Zhang & Yuan v Koh (Civil Disputes)

Link copied
Case Copied 11 min read

ACT CIVIL & ADMINISTRATIVE TRIBUNAL

ZHANG & YUAN v KOH (Civil Disputes) [2010] ACAT 6

AA 31 of 2009

Catchwords:             CIVIL DISPUTES – Dividing Fences – substandard fence – built by landowner – fence removed and replaced – whether fence should face in a particular direction – no order as to costs of applications

Legislation:               ACT Civil and Administrative Tribunal Act 2008 (ACT)
  Common Boundaries Act 1981 (ACT)

Tribunal:       Mr C.G. Chenoweth   Acting Presidential Member

Date of Orders:  10 February 2010
Date of Reasons for Decision:         10 February 2010

AUSTRALIAN CAPITAL TERRITORY            )
CIVIL & ADMINISTRATIVE TRIBUNAL       )          AA 31 of 2009

BETWEEN:                   MICHAEL ZHANG
  & LUCY YUAN

Appellants

AND:  YOUNG KOH
  & SUZANNE KOH

Respondents

TRIBUNAL:Mr C.G. Chenoweth

DATE:  10 February 2010

ORDER

  1. That the appeal be heard as a new application under section 82 (a).

  1. That neither party is to make any further payment to the other and that there be no order as to costs under section 48 of the ACT Civil and Administrative Tribunal Act 2008 (ACT) in favour of either party.

  1. That the respondents are to complete within 3 months from the date of this order and at their expense a retaining wall where excavation has occurred adjacent to the dividing fence on their property, sufficient to prevent erosion from the appellant’s property onto the respondent’s property.

…………………………….
  Mr C.G. Chenoweth
Acting Presidential Member

REASONS FOR DECISION



  1. This is an appeal from a decision of the Senior Member Lennard dated 11 November 2009. The order directed that the appellants pay to the respondents the sum of $884.40, made up of costs of hearing of $132, and $752.40 being compensation for the costs of the construction of a fence. The order also directed that each of the parties was to contribute one half of the cost of construction of the remaining section of a retaining wall, on the respondents’ side of the common fence.

  1. The appeal follows a number of conferences and hearings in the tribunal relating to the construction of different parts of a dividing fence and a retaining wall between two adjacent properties. The appellants own and rent out one of those properties, and the respondents own and live in the adjacent property. The dividing fence runs between the back fence of the properties to a garage.

  1. In these reasons I refer to the portion of the fence running from the back fence to the midpoint as ‘the back fence half’ and the section from the midpoint to the garage as ‘the garage half’. The side of the fence with the vertical palings is referred to as ‘the smooth side’, and the other side with the posts and horizontal rails as ‘the post-side.’

  1. The properties which have led to this acrimonious dispute between the parties are in a newly developed area of Canberra suburbs. The houses in the street have all been constructed at about the same time, and accordingly the dividing fences have also been constructed within a reasonably short period.

  1. The…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Zhang & Yuan v Koh (Civil Disputes) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] ACAT 6
Decision Date

CaseChat Overview and Summary

In Zhang & Yuan v Koh, the appellants, Zhang and Yuan, sought a review of a decision made by the ACT Civil and Administrative Tribunal. The respondents, Koh, had been found liable for causing erosion to the appellants' property due to excavation activities. The dispute centred on the scope of the Tribunal's decision and whether it adequately addressed the issue of erosion and the necessary remedial works.

The primary legal issues were whether the appeal should be treated as a new application under section 82 (a) of the relevant legislation and whether the Tribunal's decision correctly identified the steps needed to prevent future erosion. Additionally, the court needed to consider the costs implications of the appeal and the necessity of the retaining wall construction.

The court determined that the appeal should indeed be heard as a new application, allowing for a fresh assessment of the evidence and arguments presented. It found that the Tribunal's decision did not sufficiently address the erosion issue, and thus, the respondents were required to construct a retaining wall within three months to prevent further erosion. The court also ruled that neither party should incur additional costs for the appeal, and no costs order would be made in favour of either party.

Orders

Orders of the court

1.

That the appeal be heard as a new application under section 82 (a).

2.

That neither party is to make any further payment to the other and that there be no order as to costs under section 48 of the ACT Civil and Administrative Tribunal Act 2008 (ACT) in favour of either party.

3.

That the respondents are to complete within 3 months from the date of this order and at their expense a retaining wall where excavation has occurred adjacent to the dividing fence on their property, sufficient to prevent erosion from the appellant’s property onto the respondent’s property.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established