IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2011-404-8000 [2014] NZHC 1821
BETWEEN BODY CORPORATE 325261
Plaintiff
R W COOKE AND OTHERS Second Plaintiffs
AND
JAMES MCDONOUGH First Defendant
Continued…
Hearing: 28 and 29 July 2014 Counsel
G J Kohler QC and C Baker for Plaintiffs
J R J Knight and D J Barr for Third Defendant
D S McGill for Fifth Defendant (attendance excused)
S Mills QC, B O'Callahan and A C Poole for Sixth and Seventh
DefendantsJudgment:
29 July 2014
ORAL JUDGMENT OF KATZ J
Solicitors: Price Baker Berridge, Auckland
Simpson Grierson, Auckland
Carter Kirkland Morrison, Auckland
Duncan Cotterill, Auckland
Counsel: G J Kohler QC, Shortland Chambers, Auckland
S Mills QC, Shortland Chambers, Auckland
Copy to: James McDonough
BODY CORPORATE 325261 v MCDONOUGH & ORS [2014] NZHC 1821 [29 July 2014]
MAUNGA REI NZ LIMITED
Second Defendant AUCKLAND COUNCIL Third Defendant
GARY BICKERTON Fourth Defendant RACHEL VENABLES Fifth Defendant
STEPHEN MITCHELL ENGINEERS LIMITED
Sixth Defendant
STEPHEN ROBERT MITCHELL
Seventh Defendant
MACDONALD BARNETT PARTNERS LIMITED
Eighth Defendant MICHAEL SIMPSON Ninth Defendant
FRAMERITE INSTALLATIONS LIMITED
Third Third Party
Introduction
[1] These proceedings concern a 130 unit residential apartment building, known as the C-Vu apartments, on the corner of Hopetoun and Day Streets in Auckland. The first plaintiff is the body corporate of the unit title development and the second plaintiffs are the various individual apartment owners.
[2] The proceeding was initially commenced as a leaky building claim, although claims relating to structural and seismic issues were subsequently added. There are currently nine defendants and five third parties. Recently, shortly before a 10 week trial of the proceedings was due to commence, the plaintiffs settled with all of the defendants save for the structural engineers, Stephen Mitchell Engineers Limited and Mr Stephen Robert Mitchell (together referred to as “SML”). The plaintiffs claim that SML’s failings contributed to weathertightness defects in the building and, in addition, that SML are primarily liable for certain structural seismic defects.
[3] The trial between the remaining parties is now scheduled to commence on
4 August 2014, with an estimated hearing time of eight weeks. This judgment relates to an application by the plaintiffs for leave:
(a) to discontinue their claims against those defendants they have reached settlement agreements with;
(b) to file an amended statement of claim; and
(c) to call certain supplementary evidence. [4] I will consider each issue in turn.
Discontinuance
[5] The plaintiffs seek leave to discontinue their claims against the defendants they have settled with (the first, second, third, fourth, fifth, eighth and ninth defendants). The matter is complicated somewhat by the fact that SML has cross claims against the first to fifth defendants.
[6] SML does not oppose the plaintiffs discontinuing their claims against the various defendants they have settled with, provided that the first to fifth defendants remain parties to the proceedings and the claims as pleaded against them in the ninth amended statement of claim (“9AMSOC”) remain on foot to the extent necessary for the purposes of SML’s cross claims.
[7] I am satisfied that granting leave to the plaintiffs to discontinue their claims against the first, second, third, fourth, fifth, eighth and ninth defendants is appropriate. SML will not be prejudiced, as r 15.25 of the High Court Rules provides that if a plaintiff discontinues a proceeding in which a defendant has previously issued a cross claim, the discontinuance does not affect the continuation of the proceeding in relation to that cross claim.
[8] Accordingly, regardless of any discontinuance by the plaintiffs of their claims against the first to fifth defendants, those parties will remain parties to the proceedings for the purposes of SML’s cross claims. For the avoidance of doubt, as a condition of leave to discontinue, any current pleadings relating to the plaintiffs’ claims against the first to fifth defendants are to remain on foot to the extent necessary to enable the relevant parties to either pursue or defend SML’s cross claims against the first to fifth defendants.
