[2007] QPEC 126
PLANNING AND ENVIRONMENT COURT
JUDGE ROBIN QC
No 1434 of 2007
| BRISBANE LAND PTY LTD | Appellant |
| and | |
| PINE RIVERS SHIRE COUNCIL | Respondent |
| BRISBANE ..DATE 10/09/2007 | |
| ORDER |
CATCHWORDS: Integrated Planning Act 1997 s 3.5.21, s 3.5.22, s 4.1.5A - where development approval lapsed at expiration of the "relevant period" (currency period) - whether timely
written notice "before approval lapses" of an extension being
asked is a "requirement of the Act" held that there was a
discretion to extend time where such notice was given late and
that it should be exercised favourably
HIS HONOUR: This application within the underlying appeal
1
against the Council's refusal of its "Request to Extend [a]
Currency Period of [a] Development Permit" seeks relief under
section 4.1.5A of the Integrated Planning Act 1997 by way of
an extension of time for giving written notice by such a
| request. The applicant is in the embarrassing situation of | 10 |
| its development permit having lapsed under section 3.5.21 of the Act: | |
| " | 3.5.21 When approval lapses if development not started |
(1) To the extent a development approval is for a 20 material change of use of premises, the approval
lapses if the first change of use under the approval
does not happen within the following period (therelevant period)-
(a) 4 years starting the day the approval takes
effect; or
(b) if the approval states a different period from
when the approval takes effect - the stated 30 period.
2. To the extent a development approval is for
reconfiguring a lot, the approval lapses if a plan
for the reconfiguration is not given to the local
government under section 3.7.2(2) within thefollowing period (also the relevant period)-
(a) for reconfiguration not requiring operational
works - 2 years starting the day the approval 40 takes effect;
(b) for reconfiguration requiring operational works
- 4 years starting the day the approval takes
effect;
(c) if the approval states a different period from
when the approval takes effect - the stated
period.
50
3. To the extent a development approval is for development other than a material change of use of premises or reconfiguring a lot, the approval lapses if the development does not substantially start within the following period (also the relevant period)-
2 ORDER 60
(a) 2 years starting the day the approval takes
effect; 1 (b) if the approval states a different period from
when the approval takes effect - the stated
period.
(4) Despite subsections (1) and (2), if there is 1 or
more related approvals for a development approval
mentioned in subsection (1) and (2), the relevant 10 period is taken to have started on the day the
latest related approval takes effect.
(5) If a monetary security has been given in relation to
any development approval, the security must be
released if the approval lapses under this section.
(6) The lapsing of a development approval for a material change of use of premises or reconfiguring a lot
does not…
Keep reading for free
Create a free CaseChat account to read Brisbane Land Pty Ltd v Pine Rivers Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2007] QPEC 126
- Decision Date
CaseChat Overview and Summary
The primary issue for the court was whether the late submission of the written notice should prevent the court from exercising its discretion under section 4.1.5A of the Integrated Planning Act 1997. The court considered the decision of the Court of Appeal in Lamb v Brisbane City Council [2007] QCA 149, which held that there must be a requirement of the Act to avail the court of the discretion under section 4.1.5A. The court found that the decision in Lamb did not preclude the court from exercising its discretion under section 4.1.5A in the present case. The court held that the provisions in the Act, including section 3.5.21, serve a useful purpose and that the Council was supportive of the development. The court found that the late submission of the written notice should not prevent the court from exercising its discretion under section 4.1.5A.
The court found that the appellant's development permit had lapsed due to the late submission of the written notice, but the court exercised its discretion under section 4.1.5A of the Integrated Planning Act 1997 to extend the time for giving written notice as required by section 3.5.22(1) of the Act. The court ordered that the time for giving written notice be extended to seven days after the date of the order and granted liberty to apply.
In summary, the court held that the late submission of the written notice should not prevent the court from exercising its discretion under section 4.1.5A of the Integrated Planning Act 1997, and the court exercised its discretion to extend the time for giving written notice. The court's order granted the appellant's application for an extension of time for giving written notice and granted liberty to apply.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi