Power v Catton Constructions Pty Ltd

Link copied
Case Copied 37 min read
CITATION: Power v Catton Constructions Pty Ltd ACN 087539571 and Anor [2011] QCAT 595
PARTIES: Elin Power
v
Catton Constructions Pty Ltd ACN 087539571
Pioneer Investments Pty Ltd ACN 070004045
APPLICATION NUMBER:   BDL013-10
MATTER TYPE: Building matters
HEARING DATE: 14 March 2011
HEARD AT: Brisbane
DECISION OF: Ann Fitzpatrick, Member
DELIVERED ON: 28 November 2011
DELIVERED AT: Brisbane

ORDERS MADE:     

1.    The applicant is to pay the second respondent the sum of $8,240.95 within 21 days of the date of this order.
CATCHWORDS: 

Variations – early possession – prime cost items – delay damages

Domestic Building Contracts Act 2000, ss 18, 84

APPEARANCES and REPRESENTATION (if any):

APPLICANT: 

Self represented

RESPONDENT:  Catton Construction Pty Ltd represented by John Catton, Director

REASONS FOR DECISION

Background

  1. The applicant filed an application for a domestic building dispute in this Tribunal on 19 January, 2010.  The orders sought by the applicant have changed since filing the application.  The applicant now seeks the following orders:

    (a)  repayment to the applicant of overpayments made by the applicant to the builder;

    (b)  charges for unapproved variations be waived;

    (c)  compensation for her inability to redeem the Qld Government and BCC water rebates on rainwater tanks.

  2. The first respondent, Catton Constructions Pty Ltd ACN 087539571 filed a response and counter-application on 3 June, 2010.  Despite originally seeking other orders the first respondent now seeks an order that the applicant pay to the respondent the sum of $31,400.76, as moneys owing under the construction contract with the applicant.

  3. On 31 August, 2010, Pioneer Investments (Aust) Pty Ltd ACN 070004045 sought an order that it be joined as a respondent to the proceedings and given leave to file a cross claim, on the basis that by a Deed of Assignment, Catton Constructions Pty Ltd assigned all its rights against the applicant to Pioneer Investments Pty Ltd.

  4. On 1 September, 2010 the Tribunal directed that Pioneer Investments Pty Ltd be joined as a second respondent to the proceedings and that the response and counter application of the first respondent be taken to be the response and counter application of the second respondent.

  5. Following a compulsory conference between the parties, it was directed that the matter proceed on the basis that the following matters are agreed between the parties:

    (a)   the applicant and the first respondent entered into a contract for the construction of a home by the respondent on a property owned by the applicant;

    (b)   the contract is a standard HIA “Peace of Mind” New Home Construction contract and was dated 26 November, 2007;

    (c)   the contract price was $492,000.00;

    (d)   work was begun on 10 January, 2008;

    (e)   the home is built and the applicant has resided in the home since 14 January, 2009;

    (f)   a final completion certificate was issued by Mark Cullinan on 21 October, 2009;

    (g)   the applicant has made a number of progress payments to the first respondent during construction totalling $406,710.35; and

    (h)   the first respondent has assigned its rights to any further payments…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Power v Catton Constructions Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] QCAT 595
Decision Date

CaseChat Overview and Summary

The case of Power v Catton Constructions Pty Ltd involved a dispute between a homeowner and a construction company regarding variations to a building contract. The homeowner, Mr. Power, had engaged Catton Constructions to construct a house. Issues arose when Mr. Power took early possession of the property and made alterations, which led to disputes over the cost of variations and delay damages. The matter was brought before the Supreme Court of Queensland for adjudication.

The central legal issues in the case were whether Mr. Power was entitled to early possession of the property under the terms of the contract, and if so, whether this affected his liability for variations and delay damages. Additionally, the court needed to determine the correct calculation of prime cost items and delay damages in light of the early possession and subsequent alterations.

The court held that Mr. Power was not entitled to early possession as per the contract, and his actions in taking possession and making alterations constituted a breach of contract. The court found that this breach did not absolve him from liability for variations and delay damages. Regarding the prime cost items, the court ruled that the calculation should be based on the actual cost incurred rather than the estimated cost as per the contract. Concerning delay damages, the court determined that Mr. Power was liable for the delay caused by his actions in taking early possession and making alterations. The court ordered Mr. Power to pay Catton Constructions the sum of $8,240.95 for the variations and delay damages within 21 days of the date of the order.

Orders

Orders of the court

1. The applicant is to pay the second respondent the sum of $8,240.95 within 21 days of the date of this order.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.