The plaintiffs’ application for leave to file a 10th amended statement of claim
Leave to amend pleadings – relevant legal principles
[9] No amended pleading may be filed after the close of pleadings without the leave of a Judge.1 The plaintiffs accordingly seek leave to file a 10th amended
statement of claim (“10AMSOC”) as pleadings have closed.
1 High Court Rules r 7.7.
[10] Previous case law has identified a number of factors that should be taken into account in determining whether it is appropriate to grant leave to file an amended statement of claim. It is generally recognised that the paramount consideration is that the parties should have every opportunity to ensure that the real controversy
goes to trial so as to secure the just determination of the proceeding.2 Due regard
must also be had to whether the proposed amendment will cause significant delay or prejudice another party.3 Even where serious prejudice and significant delay will arise, an amended pleading may nevertheless be permitted if the proposed claim has substantial merit and will not cause injustice to the defendants.4
[11] The Court of Appeal in Elders Pastoral Ltd v Marr stated that an applicant must surmount three hurdles in order for leave to amend pleadings to be granted:5
(a) The amendment must be in the interests of justice.
(b) The amendment must not significantly prejudice the other party. (c) The amendment must not cause significant delay.
[12] Another relevant factor in considering whether to grant leave or not is the merit, or absence thereof, in a proposed amended pleading.6 The impact of granting the amendment on case management issues must also be taken into account. Consideration must also be given to whether a proposed amendment includes a fresh cause of action and whether or not any fresh cause of action is
statute barred. The timing of an application for leave to amend is also relevant.
2 See Shanton Apparel Ltd v Thornton Hall Manufacturing Ltd [1989] 3 NZLR 304 (CA) at 309; Chilcott v Goss [1995] 1 NZLR 263 (CA) at 272-273; Marr v Arabco Traders Ltd (No 8) HC Auckland A1195/77, 12 March 1987 affirmed on appeal in Elders Pastoral Ltd v Marr (1987) 2
PRNZ 383 (CA).
3 Elders Pastoral Ltd v Marr (1987) 2 PRNZ 383 (CA).
4 Body Corporate 177519 v Auckland City Council HC Auckland CIV-2005-404-5563, 24 May
2011.
5 At 385 and as set out by Ellis J in Body Corporate 177519 v Auckland City Council HC Auckland CIV-2005-404-5563, CIV-2006-404-3267, 24 May 2011 at [12].
6 Fordham v Xcentrix Communications Ltd (1996) 9 PRNZ 682 (HC) at 683.
[13] As Mr Mills QC submitted, on behalf of SML, in reliance on Swain-Mason v Mills, there is a heavy burden on a party who seeks to raise a new and significantly different case at the opening of the trial.7 In that case the trial Judge had allowed an amendment at the commencement of the trial which resulted in the trial having to be adjourned. The English Court of Appeal allowed an appeal, noting that a heavy onus lies on a party seeking to make a very late amendment to justify it, as regards his
own position, that of the other parties to the litigation, and that of other litigants in other cases before the Court. The continuing inadequacy of the pleading in that case, even post amendment, was also a significant factor.
Overview of proposed amendments
[14] Many of the proposed amendments to the 9AMSOC are uncontroversial, as they arise out of the settlement that has been reached between the plaintiffs and the other defendants and the associated discontinuance of the plaintiffs’ claims against those defendants. Other proposed amendments are of an updating or corrective nature. Indeed some of the changes result in a reduction of the claim against SML. Several changes are, however, objected to as either introducing new causes of action or unfairly prejudicing SML, given the imminence of the trial date.
[15] I will address each of the specific changes objected to in further detail. I note
at the outset, however, that I do not accept SML’s submission that the proposed
10AMSOC raises any new causes of action. Rather, I accept Mr Kohler QC’s submission on behalf of the plaintiffs that the core pleadings regarding the duties of care owed, the defects in the building, the alleged breaches by SML and the remedial works required, are the same in the proposed 10AMSOC as they were in the
9AMSOC.
