has involved stress, inconvenience and worry.

[160]   Accordingly the amount claimed for general damages should be significantly reduced to $7,500.00 for Mrs Abernethy, who has born the major share of the burden, and $5,000.00 for Mr Abernethy.   That is consistent with my accepting their claim for $30,225.00 for consequential losses, which is for reduced or lost rental income including lost rent while repairs are being carried out.

[116]   There is no dispute that if their claim for damages for their “leaking home” is upheld the Abernethys are entitled to general damages for non-economic loss.  The only question is the appropriate amount.

[117]   Since the Tribunal’s decision of 26 August 2009 the Court of Appeal has considered the question of the appropriate amount of damages for non-economic loss in “leaky homes” cases in Byron Avenue.67 After considering the relevant principles and a range of other “leaky home” cases, Baragwanath J concluded at [129]:

By a process of similar reasoning I would alter the figure of $12,500 set by the Judge to $15,000 in relation to the non-resident plaintiffs and the single sum where the burden is shared $20,000 to $25,000.

[118]   Commenting on the same issue in Byron Avenue William Young P, with whom Arnold J agreed, said:

67 Byron Avenue [2010] NZCA 65 and 235.

[152]    I consider that this Court has a role in giving general guidance as to appropriate levels of compensation for non-economic loss in leaky homes cases.  Rules of thumb would serve to reduce the cost of resolving litigation of this sort, and, as well would facilitate consistency. On the other hand, I agree with Baragwanath J that this is not an ideal case for such general guidance to be given, primary because, as he notes, the material before us was rather too limited for us to be confident that we have a reasonably complete grasp of all the relevant issues.

[153]    For the reasons given by Baragwanath J, I support awards for non- economic loss in this case which proceed on the bases that:

(a)   Such awards should not made in favour of corporate owners; (b)   $15,000 is appropriate per unit for non-occupiers ; and

(c)   $25,000 is appropriate per unit for occupiers.

As Baragwanath J points out, however, not all the claims can be neatly categorised in this way and some evaluative assessment may be required.

[154]  This  approach  involves  elements  of  rough  justice.  By  way  of illustration of this proposition, a purchaser with a phlegmatic disposition does as well as one who is more prone to stress and allowances for the length of time the purchasers have lived with the problem are broad-brush at best. On the other hand, there is a limit to the extent to which it is practical to go into fine detail on assessments of this kind.

[119]   While the Court of Appeal subsequently clarified that the orders proposed by Baragwanath J for the awards of damages for non-economic loss were the orders of the Court,68  it is clear that the Court was giving “general guidance” and “rules of thumb” for the purpose of reducing litigation costs and facilitating consistency.  As Baragwanath J had recognised, an appellate court will interfere with an award of general damages only if satisfied that the award is “wholly erroneous”:

68 Byron Avenue [2010] NZCA 235 at [2]–[3].

[112]    This Court will interfere with an award of general damages only if satisfied that the award is wholly erroneous. That is for two reasons. One is that the trial judge, who has a feel for the case and the witnesses unattainable from reading briefs and transcripts, is better equipped than this Court to appraise their significance and the actual effect of stress resulting from the breach of duty. The other is the imprecision of the value judgment of how that effect can be expressed in money terms. While because of the number of pending claims there would be real benefit from the provision of guidelines to assist settlements, the emphasis of the present case was understandably upon aspects other than general damages. We do not have the evidence nor did we receive the argument needed to provide guidelines. A test case on such matters would focus sharply upon:

(a)   the  objective  nature  of  the  stress-inducing factors,  including their character and duration;

(b)   the evidence as to their effect on the plaintiff;

(c)   in the case of occupants of leaky buildings the factors discussed in the report Do Damp and Mould Matter? Health Impacts of Leaky Homes;

(d)   assessment of how such injury and its results compares with that in other general damages awards.

(Footnotes omitted).

[120]   Bearing in mind the general reluctance of an appellate Court to interfere with awards   of   general   damages,   the   factors   mentioned   by  Baragwanath   J   and William Young P, and the level of general damages for non-occupiers approved by the Court in Byron Avenue in the circumstances of the cases before the Court, I am not prepared to conclude on appeal in the present case that the Tribunal’s decision to

award the Abernethys, as non-occupiers, general damages of $12,500 was “wholly erroneous” or so outside the range of what was reasonable in the circumstances of this case that it ought to be set aside.

Result

[121]   Accordingly,  for  the  reasons  I  have  given,  both  the  appeal  by  Messrs

Coughlan and Humphrey and the cross-appeal by the Abernethys are dismissed.

[122]   As submitted for the Abernethys, interest will be payable on the amounts in the Tribunal’s decision from the date of that decision: s 95(2)(a) of the Weathertight Homes Resolution Services Act 2006 and White v Rodney District Council.69

[123]   As Messrs Coughlan and Humphrey have been unsuccessful on their appeal and the Abernethys have been unsuccessful on their cross-appeal, costs should lie

where they fall.

D J White J

69 White v Rodney District Council HC Auckland CIV-2009-404-1880, 12 March 2010 at [21]–[24].

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

6

Statutory Material Cited

0

Pullar v R [2007] NZCA 389