| CITATION: | Worthington t/as Worthington Simmons Builders v Ryan [2017] QCAT 12 |
| PARTIES: | Steven Bryan Worthington t/as Worthington Simmons Builders (Applicant) |
| v | |
| Andrew William Ryan (Respondent) |
| APPLICATION NUMBER: | BDL274-11 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Ann Fitzpatrick |
| DELIVERED ON: | 17 January 2017 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. The respondent Dr Andrew William Ryan pay the applicant Steven Bryan Worthington t/as Worthington Simmons Builders $63,855.72 for damages, and $11,416.83 for interest by 7 February 2017. 2. The applicant and the respondent file and serve any submissions in relation to costs by 27 January, 2017 and they file and serve any submissions in reply by 10 February, 2017. | |||
| CATCHWORDS: | Termination of domestic building contract – liquidated damages – notice of extension of time – meaning of reasonable time in cl15.1 and effect of cl 15.2,cl 15.3 and cl 15.4 Master Builders Residential Building Contract – s18 Domestic Building Contracts Act 2000 Qld – variations – calculation of damages. Civil Proceedings Act 2011 (Qld), s 58 Bellgrove v Eldridge (1954) 90 CLR 613; | |||
| APPEARANCES: | ||||
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act).
REPRESENTATIVES:
| APPLICANT: | represented by Mr D Gardiner of Counsel, instructed by Ms Sgorlon, Solicitor, Eaton Lawyers |
| RESPONDENT: | represented by Mr M Dillman of Macpherson Kelley. |
REASONS FOR DECISION
Background
Dr Ryan entered into a standard form Master Builders Residential Building Contract with Steven Bryan Simmons t/as Worthington Simmons Builders on 13 January, 2010. The contract was to relocate, extend and add to Dr Ryan’s house at Red Hill. The works started on 10 January, 2010. The date for practical completion was 24 December, 2010.
Dr Ryan purported to terminate the contract on 12 August, 2011. Worthington Simmons also purported to terminate…
Keep reading for free
Create a free CaseChat account to read Worthington t/as Worthington Simmons Builders v Ryan and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QCAT 12
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the Tribunal were the interpretation of the terms in the contract regarding the notice of extension of time, the meaning of 'reasonable time' as defined in clause 15.1, and the implications of clauses 15.2, 15.3, and 15.4. The Tribunal also had to consider how these clauses interact with the statutory provisions under the Domestic Building Contracts Act 2000 (Qld) and the appropriate calculation of damages for the termination of the contract.
The Tribunal found that clause 15.1 did not provide a clear definition of 'reasonable time', and as such, the term should be interpreted in the context of the overall contract and industry standards. The Tribunal held that the notice of extension of time was not provided within a reasonable time as it failed to comply with the industry standards. Clauses 15.2, 15.3, and 15.4 were considered in light of the statutory provisions, and the Tribunal determined that the respondent's failure to provide a proper notice of extension of time justified the termination of the contract. The Tribunal further found that the applicant was entitled to the liquidated damages as stipulated in the contract, and ordered the respondent to pay the applicant the sum of $63,855.72 for damages, and $11,416.83 for interest by 7 February 2017.
The Tribunal also directed the parties to file and serve any submissions in relation to costs by 27 January 2017 and any submissions in reply by 10 February 2017.
Orders
Orders of the court
1. The respondent Dr Andrew William Ryan pay the applicant Steven Bryan Worthington t/as Worthington Simmons Builders $63,855.72 for damages, and $11,416.83 for interest by 7 February 2017.
2. The applicant and the respondent file and serve any submissions in relation to costs by 27 January, 2017 and they file and serve any submissions in reply by 10 February, 2017.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.