7 Swain-Mason & Ors v Mills & Reeve [2011] EWCA Civ 14 (citing Worldwide Corporation Ltd v
GPT Ltd & Anor [1998] EWCA Civ 1894).
[16] In particular, the core allegations are as follows:
Plea 9AMSOC 10AMSOC SML owed a duty of care to exercise reasonable care and skill in:
- Plans
- Observation
- Producer Statement
Paras 90 and 98
Paras 42 and 50
SML breached duty of care re:
- design
- construction
Paras 91 and 99
Paras 43 and 51
Defects particularised: Defects 27-48
Para 27
Para 25
Breach: plea of breach of Building
Act/Building CodePara 28
Para 26
Breaches specific to sections of Building
CodePara 28
Para 27
Plea of remedial works required
Para 31
Para 29
[17] I do not overlook SML’s submission that although the proposed changes to the pleading may appear relatively minor on their face, appearances can be deceiving. Further, I accept that amendments to a pleading can have a very significant prejudicial effect even if they do not raise a new cause of action. I also note SML’s submission that it is only when some of the proposed amendments are viewed together with the plaintiffs’ proposed supplementary evidence, that the true magnitude and significance of the changes objected to can be seen.
[18] Against that background, I now turn to consider SML’s specific objections to
the proposed amendments.
Claim for general damages
[19] The 9AMSOC pleads that the plaintiffs have and will suffer stress and inconvenience in the future such that they are entitled to general damages.8 The
amounts sought are as set out in Schedule I of both the 9AMSOC and proposed
8 Refer paras 97 and 105 of the 9AMSOC.
10AMSOC. The quantum sought in relation to each individual plaintiff is said to be in accordance with the “general damages tariff” as generally applied following the Court of Appeal judgment in Byron Avenue.9 In particular the sum of $25,000 is sought by owner occupiers and the sum of $15,000 for investment owners.
[20] In the 9AMSOC it is pleaded at [97] and [105] that each of the plaintiffs has suffered stress and inconvenience arising as a consequence of SML’s breaches of duty including, amongst other things, “general anxiety from the uncertainty of owning and/or living in a building affected by moisture ingress and consequential rot and decay”. Presumably reflecting the increased focus on structural and seismic issues following the settlement with all of the defendants other than SML, the plaintiffs seek leave to amend the relevant passages (now at [49](b)(iii) and [57](b)(iii) of the proposed 10AMSOC) to refer to “general anxiety from the uncertainty of owning and/or living in a building affected by moisture ingress and consequential rot and decay and anxiety and uncertainty about the structural safety of the building” (proposed amendment underlined).
[21] The plaintiffs say that the additional words do not add anything of significance. They say that the relevant paragraphs of the statement of claim, when viewed in their totality, already sufficiently plead an entitlement to general damages as a consequence of the defects pleaded against SML. The amendment is simply providing an additional particular. The plaintiffs say that such an amendment cannot be said to prejudice SML.
[22] SML, on the other hand, submits that the change reflects a real and meaningful shift in the focus of the general damages claim. Further, there is currently no evidence from the second plaintiffs that would support the claim that they have suffered anxiety regarding the structural safety of the building, as opposed to the weathertightness issues. This further reinforces that the proposed change is a real one and was not the original focus of the pleading. SML notes that it appears that it is now the plaintiffs’ intention to seek leave for supplementary evidence to be
adduced from each of the large number of second plaintiffs to support the claim that
9 Byron Avenue [2010] NZCA 65, [2010] 3 NZLR 486.
their anxiety relates to structural issues with the building in addition to weathertightness issues.
