IN THE HIGH COURT OF NEW ZEALAND CHRISTCHURCH REGISTRY
CIV 2008-409-002301 [2014] NZHC 2118
BETWEEN CONCRETE STRUCTURES (NZ)
LIMITED Plaintiff
AND
NZ WINDFARMS LIMITED Defendant
Hearing: 21-24 July 2014 Counsel:
G P Blanchard for Plaintiff
J Smith QC and R G Smedley for DefendantJudgment:
3 September 2014
JUDGMENT OF WHATA J
Introduction
[1] Concrete Structures (NZ) Limited (CSL) and NZ Windfarms Limited (NZ Windfarms) entered into a construction contract under which CSL was engaged to assist in the construction of a wind farm. The wind farm was duly constructed, but there were several problems along the way. CSL seeks to recover about $250,000 plus interest for variations that were not approved by NZ Windfarms’ engineer. The critical issue before me therefore is whether or not the sought after variations should have been approved.
Background facts
[2] In March 2006 CSL entered into a contract with NZ Windfarms to carry out civil engineering and construction work at NZ Windfarms’ Te Rere Hau Windfarm Development, Palmerston North. There were two key aspects of the contract namely to upgrade and maintain roads to enable access to the various tower locations and to construct
the bases for the towers.
CONCRETE STRUCTURES (NZ) LIMITED v NZ WINDFARMS LIMITED [2014] NZHC 2118 [3 September
2014]
The contract
[3] The contract included the following particulars:
(a) The contract was a measure and value contract that included a schedule of quantities and prices;
(b)The contract price was $832,218.30 including GST or such other or lesser sum shall become payable under the contract;
(c) NZS 3910:2003 (“3910”) was incorporated into the contract as the general
conditions of contract except as where modified by the special conditions;
(d)Murray Fletcher was appointed by the defendant as the engineer to the contract;
(e) Clause 5.11.3 of the contract contained provisions concerning the obtaining of licences and consents under the contract:
5.11.3 The Principal shall at the Principal’s expense obtain all licences, which may be required for the construction of the Contract Works and for the use of the Contract Works when constructed except as otherwise provided for in 5.11.4.
(f) Clause 5.11.6 of the contract provided that:
5.11.6 If licences, obtained by the Principal or by the Contractor are subject to conditions affecting the carrying out of the Contract Works, those conditions shall be notified to the other party and to the Engineer. If the compliance with these conditions causes delay in the completion of the Contract Works or additional Cost to the Contractor which in either case the Contractor could not reasonably have foreseen when tendering the compliance will be treated as if it was a Variation.
(g)Clause 6.2.1 of the contract provided that the dual role of the engineer in the administration of the contract was:
i. As an expert adviser to and representative of the defendant; and
ii.To independently of the contracting parties, fairly and impartially make decisions entrusted to him under the contract, to the value of the work and to issue certificates.
(h)Clause 6.7.1 of the…
Keep reading for free
Create a free CaseChat account to read Concrete Structures (NZ) Limited v NZ Windfarms Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] NZHC 2118
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.