Zenmak Pty Ltd & Zenonos v Moreton Bay Regional Council
[2010] QPEC 13
•05/02/2010
[2010] QPEC 13
PLANNING AND ENVIRONMENT COURT
JUDGE ROBIN QC
P & E No 90 of 2010
| ZENMAK PTY LTD AND CHRISTOPHER ZENONOS | Plaintiff |
| and | |
| MORETON BAY REGIONAL COUNCIL | Respondent |
BRISBANE
..DATE 05/02/2010
..ORDER
CATCHWORDS
Integrated Planning Act 1997 s 3.5.21, s 3.5.22(1), s 3.5.23(11), s 4.1.5A, s 4.1.55
Developer request for extension of development approval out of time (i.e. after it had "lapsed") - developer did not regard Council refusal to process request as "written notice of the decision" - Council did not meet request for a "formal notification" on basis of which an appeal could be instituted - extension of time for appeal granted - request granted - extension of time for appeal allowed
HIS HONOUR: The Court makes an order in terms of the
initialled draft.
The appellants, or one of them, purchased land the subject
of a development approval for material change of use in
respect of a five storey building at Scarborough to contain
21 units.
The currency period, the traditional four year one, was to
expire in May 2008.
Some steps were taken by the appellants after their
acquisition of the property to make use of the approval; for
example, application was made for a development permit for
operational works - but nothing substantial has been done.
Application was made in the proper way for an extension of the
currency period which was granted by the council with a new
closing date of 11 May 2009.
By this stage the appellants' interest in proceeding with the
development waned and it was determined to sell the property.
Difficulties have arisen in that process and negotiations are
currently underway with a third potential purchaser. Two
earlier purchasers went to contract but difficulties arose
which apparently culminated in litigation.
The Court accepts the evidence of Mr Zenonos, the principal of
the appellant company, that these matters distracted him from
attending to getting the currency period further extended.
It's surprising that this might have been the case. Section 3.5.22(1) of the Integrated Planning Act 1997 (IPA) requires a request for extension to be made before a development approval lapses under s 3.5.21.
The second of the purchasers, understandably interested, as
the potential purchaser in negotiations is, in having the benefit of the development approval, made inquiries of council to ascertain that the approval had lapsed which information was communicated to the appellants.
They promptly requested the council to extend time and
received a response by letter of 23 September 2009 which
referred to council having previously extended the currency
period under section 3.5.23 of the IPA. It was noted that the
current request for further extension had been received by
council on 8 September 2009:
"There is no provision within the Act to allow council to
reinstate the permit once it has lapsed.
You are therefore advised the request is unable to be
processed as the permit is no longer valid. A full refund of
the application fees submitted with the application will be
lodged in due course".
Understandably, the view was taken, as I accept, that the
application was in a kind of limbo. The appellants engaged
new solicitors, those now acting, who wrote to the council on
19 November 2009 in reference to the council's letter
requesting that "council formally provide notice under
section 3.5.23 of IPA refusing the request for extension of
the relevant period made on 7 September 2009 on the limited
grounds the request was not made during the currency of the
development approval. My client would then appeal the
decision pursuant to section 4.1.30(1)(a) of the IPA". Section 3.5.23(11) requires written notice of the decision to be given to the maker of the request for extension. Section 4.1.30 confers a right of appeal on a person who has received such a notice. The letter went on to foreshadow an application to the Court following council's entry of appearance in the appeal to act under section 4.1.5A of IPA to excuse the failure to comply with the IPA requirement to lodge the request during the currency of the relevant development approval. A copy of the decision in Brisbane Land Pty Ltd v. Pine Rivers Shire Council [2007] QPEC 126, which is in point, was provided to the council as part of this communication.
The response was some time in coming, arriving at an
inconvenient time of the year, 22 December 2009 at 4.46 p.m.. The writer's advice to Mr Timbs, the solicitor now looking after the appellants' interests was, "I have checked with council's legal services and confirmed that the letter council sent to you on 23 December 2009 should be sufficient to commence proceedings to seek relief from the Court under section 4.1.5A."
Unfortunately for the appellants, they were left without the
anticipated formal decision which might have set the appeal
period running, though plainly too late, if the date which set
the period running was identified by reference to the
council's letter of 23 September 2009. Thus, not only the
Brisbane Land indulgence is necessary but an indulgence in
respect of the time for institution of the appeal.
The discussion of the topic of longer times being allowed for
appeal under section 4.1.55 in Fogg Meurling and Hodgetts,
Planning and Development Queensland is helpful. It indicates
that extensions of time are not to be granted simply for the
asking. Circumstances rendering the allowing of additional
time appropriate have to be established.
It seems to me, and for obvious reasons, that extensions may
be more readily granted to developers desiring to proceed who
have committed themselves to trouble and expenditure in respect of their proposals than to adverse submitters who, the cases show, often have trouble in getting additional time. The high water mark in special circumstances in Butler v Kingaroy Shire Council [2006] QPELR 10 (considered in Rynah Pty Ltd v Gold Coast City Council [2006] QPEC 104) was a siz month extension granted to a developer.
In my opinion, the circumstances of the appellants here are
sufficient to justify the Court's acting under section 4.1.55.
Some significant matters apart from the arguable inadequacy of
the “written notice” require from the Council, include that
the development proposal was an impact assessable one which went through public notification attracting no submissions. It would not be attractive to the appellants to have to start all over again and with an impact assessable development application to suit the wishes or expectations of the purchaser with whom they're in negotiations, it may well not be inclined to wait.
At the time of the extension of the currency period referred
to above the latest amendments to the council's planning
scheme had come into effect. It's significant to note that at
that point the council regarded the development as a suitable
one for the area. Mr Skoien, representing it, confirms that
such is still its attitude today and there's indeed in the material before the Court a letter of the council of 13th of November 2009 which confirms that the council would raise no objection should the appellants seek a declaration to grant a further extension of time "as the approval was not out of
character with existing development in the area, nor the
current unconstructed development approvals."
The section 4.1.5A relief should be granted on the same basis
as it was in Brisbane Land. Public notification of the
“suitable” proposal occurred; no “opportunity” referred to in
subsection (11)(b) has been restricted. We're in the
fortunate situation of being able to resolve the matter and spare the parties the need for further steps to be taken in the Court by the appeal being allowed at this stage, given the council's approach.
I might conclude by mentioning that the matter has been dealt
with on the basis that the Intergrated Planning Act 1997
applies. Should it be the case that section 820 of the
Sustainable Planning Act 2009 is the relevant provision, it
would be clear that the appellants' task of obtaining the
indulgences sought would be much easier, certainly not more
difficult.
Does that cover everything?
MR SKOIEN: Thank you, your Honour.
MR HUGHES: Thank you, your Honour.
------
0
2
0