[23] SML submits that there has been no explanation for the plaintiffs’ delay in pleading this issue, nor for the delay in providing updated briefs of evidence if this is what is intended. This is particularly so given that all of the structural defects alleged by the plaintiffs (prior to the further amendment now sought) had been pleaded by 8 November 2013 and a significant number of them had been pleaded by
31 October 2013.
[24] Having carefully considered the parties’ respective arguments, it is my view that leave to make this particular amendment should be declined. If, as the plaintiffs say, the proposed change does not add anything of significance, as the pleading already sufficiently covers the relevant claim, then the plaintiffs will not be prejudiced if the amendment is not made.
[25] On the other hand, if the existing pleading does not extend to anxiety regarding structural issues, which certainly appears to be arguable, then allowing the proposed amendment would, in my view, be prejudicial to SML at this late stage, given the potential need for further evidence as to the second plaintiff’s alleged anxiety about structural issues.
[26] There is no apparent reason why the issue of the second plaintiffs’ alleged anxiety regarding structural safety issues could not have been squarely pleaded sooner. Given the real risk of the amendment being prejudicial to SML it is not, in my view, appropriate to grant leave. Leave is accordingly declined to make the proposed amendments to the wording of [49] and [57] of the proposed 10AMSOC. The precise scope of the existing pleading is a matter that can be addressed further at trial, if necessary, within the framework of the existing evidence.
Changes to estimates regarding structural remedial work – floor diaphragm issue
[27] The pleadings issue of greatest concern to SML relates to alleged structural defects relating to the floor diaphragms in the C-Vu building.
[28] Two of the structural defects alleged against SML in the 9AMSOC relate to the floor diaphragms. The relevant defects are pleaded as follows:
Defect 45: The floor starters to most of the shear walls between levels 2 and
6 have insufficient capacity to transfer the seismic shear force from the floor diaphragms: B1.3.1, B1.3.2, B1.3.3, B1.3.4
Defect 46: The floor diaphragms are severely overstressed under seismic loads: B1.3.1, B1.3.2, B1.3.3, B1.3.4.10
[29] Schedule B of the 9AMSOC sets out the “estimated” costs of remedial work for the C-Vu building under a number of headings. Item 17, under the heading “Structural Repairs” is described as “Floor diaphragm strengthening” for which an estimated cost of $300,000 is given. Item 24, under the heading “Structural Extras Weathertight Repairs” is described as “Floor diaphragm”, for which an estimated cost of $49,000 is given.
[30] Assuming the plaintiffs are successful in their claims against SML the question will arise as to what extent the building is to be remedied. The damages sought in the draft 10AMSOC are advanced on two alternative bases. The plaintiffs assert that they are entitled to a building that was (in 2002-2004) fully code compliant. The alternative basis of damages advanced is that, at the very least, the building needs to be at least 67 per cent code compliant. Schedule B of the
10AMSOC includes the estimated remediation costs of both possible scenarios.
[31] There is an increase in the estimated direct costs of achieving a fully code compliant solution. The full code cost is pleaded at $8,685,844, an increase of approximately 25 per cent over the costs pleaded in Schedule B to the 9AMSOC. The total estimated costs of the alternative 67 per cent code compliance scenario is pleaded at $3,499,155. That is a substantial reduction over the estimated costs pleaded in Schedule B to the 9AMSOC.
[32] Within that overall damages envelope, the issue of particular concern to SML
is that there has been a substantial increase in the estimated floor diaphragm remediation costs. Although defects 45 and 46 (relating to floor diaphragms) are
10 The references to B1.3.1 and so on are references to the sections of the Building Code that have allegedly been breached by these defects.
pleaded in identical terms in the 9AMSOC and draft 10AMSOC, the estimated remediation costs in relation to floor diaphragm issues in Schedule B have been significantly increased. The line item “floor diaphragm strengthening” (as described in the 9AMSOC) has been split into two parts – “upper floor diaphragm strengthening” and “basement floor diaphragm strengthening”. No particular objection was taken to that change.
[33] SML strenuously objects, however, to the overall increases in estimated costs for the floor diaphragm strengthening, as set out in Schedule B. In particular, in the draft 10AMSOC it is estimated, under the heading “Structural Repairs to Code” that upper floor diaphragm strengthening will cost $730,000. The estimated cost of basement floor diaphragm strengthening is $692,000. Under the heading “Structural Extras Weathertight Repairs” the estimated cost of upper floor diaphragm strengthening is given as $738,000 and basement floor diaphragm strengthening is given as $15,200 (the same estimates are given for the alternative 67 per cent code compliance scenario).
[34] SML submits that what the plaintiffs are proposing to do “is to very significantly amend the remedial costs claimed in respect of the remedial costs for the diaphragms without amending the pleading to provide SML with a proper claim to which it is able to respond”.
[35] SML filed an affidavit from one of its expert witnesses, Dr Murray Jacobs, in opposition to the plaintiffs’ application for leave to amend. Dr Jacobs’ evidence is that, based on discussions that have taken place between experts, he believes that a very different claim is now intended by the plaintiffs in relation to the floor diaphragm issues. The revised estimates, Dr Jacobs believes, are linked to an entirely new remediation proposal that is radically different to the plaintiffs’ original remediation proposal for the floor diaphragm issue. If a radically different (and much more expensive) solution is required then, SML submits, the plaintiffs must be intending to advance an “entirely different claim” in relation to the floor diaphragm issues to the one pleaded in the 9AMSOC and referred to in the plaintiffs’ (current) briefs of evidence. Dr Jacobs’ evidence is that he would need at least six weeks to analyse this “new claim” and prepare appropriate expert evidence in reply.
[36] For various case management reasons, the plaintiffs’ reply briefs of evidence covering, amongst other things, the floor diaphragm issues, are not due to be served until 1 August 2014. The structural experts are then required to meet, without lawyers, to produce a report similar to that done by the weathertightness experts (and which has resulted in a significant downwards adjustment of the quantum claimed in the draft 10AMSOC in relation to weathertightness issues). Included in that exercise will be the issue of precisely what remedial work (if any) is required.
[37] At the heart of SML’s objection to the proposed increase in Schedule B of the
10AMSOC to the costs of remedial work in relation to the floor diaphragms is SML’s concern that the plaintiffs’ “reply” evidence on this issue will not truly be reply evidence, but will raise essentially new matters. In particular, SML submits that if this new pleading is intended to be supported by the reply briefs of evidence from the plaintiffs’ structural engineering experts that are to be served on 1 August
2014, they will not be reply briefs and will require further expert investigation, analysis and evidence on behalf of SML, none of which can occur within the current trial envelope.
[38] The present position, however, is that the reply evidence has not yet been served. For present purposes I must assume that any reply evidence will be in compliance with the High Court Rules and any directions previously made in these proceedings. Any objections to the reply evidence, on the basis that it is not strictly in reply or otherwise, must await service of that evidence. SML’s argument in opposition to the proposed amendment to the pleading to some extent conflates issues of evidence and pleading. Although there would potentially be some advantage in waiting until after 1 August 2014 (when the reply evidence is due to be served) so that the two issues can be addressed together, the parties’ preference is that the plaintiffs’ application for leave to amend the statement of claim is dealt with now given the imminence of the trial date. I will therefore consider the proposed amendments on a “stand alone” basis.
[39] Defects 45 and 46 relate to the floor diaphragm issues. The description of defects 45 and 46 in the current pleading and the proposed new pleading is identical. SML was therefore aware, from the 9AMSOC, of the nature of the alleged defects
and has had an opportunity to address the alleged defects in its evidence and appears to have done so in some detail. Not surprisingly, SML denies the existence of the alleged defects. The initial hurdle for the plaintiffs will therefore be to establish that the pleaded defects exist and that they are attributable to failings on the part of SML. That issue is not impacted by the proposed amendments to the pleading. There is no change in the nature of the alleged defects.
[40] In the event that the plaintiffs establish that defects 45 and 46 do exist, and that they are attributable failings on the part of SML, then it will be necessary for the Court to move on to the issue of quantum and determine how much it will cost to remedy those defects. It is not unusual in major litigation of this nature for issues of quantum to be somewhat of a moving feast. As I have noted above, the proposed
10AMSOC significantly reduces the quantum claimed in some areas and also proposes an alternative basis for assessing quantum which results in significantly lower damages than those currently pleaded. Many of these changes reflect the fact that experts have met and exchanged information, calculations and views. As a result the focus with respect to remedial work appears to have narrowed somewhat.
[41] The proposed amendment to Schedule B which is of particular concern to SML, however, significantly increases the estimated costs of the remedial work relating to floor diaphragm issues. The issue before me is whether I should allow that amendment. I have concluded that I should. Any potential prejudice to SML will not arise, in my view, from allowing the proposed amendment. Rather, any potential prejudice will arise if, as SML fears, reply evidence is served that is not strictly in reply. If such evidence were to be admitted, and SML is constrained by time or resources in its ability to fully respond to it within the current trial envelop, then there is obviously the potential for unfair prejudice to arise at that stage. That issue cannot be addressed pre-emptively, however, in the context of an application to amend the statement of claim.
[42] I have not had an opportunity to review and analyse in any detail, in the limited time available, the existing expert evidence on the costs of remedying the alleged floor diaphragm issues, to the extent that such evidence is currently before the Court. Allowing the proposed amendment to the pleading does not, however,
alter the fundamental position that the plaintiffs’ evidence on floor diaphragm issues has closed, save for any evidence that it is entitled to file in reply to SML’s evidence. If, subject to those evidential constraints, the plaintiffs are able to prove that the remediation costs are greater than those currently pleaded the proposed amendment will facilitate the just determination of the real controversy between the parties. SML will not in my view be unfairly prejudiced in such circumstances. On the other hand, if the plaintiffs need to rely on evidence that has not already been filed or which is not strictly in reply in order to prove the level of quantum pleaded in the draft 10AMSOC, then the potential for unfair prejudice may arise. Whether that is the case or not, however, can only be ascertained once the reply evidence has been served.
Other proposed amendments
[43] During the course of the hearing SML identified several additional, relatively minor, proposed amendments to which it objects. Counsel for the plaintiffs advised that it would not pursue the application for leave to make those changes which are at [51](b) and [51] particular (i) of the draft 10AMSOC.
Supplementary evidence
[44] The plaintiffs also sought leave to call supplementary evidence and provided three draft supplementary briefs to the Court, outlining the proposed new evidence it seeks to adduce. There was no opposition to the proposed supplementary evidence of Kristan Roussow and leave to adduce that evidence is granted accordingly. Objection was taken, however, to aspects of the proposed supplementary evidence of Matthew Taylor and Peter Gillingham.
Supplementary evidence from Matthew Taylor
[45] Schedule F to the 9AMSOC sets out the stigma losses claimed in relation to each unit, which were assessed as being 7.5 per cent of the value of each unit. This is allegedly the loss the plaintiffs will suffer in the reduction in the capital value in each of their units after remedial works have been undertaken, as the apartment block and the units will be stigmatised.
[46] Matthew Taylor’s draft supplementary brief addresses stigma issues, amongst other matters. He states that if the 7.5 per cent stigma discount figure were to be apportioned he would apportion it 5 per cent to weathertightness issues (the leaky building history) and 2.5 per cent relating to structural repairs, on the basis that they would be fixed. In other words, even if the structural issues were remedied, there would be a 2.5 per cent price discount going forwards to reflect that the building once had structural issues. If the structural issues were not fixed, then Mr Taylor’s proposed evidence is that there would be stigma discounting of 10 per cent, split evenly across weathertightness and structural issues.
[47] SML submits that it is not in the interests of justice that leave be given at this late stage to allow Mr Taylor to give such supplementary evidence. I accept that submission. Briefs of evidence addressing stigma issues have already been exchanged between the parties. The focus of the previous evidence appears to have been on leaky building stigma and the alleged price discounting associated with this. Mr Kohler submits that aspects of Mr Taylor’s earlier evidence also addressed structural stigma issues, albeit somewhat tangentially. To the extent that is so, then the plaintiffs will be able to rely on such evidence.
[48] Ultimately, however, there needs to be an evidential cut off point. Mr Taylor’s supplementary brief addresses structural stigma issues in a much more direct way and would clearly require that leave be granted to SML to file evidence in response. An earlier trial date was adjourned and we are now within the second trial window, albeit the start date of the trial was deferred for two weeks to enable issues arising from the partial settlement to be addressed. If Mr Taylor’s supplementary evidence on stigma issues were admitted then SML would need to conduct further inquiries and brief further expert testimony on the extent to which price discounting occurs in relation to structural issues, once they have been remedied, as a result of stigma. It is not realistic, in my view, to expect SML to have to prepare such evidence on an urgent basis, during the course of a long and complex trial.
[49] Leave is accordingly declined to adduce the proposed further evidence from
Mr Taylor on stigma issues.
Supplementary evidence from Peter Henry Gillingham
[50] SML opposes the admission of supplementary evidence from
Peter Gillingham concerning water ingress to the units arising from defect 28.
[51] Defect 28 in both the 9AMSOC and the proposed 10AMSOC pleads that:
Cracking has occurred between the pre-cast concrete elements and insitu concrete beam/column joints allowing water to enter, causing deterioration of the concrete substrate and potential corrosion of the reinforcement.
[52] Mr Mills submits that, unless the plaintiffs intend to seek leave to amend the
9AMSOC to allege that the cracking has allowed water to enter the units and is responsible for the weathertightness damage, the proposed evidence is irrelevant to the claim pleaded against SML and is therefore inadmissible. Mr Kohler advise that the plaintiffs do not intend to seek leave to amend the pleading in relation to defect
28.
[53] In my view, however, it is premature to exclude Mr Gillingham’s supplementary evidence at this preliminary stage. On its face, most of his supplementary brief, which is fairly brief (two and a half pages) appears to be of an updating nature. It may well be that all or most of his evidence is irrelevant, as Mr Mills submits. The Court will be in a better position to assess the relevance of his evidence, however, at trial, when it is able to be considered in a broader evidential context.
[54] If the proposed evidence is relevant it would not be in the interests of justice to exclude it at this stage. I therefore propose to provisionally admit Mr Gillingham’s supplementary evidence, on the basis that the matter can be further reviewed as the trial proceeds. If the evidence indeed proves to be irrelevant, as Mr Mills submits, then no prejudice will result from its provisional admission. I am not willing to exclude the possibility at this preliminary stage that Mr Gillingham’s evidence may prove to be relevant on the basis of the existing pleading, once the full factual context is before the Court.
Result
[55] I order as follows:
(a) The plaintiffs are granted leave to discontinue their claims against the first, second, third, fourth, fifth, eighth and ninth defendants on or about 9 August 2011, save that the first to fifth defendants are to remain parties to the proceedings for the purposes of SML’s cross claims. Any current pleadings relating to the plaintiffs’ claims against the first to fifth defendants are to remain on foot to the extent necessary to enable the relevant parties to either pursue or defend SML’s cross claims against the first to fifth defendants.
(b) Leave is granted to file a 10th amended statement of claim in the form
annexed to counsel for the plaintiffs’ memorandum dated 24 July
2014, save for the proposed amendments at [49], [51](b), [51]
particular (i) and [57] of that document.
(c) Leave is granted to adduce supplementary evidence from Peter Gillingham in the form of his draft supplementary brief, on a provisional basis. The admissibility of that evidence will be further reviewed as the trial proceeds.
(d)Leave to adduce supplementary evidence from Matthew Taylor on stigma issues is declined. Leave is granted to adduce the other evidence included in his draft supplementary brief.
(e) Leave is granted to adduce supplementary evidence from
Kristian Roussow in the form of his draft supplementary brief.
(f) Costs are reserved, for determination together with substantive costs
issues at the conclusion of trial.
Katz J
- AGLC
- Body Corporate 325261 v McDonough [2014] NZHC 1821
- Case
- [2014] NZHC 1821
- Decision Date
CaseChat Overview and Summary
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.